Aquino, Mark Joseph B.
1910185

ACADEMIC INTEGRITY PLEDGE

I swear on my honor that I did not use any inappropriate aid, nor give such to others, in accomplishing this coursework. I
understand that cheating and/or plagiarism is a major offense, as stated in TIP Memorandum No. P-04, s. 2017-2018, and
that I will be sanctioned appropriately once I have committed such acts. 
 

Aquino, Mark Joseph, B.


1910185
PROJECT COST 5200000                
CASH IN   FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER
  STARTING BALACE   1,815,934 1,715,022 1,607,972 1,505,652 1,390,394 1,260,030 1,031,144
  CAPITAL 900,000              
  DOWN PAYMENT (20%) 1040000              
  PROGRESS BILLING 406012.8293 306074.7 332568.1 312152 367993.5 433195.8 858446.1 623556.9442
  RETENTION               520000
TOTAL   2,346,013 2122009 2047590 1920124 1873645 1823590 2118476 2,174,701
                   
PROJECT COST                  
  CONSTRUCTION COST 500078.8087 376986.8 409618.3 384472 453251.1 533559.6 1057333 768024.041
  ADMIN COST 30,000 30,000 30,000 30,000 30,000 30,000 30,000 30,000
                   
TOTAL   530078.8087 406986.8 439618.3 414472 483251.1 563559.6 1087333 798024.041
                   
END TOTAL   1,815,934 1,715,022 1,607,972 1,505,652 1,390,394 1,260,030 1,031,144 1,376,676
                   
                   
PROFIT 476,676                
TAX 9533.529754                
ACTUAL PROFIT 467,143                