MPRDC Division Gwalior

INTERMITTENT WORK PROGRAM FOR RECONSTRUCTION OF


PADORA-GORA-PICHHORE ROAD NDB and PICHHORE-BASAYI ROAD under NDB Pkg. P-4A

Completed 17.08.2021 to 30.09.2021 01.10.2021 to 11.10.2021 12.10.2021 23.10.2021


Qty. in
S.No. Item Unit BOQ upto to to Remark
11.10.2021 Target Achievement Target Achievement 22.10.2021 29.10.2021
1 Site Clearance Km. 72.77 50.00 - - - - - -
2 Excavation Km. 72.77 45.00 - - - - - -
3 Emb./Subgrade Km. 72.77 44.96 6.84 - 1.50 - 2.50 2.50
4 GSB Km. 72.77 37.05 6.48 10.30 2.50 2.20 3.50 3.50
5 DLC Km. 72.77 34.32 8.08 9.70 4.00 3.62 3.50 3.50
6 PQC Km. 72.77 33.41 7.33 9.66 3.00 2.90 3.00 3.00
7 HPC No. 93 82 6 21 4 4 4 4
8 Slab/Box Culvert No. 24 8 4 2 3 3 1 1
9 Minor Bridge No. 12 2 1 - - - 1 1
10 Major Bridge No. 2 - - - - - - -
MPRDC Division Gwalior
INTERMITTENT WORK PROGRAM FOR RECONSTRUCTION OF
PADORA-GORA-PICHHORE ROAD NDB and PICHHORE-BASAYI ROAD under NDB Pkg. P-4A

Completed 12.10.2021 to 22.10.2021 23.10.2021 to 27.10.2021 28.10.2021 01.11.2021


Qty. in
S.No. Item Unit BOQ upto to to Remark
27.10.2021 Target Achievement Target Achievement 31.10.2021 05.11.2021
1 Site Clearance Km. 72.77 64.00 - - - - - -
2 Excavation Km. 72.77 62.00 - - - - - -
3 Emb./Subgrade Km. 72.77 58.71 2.50 10.20 2.50 3.55 2.00 1.50
4 GSB Km. 72.77 42.20 3.50 2.58 3.50 2.58 1.50 1.00
5 DLC Km. 72.77 40.50 3.50 3.50 3.50 3.00 1.00 1.00
6 PQC Km. 72.77 39.70 3.00 3.15 3.00 3.00 1.00 1.00
7 HPC No. 93 85 4 2 4 1 1 1
8 Slab/Box Culvert No. 24 8 1 1 1 1 1 1
9 Minor Bridge No. 12 2 1 - 1 1 1 1
10 Major Bridge No. 2 - - - - - - -