CHECKLIST BEFORE TESTING & COMMISSIONING VRF (FSV)

Reference No:

Project Name Victory Ivf Landmark


Address Medical Suites 02-04, Level 2 Menara Landmark No 12 Jalan Ngee Heng 80000 Jb
Customer Company Sension Engineering Sdn Bhd
Attend Date 2022/7/7
Contact Person: Chris
ACMV Contractor
Tel.No: 012-3506075

Outdoor Unit Yes No


1. Is the installation compliance of specification? /
2. Is the outdoor unit properly mounted? /
3. Is any air-discharge chamber installed for the outdoor unit? /
4. Is the outdoor unit install of anti-vibration materials? /
5. Is the outdoor unit install with filter dryer? (New installer or non certify installer by Panasonic, it's recommed to use
/
filter dryer before conduct T&C).

Indoor Unit Yes No


1. Is the installation compliance of specification? /
2. Is the indoor unit Drain Pan/Drain Pipe in good conditions ? /
3. Is the indoor unit properly mounted? /
4. Is the indoor unit air filter in good conditions? /
5. Is all the Indoor Unit remote controller proper located? /

Piping System Yes No


1. Is the installation compliance of specification? /
2. Had all the piping properly connected? /
3. Is all the piping properly insulated? /
4. Is the size of the straight joints and Distribution joints Kit used correctly? /

5. Was the piping used of the correct size as requested?


Note: The pipe thickness for each diameter of pipe:
____mm (Ф6.35mm), ____mm (Ф9.52mm), ____mm (Ф12.7mm), ____mm (Ф15.88mm), 30 mm (Ф19.05mm), mm /
(Ф22.22mm), 45 mm (Ф25.4mm), 60mm (Ф28.58mm), ____mm (Ф31.75mm),, ____mm (Ф38.1mm), ____mm
(Ф41.28mm),, ____mm (Ф44.45mm)

6. Was the piping length within the allowable tubing length? /


7. Was the piping holding pressure test by Nitrogen 600psi? /
8. Was the copper piping flushing by Nitrogen? /
9. Was the copper piping vacuuming for 4 hours (each system)? /
10. Was the copper piping length already submitted for additional gas calculation? /
11. Is the LPG Fuel Regulator installed to the system?

Drain Piping Yes No


1. Is the installation compliance of specification? /
2. Is the drain pipe have gradiant? /
3. Is the drain pipe mixed with other pipe? /
4. Is the drain pipe raise up (for drain pump)? /

Electrical System Yes No


1. Is the installation compliance of specification? /
2. Is the wiring size correct?
Note:
Outdoor unit:
ME1/ME2: 6mm² (8HP),6mm² (10HP),10mm²(12HP),10mm² (14HP),____mm² (16HP),____mm² (18HP),____mm² /
(20HP),
LE1/LE2 : ____mm² (4HP),____mm²(5HP),____mm² (6HP),____mm² (8HP),____mm² (10HP),
Indoor unit:6mm²
3. Is all the wire firmly tightening to the terminal base? /
4. Is the wiring connection correctly connected as shown in the wiring diagram? /
5. Is the colour code used to indicated the "Live", "Neutral" and "Earth" wire? /
6. Is the breaker installed with the correct breaker Ampere?
7. Is incoming power supply for indoor & outdoor unit ready?

Communication Cable Yes No


1. Is the installation compliance of specification? /
2. Is the Communication Wire size correct?
/
Note: ____mm² / AWG____
3. Is the Communication wire using shield type? /
4. Is all the wire U1 , U2 & Ground tightening to the terminal base? /
5. Is all the wire indicate a label/number for future tracking/trouble shooting ? /

* If there is any discrepancy between the checked list with actual site condition, which resulted in Panasonic Service Team to
reattend, Panasonic hold the right to charge RM600 per each system for re-T&C with labor cost.( Spare parts cost and replace cost
excluded if any)

Inspected By :
( Name) (IC No) (Signature)
Date :
Senarai Semak Sebelum Pengujian dan Pentauliahan VRF (FSV)
No Rujukan:

Nama Project
Alamat
Nama Syarikat
Tarikh Pemeriksaan
Nama Kenalan :
ACMV Kontractor
Nombor Telefon:

Unit Luaran (Outdoor Unit) Ya Tidak


1. Adakah permasangan mengikut spesifikasi?
2. Adakah Unit Luaran (Outdoor Unit) dipasang dengan betul?
3. Adakah ruang pelepasan udara (discharge chamber) dipasang pada Unit Luaran (Outdoor Unit)?
4. Adakah Unit Luaran (Outdoor Unit) dipasang dengan bahan anti getaran?
5. Adakah Unit Luaran dipasang dengan pengering tapis (filter drier) (Pemasang baru atau Pemasang yang tidak
disahkan oleh Panasonic, pengering tapis (filter drier) adalah disyorkan sebelum menjalankan T&C).

Unit Dalaman (Indoor Unit) Ya Tidak


1. Adakah permasangan mengikut spesifikasi?
2. Adakah bekas pengaliran air (drain pan)/ paip pengaliran air (drain pipe)untuk Unit Dalaman (Indoor Unit) dalam
keadaaan yang baik?
3. Adakah Unit Dalaman (Indoor Unit) dipasang dengan betul?
4. Adakah penapis udara untuk Unit Dalaman (Indoor Unit) dalam keadaan yang baik?
5. Adakah alat kawalan jauh (remote controller) untuk Unit Dalaman (Indoor Unit) dipasang pada tempat yang sesuai?

Sistem Paip Ya Tidak


1. Adakah permasangan mengikut spesifikasi?
2. Adakah semua paip sudah disambungkan dengan betul?
3. Adakah semua paip sudah dipasang penebat (insulated) dengan baik?
4. Adakah saiz ukuran penyambung lurus (straight joints) dan kit penyambung edar (distribution joints kit) dipasang
dengan betul?

5. Adakah saiz ukuran paip dipakai mengikut spesifikasi yang diperlukan?


Nota: ketebalan paip untuk setiap diameter

____mm (Ф6.35mm), ____mm (Ф9.52mm), ____mm (Ф12.7mm), ____mm (Ф15.88mm), ____mm (Ф19.05mm),
____mm (Ф22.22mm), ____mm (Ф25.4mm), ____mm (Ф28.58mm), ____mm (Ф31.75mm),, ____mm (Ф38.1mm),,
____mm (Ф41.28mm),, ____mm (Ф44.45mm)

6. Adakah panjang paip berada dalam spesifikasi yang dibenarkan?


7. Adakah ujian tekanan ketahanan (holding pressure test) paip dijalankan dengan nitrogen pada 600 psi?
8. Adakah paip dipam (flush-out) dengan nitrogen?
9. Adakah paip divakum untuk 4 jam (setiap sistem)?
10.Adakah panjang paip telah diserahkan untuk pengiraan refrigeran tambahan?
11.Adakah pengawalselia bahan bakar LPG (LPG fuel regulator) dipasang pada sistem?

Paip Pengaliran Air Ya Tidak


1. Adakah pemasangan mengikut spesifikasi?
2. Adakah pemasangan paip pengaliran air mempunyai kecerunan?
3. Adakah pemasangan paip pengaliran air berkongsi dengan paip lain?
4. Adakah pemasangan paip pengaliran air dinaikan? (untuk unit dengan pam air)

Sistem Elektrik Ya Tidak


1. Adakah pemasangan mengikut spesifikasi?

2. Adakah saiz dan ukuran wayar pendawaian betul?


Nota:
Outdoor unit:
ME1/ME2: ____mm² (8HP),____mm² (10HP),____mm²(12HP),____mm² (14HP),____mm² (16HP),____mm²
(18HP),____mm² (20HP),
LE1/LE2 : ____mm² (4HP),____mm²(5HP),____mm² (6HP),____mm² (8HP),____mm² (10HP),
Indoor unit:____mm²

3. Adakah semua wayar disambung ketat ke tapak terminal?


4. Adakah sambungan pendawaian disambungkan dengan betul seperti yang ditunjukkan dalam rajah pendawaian?
5. Adakah kod warna digunakan untuk menunjukkan wayar "Hidup (Live)", "Neutral (Neutral)" and "Bumi (Earth)"?
6. Adakah pemutus (breaker) dilengkapi dengan arus pemutus (breaker ampere) yang betul?
7. Adakah bekalan elektrik untuk unit dalaman (indoor unit) & unit luaran (outdoor unit) sudah tersedia?

Kabel Komunikasi Ya Tidak


1. Adakah pemasangan mengikut spesifikasi?
2. Adakah saiz dan ukuran wayar komunikasi betul?
Nota: ____mm² / AWG____
3. Adakah wayar komunikasi jenis pelindung (shielded) digunakan?
4. Adakah semua wayar komunikasi (U1 , U2 & Ground) disambung ketat ke tapak terminal?
5. Adakah semua wayar dilengkapi label/ nombor untuk aktiviti menjejak/ membaikpulih pada masa depan?

*Sekiranya terdapat perbezaan antara senarai semak dengan situasi projek sebenar yang memerlukan Panasonic Service Team membuat
lawatan semula, Panasonic berhak untuk mengenakan bayaran sebanyak RM600 untuk T&C semula setiap system termasuk kos
buruh( Tidak termasuk kos alat ganti dan kos buruh menukar alat ganti jika ada)

Pemeriksaan oleh :
( Name) (IC No) (Tandatangan)
Tarikh :
VRF (FSV)测试和调试前的检查清单
参考编号:

工程名称
地址
客户公司名称
出席日期
联系人:
ACMV 承包商
电话号码:

室外机 是 否
1. 安装是否符合规范?
2. 室外机安装是否正确?
3. 室外机是否安装了排风管?
4. 室外机是否安装了抗振物?
5.室外机是否安装过滤干燥器? (新安装人员或非松下认证安装人员,建议在进行 T&C 之前使用过滤干
燥器)

室内机 是 否
1. 安装是否符合规范?
2. 室内机排水盘/排水管是否完好 ?
3. 室内机安装是否正确?
4. 室内机空气过滤器是否完好?
5. 是否所有室内机遥控器都位于正确位置?

铜管系统 是 否
1. 安装是否符合规范?
2. 是否正确连接了所有铜管?
3. 所有铜管是否正确绝缘?
4. Straight joints和Distribution joints Kit 的尺寸是否正确使用?

5. 是否按照要求使用了正确尺寸的铜管?
备注:铜管厚度,根据直径长度

____mm (Ф6.35mm), ____mm (Ф9.52mm), ____mm (Ф12.7mm), ____mm (Ф15.88mm),


____mm (Ф19.05mm), ____mm (Ф22.22mm), ____mm (Ф25.4mm), ____mm (Ф28.58mm),
____mm (Ф31.75mm),, ____mm (Ф38.1mm),, ____mm (Ф41.28mm),, ____mm (Ф44.45mm)
6. 配管长度是否在允许的配管长度内?
7. 铜管保压测试是通过氮气 600psi 进行的吗?
8. 铜管被氮气冲刷了吗?
9.铜管是否抽真空了 4 小时(每个系统)?
10. 铜管长度是否已经提交以计算额外的冷媒?
11. 系统中是否安装了液化石油气燃料(LPG)调节器?

排水管 是 否
1. 安装是否符合规范?
2. 排水管是否有斜度?
3. 排水管是否与其他管道混合?
4. 排水管是否升高(用于排水泵)?

通电系统 是 否
1.安装是否符合规范?
2.电线尺寸是否正确?
备注:
室外机:
ME1/ME2: ____mm² (8马力),____mm² (10马力),____mm²(12马力),____mm² (14马力),____mm² (16马
力),____mm² (18马力),____mm² (20HP),
LE1/LE2 : ____mm² (4马力),____mm²(5马力),____mm² (6马力),____mm² (8马力),____mm² (10马力),
室内机:____mm²
3. 所有电线是否牢固地锁紧在terminal base上?
4. 电线连接是否如接线图所示正确连接?
5. 用于指示“火线”、“中性线”和“地线”线的颜色代码是否正确?
6. 断路器是否安装了正确的安培指数(Ampere)?
7. 室内外机的进线电源是否准备好了?

通讯电缆 是 否
1. 安装是否符合规范?
2. 通讯线尺寸是否正确?
备注: _____mm² / AWG____
3. 通讯线是否采用屏蔽式?
4. 是否所有的通讯电缆 U1、U2 和地线都紧固到terminal base上?
5. 是否所有电线都标明了标签/编号以方便将来记录/维修?

* 如果核对清单与现场实际情况存在差异,导致松下服务团队(Panasonic Service Team) 需要额外造访服务, Panasonic 有权对


每个系统收取 RM600 以进行重新测试和调试(T&C) (包含人工成本)。(不包括备件成本和更换成本,如有)