Professional Documents
Culture Documents
Untitled Document
Untitled Document
Untitled Document
MANGALDAN SITE
On our second day, we are assigned to Foreman Danny Soriano (Construction Manager of DHD Design
+ Construction) in Mangaldan Site under Architect Rachel Quinto.
Upon our arrival, we are then introduced by Ar. Quinto to her skilled workers and laborers. We had small
chitchats and orientation wherein we had a chance to get to know about the project.
The project is a Two Storey Residential Commercial Building and is located at Poblacion, Mangaldan,
Pangasinan.
During the day, we are tasked to observe the existing project. The team consisted of 6 skilled workers, 13
laborers, 4 plumbers, and 1 time keeper.
The tasks for the day included skim coating interior walls, plastering circular and other columns,
excavation for concrete fencing, ceiling works, window and door molding, and installing a concrete fence.
In the afternoon, work resumed at 1:00 PM. Additional tasks included siphoning the excavation for the
concrete fence, continuing the plumbing work from the morning, installing pipes in the G.F. Toilet Male,
and working on footing and column installations.
On our third day, we are again tasked to do site observation and inspection on different construction
activities that were undergone.
At the end of the day, the construction project has made significant progress:
1. Scaffoldings are set up on the second floor, preparing for the ceiling installation.
2. Ceiling work completed in the 2nd Floor Storage room next to the kitchen.
3. Skim coating on the second floor is almost finished with its 3rd coat.
4. The left side of the perimeter fence saw the casting of CHB Laying and Columns in place.
5. "Pagtiktik" has been applied to the Stairs and portions of the slab.
6. Water lines have been successfully installed.
7. Plastering and Molding work have been carried out on specific parts of the structures.
In our fifth day at Mangaldan Site, we have learned the value of wearing personal protective equipment
and the value of material inventory.
Upon arrival, the labor caught our attention and reported that one labor had torn his foot by a nail. The
action that we'd given is to rush him to the nearest clinic. There, he was treated and injected anti-tetanus
and antibiotics.
The PPE is necessary to to protect employees from health and safety risks they might encounter at work,
including injuries.
After that, a 500 hollowblocks were delivered. In the receipt, it said that Ar. Quinto ordered 500 pieces of
#4 CHB and we are expecting 504 pieces to be delivered. However, upon manual counting and
recounting, we found out that there are 15 pieces lacking.
Material inventory is very important in construction. It is a crucial part since every piece of material cost a
lot. It is always be a must to do recount whenever there are delivery.