1.0 Introduction:
This Report has been designed to submit to the Council of the Institution of Engineers Sri
Lanka (IESL) for the 2016 March Professional Review. This Report highlights how I have
attained the relevant Standard of Education, Training, Experience, and Competences
required by the council of the IESL to testify my Civil Engineering Proficiency as a Charted
Engineer. I have realized that unless qualifying as a Charted Engineer, it is impossible to
achieve my career objectives.
Soon after the completion of Final Examination in Engineering Part III, I got an appointment
as an Instructor at Faculty of Engineering, University of Peradeniya. Before I resigned from
the post I had served about five months in Geotechnical Laboratory.
In the next as a fresh graduate, I joined with a Contractor (M/S V.V. Ramanathan Company
(Pvt) Ltd) at Vavuniya in September, 2005 as a Site Engineer in the construction of Vavuniya
Study Centre, Open University of Sri Lanka. Due to abnormal situation prevailed in the
country at that time; I was unable to continue in that more than three months. But, within a
short span of time I could make a substantial progress starting from setting out of Grid Lines
to completion up to DPC and columns up to first storey level. A similarity happened again
when I joined at District Secretariat, Kilinochchi in November, 2005 as a Civil Engineer (On
contract basis).Before I left from the post, I could serve about four months.
10
IESL Professional Review- March 2016 AM 13779
After returning to Sri Lanka in 2011, I worked with Squire Mech Engineering (Pvt) Ltd. &
Department of Buildings (Northern Province) at several major projects in the capacities of
Site Engineer & Project Engineer (Deputy Project Manager) respectively before I joined with
Irrigation Department through the appointment of Engineering Service board (ESB) of
Sri Lanka on 15th of May, 2012.
Since I joined the Irrigation Department, I was posted to Irrigation Training Institute (ITI),
Galgamuwa, where Engineering Assistants of the Department are mould, in the capacity of
Irrigation Engineer (IE). And from 15th January, 2013, I was given an additional post of
Additional Divisional Irrigation Engineer (Addl. DIE), Galgamuwa. I continued in these two
posts until I was transferred to Office of the Director of Irrigation, Vavuniya on 11 th of
February, 2015.
From February, 2015 to date, I continue to serve at the Office of the Director of Irrigation,
Vavuniya in the post Irrigation Engineer.
Not only I was merely successful in the Professional Review Examination Aug / Sept- 2014
“The Engineer in Society” – Section ‘B’ Paper, but also it changed my attitudes towards the
Engineering profession substantially.
In addition I keep myself updating by reading Civil Engineering Books, Manuals, Codes, etc.
To emerge as a Leading Project Manager capable of handling complicated major projects,
being qualified for making influence in the technical and management aspects, and being
equipped with relevant computer software applications are my Career Objectives.
Table 2.1: Details of Recognized Training prior to the Graduation Total 5 months
Eng.
V.Devarajan,
Department B.Sc.,C.Eng.,
of Buildings, Chief
07 th
28th
Trainee
Northern 2.5 Engineer,
Oct,2002 Dec,2002 Engineer
Division, Northern
Jaffna. Division,
Buildings
Dept, Jaffna.
Mr. D.
Sriyantha I.
Punchihewa,
Site
Construction
Engineer,
Engineering 29th 19th Trainee
2.5 Municipal
Company Sep,2003 Dec,2003 Engineer
Dispensary
(Pvt) Ltd.
Site,
Elvitigala
Mawatha,
Colombo-08
Table 2.2: Details of Recognized Training after the Graduation Total 36.5 months
Work of the
Certifying
Duration Officer
From To
(Months)
Mr. S.
District Thayaparasivam
15th 14th Civil
Secretariat, 4.0
Nov,2005 Mar,2006 Engineer District Engineer,
Killinochchi
Killinochchi
United
Eng . N.
Nations
Suntharamoorthy,
Office for
31st 30th Site B.Sc(Eng).,
Project 15.0
June,2006 Sept,2007 Engineer C.Eng., Senior
Services
Site Engineer,
(UNOPS) -
UNOPS, Jaffna.
Jaffna
Er Chan Chee
Structural Choon
Castello 06th 28th
6.5 Design Professional
Consultant Mar,2008 Sep,2008
Engineer Engineer,
Singapore
Eng. S.
Office of the Kumarathevan
Irrigation
Director of 11th 15th
6.0 Engineer Director of
Irrigation, Feb,2015 Aug,2015
(Designs) Irrigation,
Vavuniya
Vavuniya
of the
Certifyin
Duration
From To g Officer
(Months)
ENGINEERS
Er. Lee Mow
PARTNERSHI
Woo
P
B.Sc.,M.Eng.,P.E
Civil & 27th Structura
ng.,
Structural 29th
l Design
Mar,201 18.0 C.Eng.,M.I.E.S.,
Consultants Sep,2008 Engineer
0 M.I.E.M.,M.I.E.A
No:28-14 (General)
ust. M.I.Struct.E.,
International
Accredited
Plaza, 10
Checker
Anson Road
WRX
CONSULTAN
TS 221, Er. William Wu
Henderson Ruixin,
Road, Director
No: 04-09 21st 10th Civil
6.5 B.Sc.,M.Eng.,
Henderson Jun,2010 Jan,2011 Engineer
M.B.A., P.Eng.,
Building, C.Eng.,M.I.E.S.,
Singapore M.I.Struct.E.,
159557
Squire Mech
Engineering
(Pvt) Ltd.
14
IESL Professional Review- March 2016 AM 13779
(Northern
Province),
Killinochchi
Eng. A.
Gunasekara
B.Sc(Eng)., C.Eng
15th
14th Irrigation Director of
May,201 8.0
Jan,2013 Engineer Irrigation
2
Training Institute
(ITI),
Irrigation
Galgamuwa.
Training
Institute, Eng. H.G.M.
Galgamuwa Kulasinghe
B.Sc(Eng)., C.Eng
Director of
15th 10th Irrigation
25.0 Irrigation,
Jan,2013 Feb,2015 Engineer
Irrigation
Training Institute
(ITI),
Galgamuwa
Eng. S.
Office of the Kumarathevan
15th
Director of Irrigation B.Sc(Eng)., C.Eng
Aug,201 To date 5.0
Irrigation, Engineer Director of
5
Vavuniya Irrigation,
Vavuniya
Table 2.4: Details of Recognized Training and Responsible Experience Total 36.5 months
15
IESL Professional Review- March 2016 AM 13779
of the
Duration
From To Certifyin
(Months)
g Officer
ENGINEERS
PARTNERSHI
P
Civil &
Er. Lee Mow Woo
Structural Structur
B.Sc.,M.Eng.,P.En
Consultants al
g.,
No:28-14 27th Design
29th C.Eng.,M.I.E.S.,
International 18.0 Enginee
Sep,2008 Mar,2010 M.I.E.M.,M.I.E.Au
Plaza, 10 r
st. M.I.Struct.E.,
Anson Road (General
Accredited
)
Checker
WRX
CONSULTAN
TS 221, Er. Wu Ruixin
Henderson Director
Civil
Road, 21st 10th B.Sc.,M.Eng.,
6.5 Enginee
No: 04-09 Jun,2010 Jan,2011 M.B.A., P.Eng.,
r
Henderson C.Eng.,M.I.E.S.,
Building, M.I.Struct.E.,
Singapore
159557
Engineers &
16
IESL Professional Review- March 2016 AM 13779
Contractors
No.135/1, Old
Kottawa Road,
Nawinna,
Maharagama
Project
Enginee
Department of Eng. S.
11th 14th r
Buildings Suntharakumar
Nov,201 May,201 6.0 (Deputy
(Northern B.Sc., C.Eng
1 2 Project
Province) Chief Engineer
Manager
)
Irrigatio Eng. A.
15 th
Gunasekara
10th n
May,201 32.0 B.Sc(Eng)., C.Eng
Irrigation Feb,2015 Enginee
2
Training r
Institute,
Irrigatio
Galgamuwa 15th Eng. H.G.M.
10 th
n
May,201 32.0 Kulasinghe
Feb,2015 Enginee
2 B.Sc(Eng)., C.Eng
r
Additio
nal Eng. B.A.S.S.
Divisional
Division Perera B.Sc(Eng).,
Irrigation
15th 10th al C.Eng Director of
Engineer’s 25.0
Jan,2013 Feb,2015 Irrigatio Irrigation,
Office,
n Kurunagella
Galgamuwa
Enginee Range
r
Eng. S.
Office of the Irrigatio Kumarathevan
15th
Director of n B.Sc(Eng)., C.Eng
Aug,201 To date 5.0
Irrigation, Enginee Director of
5
Vavuniya r Irrigation,
Vavuniya
17
IESL Professional Review- March 2016 AM 13779
18
IESL Professional Review- March 2016 AM 13779
I successfully followed four years full time Engineering Degree Course at Faculty of
Engineering, University of Peradeniya from January, 2001 to February, 2005. I obtained
19
IESL Professional Review- March 2016 AM 13779
Category : Construction
Major portion of my training period engaged with the construction of first storey slab while
other works were going parallel.
Site Engineer guided me to perform following works and then I had completed those to the
satisfaction of them.
1. Checking Reinforcement of Columns, Beams, & Slab, Reporting to the Site Engineer and
Getting rectified the problems.
During Reinforcement checking, I had inspected following items & made rectified if
necessary.
Appropriate Drawing referred
Sizes of Reinforcement
Required Shape
Correct Spacing
Correct Placement & Alignment
Enough Lapping & Anchorage
Required Cover for Reinforcement
Position and size of cover blocks
2. Checking Formworks of Columns, Beams, & Slabs. While checking Formworks, I had
inspected following items and made rectified if needed.
Required Size as per relevant drawings
Checked the Stability
Quality of forms
Setting out and Alignment
Vertical alignment of Column formworks
20
IESL Professional Review- March 2016 AM 13779
21
IESL Professional Review- March 2016 AM 13779
Made construction joints clean and made sure good bond between hardened and fresh
Concrete surfaces at appropriate places.
Standing at Site, I made sure proper compaction of concrete, by directing use of Poker
Vibrators. I explained and demonstrated the workers how to use the Poker Vibrator to
compact the Concrete placed.
I took immediate stringent actions to cover gaps or leaks in formworks if formed during
Concreting.
I was monitoring the Finishing Level of Concrete appropriately by using Leveling
Instrument.
I took appropriate measures to minimize the effects of Sun and rain.
I coordinated and made sure that Curing for a minimum period of 7 days.
In addition to the above tasks described above, I had attended other works assigned by the
Site Engineer time to time during my General Industrial Training period.
Bii
Given Tasks and Performance
B
1. Setting out of Columns
Bi
I had set out number of Kicker boxes for Column Shafts. Following sketch describes a case of
example.
A
In this case Columns 2-B, 2-C, 2-D, 3-A, and 3-D were already casted and Column 3-B had to
set out. Sizes of these Columns were similar. At first I set out Grid Line B and Sub Grid Lines
3a and 3b as shown in the sketch above. After checking the accuracy of the Grid Lines, I
marked the outlines of the Column and I made a cross-check by aligning another set of Sub
Grid Lines B-i and B-ii as shown above.
By using appropriate method I set out number columns for satisfaction of the Site Engineer
and Client Engineer.
2. Inspection of Column formworks
Steel moulds were used for casting Columns, following Setting out and Kicker. I had given
instruction to mason that to get the prior consent from me to commence the Column
Formwork. I checked Column rebar and specially Stirrups (Links) prior to setting Formwork
and gave the approval on behalf of the Site Engineer. Grease (Lubricant) was applied on the
internal sides of the mould and after setting the Formwork, I checked the vertical alignment,
stability, gaps or leaks, cover for the reinforcement, and presence of any unwanted materials
get rectified those shortcomings if any. And I reported to the Site Engineer and he reported
to the client Engineer. And after the final checking, Concreting was approved.
23
IESL Professional Review- March 2016 AM 13779
15mm Thk Plywood 50x50mm Reapers @ 100x50mm Joists @ 50mm Steel Props
450 C/C 750 C/C @ 900 C/C
X - Bracing
Base Plate
During the erection of Formwork, I had checked the relevant measurementsFirm andBase
levels and
supervised that whether Sub-Contractor complies with our requirement as agreed. I reported
to Site Engineer if any Figure: 3.2.2detected
deviations (2): Design of Slab
and made to & Beamthose
rectify Formwork
if necessary.
During this period, I demonstrated Soil Mechanics experiments such as Atterberg Limit
Tests, Permeability Tests for 4th semester undergraduates and few other experiments for first
semester under graduates. Also I had contributed to the Geotechnical Design classes.
25
IESL Professional Review- March 2016 AM 13779
f) Attending project meetings with the representatives from local and foreign agencies
I really worked hard and got involved with the project and managed well to the satisfaction
of funding and implementing agencies. But, it was very unfortunate this project had been
abandoned in midway due to the severe escalation of violence in 2006, especially in south
east part of the Jaffna Peninsula where then conflicting parties had their Front Defense Line
(FDL). Nevertheless, this gave me a golden opportunity to work with the foreign
professionals and raised my confident to such a level that “I can work with anyone at
anywhere”. Following the uncertain situation, I was transferred to other project which was
going in the main land of Jaffna peninsula.
2. Water and Sanitation Project for internally displaced people (IDPs) under emergency
relief – a collaborative project between Unicef and Unops; two prominent UN agencies
Throughout this project I had to shoulder multi disciplinary responsibilities to lead the
project under the uncertain situation in Peninsula. My task included collecting requirement
data form 14 Nos of IDPs’ centres throughout Jaffna peninsula and the government
authorities, analyzing those data, writing proposals, making work plan, preparation of
relevant drawings and Estimates for the construction of water and sanitary facilities,
implementation, and monitoring of construction activities, reporting weekly progress and
financial management. Due to various constraints, we had decided to implement this project
by direct and it made me to involve with the United Nation’s procurement procedures
extensively. I could effectively manage procurements without deviating from the procedures
to lead the project comfortably. Following works had been completed under this project.
Construction deep tube wells with hand pumps – 12 Nos
Construction Lavatories- single cabin with septic tank – 25 Nos
Construction of Lavatories with twin cabin and common septic tank – 5 Nos
Construction of Lavatories with multi cabin with common septic tank – 4 Nos
Renovation of Toilets – 40 Nos
Renovation of Wells – 10 Nos
Renovation of water tanks – 6 Nos
Construction water supply systems – 18 Nos
Refurbishment of school buildings – 6 Nos
Construction of bathing places – 25 Nos
Construction of temporary huts – 10 Nos
During this period I had to deal with the public extensively and I realized that there should
be management tactics to manage the public such a way we could get things done
appropriately. In short, I learnt good lessons in many ways from this project which made me
sharper.
3. Construction of 3 Nos. of two storey school buildings at Point Pedro and Karaveddy:
For these projects I was posted as a Project Engineer for overall supervision of the works.
Followings were my key responsibility areas:
Structural Inspection
Quality control
26
IESL Professional Review- March 2016 AM 13779
This was my ever first chance to work with structural design consultant as a Structural
Design Engineer under the guidance of Er. Chan Chee 2.2 m Choon,
Height RC
a Beam
Singapore Professional
Engineer (PE), and Qualified Person (QP) for structural works. I joined this consultants with
much expectation of qualifying in the field of structural design and my expectation became
substantially fulfilled as I worked hard. I used to work more than 12hrs in the office. I RC
madeWall
2nd Floor – RC Floor
significant contribution to the following projects as Structural Design Engineer.
Basement
27
Figure 3.3.3 (1): Structural Framing Layout of MSS Head Quarters Building, Dammam
IESL Professional Review- March 2016 AM 13779
G.L
In the Structural System it was a challenging to design 4 Nos of 9.4m long Cantilever beams
at 3rd storey / Roof level which carries a half of the 1 st and 2nd portion load through RC wall
as shown in figure: 3.3.3(1). The sizes of these beams are 500 X 2200. In this project had
designed and made detailing of the each and every structural element which makes this 4
storey building. These include;
Reinforced Concrete Slabs
Reinforced Concrete Beams
Reinforced Concrete Columns
Staircase (RC)
Reinforced Concrete Walls / Shear walls
Lift Core walls
Basement slabs
Bored Piles and Pile Caps
Reinforced Concrete Retaining walls
Another interesting part was design of basement slab. When I designed the basement I had
to consider two scenarios: water table below the basement level and water table at ground
level. In these two scenarios I had to consider different loading combinations: 1.4 Dead Load
(DL) + 1.6 Live Load (LL) and 1.0 Dead Load + 1.5 Up Lift Pressure (Negative) respectively.
3 m height water table was considered in the design. In addition to the structural workouts, I
made significant contribution in the drafting section as well. This project provided me an
28
IESL Professional Review- March 2016 AM 13779
opportunity to get much familiarized with the British Standard- BS 8110; Code of practice for
structural use of Reinforced Concrete.
Glass front facade design for Orchard Central commercial development – shopping centre
was basically a structural design project which required very good fundamental knowledge
in Structural Engineering. There were numerous applications of Basic Principles of Structural
Engineering. It comprised a variety of designs & detailing. Following sketches illustrate the
similar works. Following design works involved in this project.
Estimation of forces including wind force
Modeling and analysis
Design of Structural glasses
Design of anchor bolt joints
Design of steel frames
Design of steel connections
Design of Stainless Steel members etc
Design Anchor bolts (Hilti)
29
IESL Professional Review- March 2016 AM 13779
Design of Temporary steel supports for erection of mega steel truss at 78, Shenton way.
Actually this project was based on Design of Steel Structures. I had carried out following
design works involved
Figure 3.3.3 with this project.
(3): Example Layout of Glass Facade - Connections
Design of Steel joints
Design of moment connections
Checking of Crane capacity
Checking Capacity of Crane trigger
Crane base
In this six month period, I involved in the following types of designs and Estimation.
Design of Irrigation Canals (Hydraulics and Structural)
Other various Canal Structures
Design of Canal Trough made of steel truss for Irattaperiyakulam main canal across spill
way.
30
IESL Professional Review- March 2016 AM 13779
For design of irrigation canals, I used Manning’s equation for hydraulics design and for
structural design, similar method of designing Reinforced Concrete cantilever retaining wall.
Irataperiyakulam canal Trough design was a solution for a long delayed works and ensured
water issue for 50acs of paddy land which was dependent of water pump. Design of
Concrete road for Pavatkulam bund access road provided a proper design to the standards
and superseded irrational designs earlier proposed. All design calculations for proposed
three storey building was manual since there is no structural analysis software available.
Followings photos were taken at the sites where and when my Concrete pavement design
works were executed.
31
IESL Professional Review- March 2016 AM 13779
In this Civil & Structural Consultants I was working with the guidance of Er. Lee Mow Woo,
Professional Engineer (PE) and Accredit Checker (AC) Singapore. I made a significant
contribution for successful progress and completion of the following projects.
(2) Proposed new erection of 2- blocks 0f 39- storey condominium housing development
(total 623 units), comprising of basement carparks, communal facilities and swimming
pool on lot 16618k MK 18 at Bishan street 22 (Bishan planning area)
(Project cost: 183 millions sing. Dollars)
(3) Proposed public housing development under design, build and sell scheme comprising
the erection of 4 blocks of 30 storey residential flats (578 units), 1 block of precinct
pavilion and 1 block multi -storey car park with electrical substation on lot 16738k MK 18
32
IESL Professional Review- March 2016 AM 13779
(4) Proposed public housing development comprising the erection of 3 blocks of 40 storey
residential flat (total 480 units) with 1 basement carparks on lot 16852m MK 18 Bishan
PH1 at Bishan street 24 (Bishan planning area).
(5) Proposed public housing development comprising 7 blocks of 16 storey residential flats
(total 750 units) with basement car parks, communual facilities & precinct pavilion at
Pungol west contract 3 on lot 2132m Mukim 21 at Pungol place / Pungol field (Pungol
planning area).
Loading calculations.
Frame analysis
Pile design
Column design
Slab design
Flat slab / plate design (using SAFE)
Beam design ( Including Beams with openings & Non – uniform cross section)
Retaining wall design
Pile cap design
Ecc for piles – overstress and pile cap checking
Ecc remedial works (Tie beam, strengthening, enlargement etc…)
Slope stability checking (Using Plaxis software)
Moderate Steel Structures.
Steel connections
Preparation of calculations & structural drawings for BCA submission.
(2) Proposed public housing development comprising 2 blocks of 16 storey and 2 blocks of 16
storey residential buildings (total 867 units) with multi storey car park at Jurong East
NC13 / Jurong East Avenue 1/ Jurong East street 32.
(3) Proposed erection of 3 storey fire station (with 7 storey training tower) & neighborhood
police centre on lots 0221W, 0222V & 0316N TS 30 at Maxwell Rd, Prince Edward Rd
(Downtown planning area).
(4) Proposed industrial development comprising a block of 6 storey multiple- user factory
with mezzanine floor on each storey (total 45 units) and other ancillary facilities on lot
4404M (JTC plot A20 45504) MK 06 at Tanjong Kling / Pioneer crescent (power planning
area)
33
IESL Professional Review- March 2016 AM 13779
(5) Design & build for proposed erection of industrial development comprising of a single
storey engine test facility building with 3 storey control building on lots 4303V PT, 4354A
PT, 3967C PT, 4380M PT MK 20 at Seletar Aerospace park for Rolls Royce Singapore pte
ltd.
(6) Proposed addition & alterations to existing daughters of charity of the Cannosian
institute on Mukim 05 lot 1052K at 100, Jalan Merbok Singapore for M/S Daughters of
charity of the Cannosian Institute.
(1) Proposed erection of 10 storey building with attic comprising residential, car park & 1 st
storey commercial, including partial reconstruction of conserved ware house on lot 264X,
99274X, 470A PT & 486N PT TS 21 at Rodyk street & 82, 83 & 84 Robertson Quay.
(2) Contract 870G- Architectural and Engineering consultancy service for circle line stages 4
& 5. As built evaluation for slope stability check.