PROJECT S-CURVE

PT. TRIGUNA INTERNUSA PRATAMA


JASA SEWA GAS PROCESSING FACILITY KAPASITAS 45 MMSCFD
NO. TENDER : 5188-369-PGE
DOKUMEN NO: TIP-AGPF-GN-CHT-00-003 | REVISI: A
WEIGHT YEAR 2023 / 2024
NO WORK DESCRIPTIONS FACTOR SCALE REMAKS
M-01 M-02 M-03 M-04 M-05 M-06 M-07 M-08 M-09 M-10 M-11 M-12 M-13 M-14
(%AGE)
A PROJECT MASTER SCHEDULE
100%
1 CONTRACT AWARD
2 PREPARATION FACILITIES 4,242% 4,242%
3 DETAILED ENGINEERING DESIGN
3.1 ISBL Scope 2,517% 0,629% 1,888%
3.2 OSBL Scope 1,677% 0,419% 1,006% 0,252% 75%
3.3 Civil & Structure 0,560% 0,084% 0,224% 0,168% 0,084%
4 PROCUREMENT
4.1 ISBL Scope 37,751% 0,755% 0,755% 0,755% 3,775% 5,285% 13,213% 13,213%
4.2 OSBL Scope 23,482% 0,470% 0,470% 0,704% 1,644% 1,879% 1,879% 4,109% 4,109% 4,109% 4,109%
50%
4.3 Civil & Structure 3,917% 0,588% 1,567% 1,175% 0,588%
5 CONSTRUCTION & INSTALLATION
5.1 ISBL Scope 10,067% 3,356% 3,356% 3,356%
5.2 OSBL Scope 8,386% 1,048% 1,048% 1,048% 1,048% 1,048% 1,048% 1,048% 1,048%
5.3 Civil & Structure 6,716% 0,839% 0,839% 0,839% 0,839% 0,839% 0,839% 0,839% 0,839% 25%
6 COMMISSIONING
6.1 Commissioning & Start-up 0,468% 0,312% 0,156%
6.2 Trial Operation 0,216% 0,216%
7 ON STREAM 0%

INCREMENTAL PROGRESS PLAN: 7,439% 5,770% 4,285% 7,518% 9,639% 16,979% 19,210% 9,353% 8,513% 8,513% 1,048% 1,048% 0,312% 0,372%
100,00%
CUMULATIVE PROGRESS PLAN: 7,439% 13,208% 17,494% 25,011% 34,650% 51,630% 70,840% 80,192% 88,706% 97,219% 98,267% 99,316% 99,628% 100,000%

ISSUED FOR TENDER Page 1 of 1 TIP-AGPF-GN-CHT-00-003 | REVISI: A