797225-01Z-ME-985-0001

MDS- Crude Storage Tank


HMB-21-T-001 A/B

CLIENT: HAMADA Oil Operations

PROJECT: Early Production Facility Package Service

SLB PROJECT NUMBER: 797225

LOCATION: Libya

Mechanical Data sheet - Crude Storage Tank


DOCUMENT TITLE:
(HMB-21-T-001 A/B )

SLB DOCUMENT NUMBER: 797225-01Z-ME-985-0001

SCHLUMBERGER DOCUMENT HISTORY

C 30-09-2022 Issued for Quote GG MT SM


B 31-05-2022 Issued for Information GG MT SM
A 11-05-2022 Issued for Information GG MT AM
Rev Issue Date Revision Description Prepared By Verified By Approved By

Schlumberger-Private
#
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Job No 797225
* For boxes marked with *, if blank, Contractor Shall determine and submit as per Appendix L. For all lines, see Appendix L for line-by-line instructions.
GENERAL Special Documentation Package Requirements:

Measurement Units to be used in API Std 650: SI US Customary

1. Manufacturer* TBA Contract No.*

Address* TBA

Contractor Sr No.* TBA Year Built* (TBA) Edition & Addendum to API 650 * 13th Edition ( March 2020)

2. Purchaser Schlumberger Contract No. TBA

Address

Tank Designation Crude Storage Tank (HMD-21-T-001 A/B)

3. Owner Hamada Oil Operations Location Libya

4. Size Limitations* NA Tank Diameter* 9.5 M (ID) Shell Height* 9.7 M C

Capacity: Maximum* 4325 BBL (Each) Net Working* 3,125 BBL (Each) Criteria* Refer Liquid Levels Provided in the sketch (page 9) C

5. Products Stored:

Liquid HYDROCARBON CRUDE Max. Density.: 715 at 65 ° C (Note 4)

Operating. Temp. 17 to 63 ° C Min Design Metal Temp.* -7 ° C Operating Pr 0.06 Barg

Blanketing Gas Yes Vapor Pressure 1.1 BARA at Max. Operating Temp.

% Aromatic NA Suppl. Spec. Refer Design Basic & Criteria H2S Service? Yes No Suppl. Spec. NA

Other Special Service Conditions? Yes No Suppl. Spec. NA

DESIGN AND TESTING Purchaser to Review Design Prior to Ordering Material? Yes No

6. Applicable API Standard 650 Appendices:* A B C F G H I J L M O P S U V W

7. Max. Design. Temp. 90 ° C Min Design Metal Temp.* 0 ° C Design Liquid Level* 9.7 M C
3
Design Pressure Min: -0.05 Max: 0.1 External Pressure -0.050 Barg Maximum Fill Rate 165.6 m3/hr Maximum Emptying Rate 165.6 m /hr
C
Floatation Considerations? Yes No Flot. Suppl. Spec:* NA Applied Supplemental Load Spec. NA

8. Seismic Design? Yes No Alternate Seismic Criteria NA Seismic Use Group NA

MBE Site Class NA Vertical Seismic Design? Yes No Vertical Ground Motion Accelerator AV: NA

Basis of Lateral Acceleration (Select one): Mapped Seismic Parameters? Ss NA S1 NA S0 NA Site-Specific Procedures: MCE

Design Required? Yes No ; Other (Non-ASCE) Methods NA

Freeboard Required for SUG I Design Roof Tie Rods @ Outer Ring?* Yes No

9. Wind Velocity for non-U.S. sites, 50-yr. wind speed (3-sec. Gust)* 145 km/h - Note 25

Top Wind Girder Style* NA Dimensions* NA Use Top Wind Girder as Walkway? Yes No

Intermediate Wind Girders?* Yes No Intermediate Wind Girder Style* Angle (Note 17) Dimensions* VTA

Check Buckling in Corroded Cond.? Yes No

10. Shell Design: 1-Ft Mthd?* Yes No ; Variable-Des-Pt Mthd?* Yes No Alternate ; Elastic Anal. Mthd?* Yes No Alternate

Plate Stacking Criteria* Centerline-Stacked? Yes No Flush-Stacked? Yes No Inside Outside

Plate Widths (Shell course heights) and Thicknesses * Numbers below Indicate Course Number.
1. VTA 2. VTA 3. VTA 4. VTA 5. VTA
6. VTA 7. 8. 9. 10.
11. 12. 13. 14. 15.
Joint Efficiency* As Per Code Shell-to-Bottom Weld Type* Double fillet weld Shell-to-Bottom Weld Insp. Mthd* As per Cl 7.2.4 of API650

Page 2 of 9

# Schlumberger-Private
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Contract No 797225
* If box is blank, Contractor shall determine and submit as per Appendix L.

11. Open-Top and Fixed Roofs: Open Top?* Yes No

Fixed Roof Type* Supported Cone Roof Roof Support Columns*: Pipe Or Structural Shape Rafter Supported (without columns)

Cone Slope* 1 in 5 Dome or Umbrella Radius* NA Weld Joints* Fillet on top side
(Lap, Butt, Other)
Seal Weld Underside of: Lap Joints? Yes No ; Seal Weld Underside of Wind Girder Joints? Yes No

Gas-tight? Yes No Joint Efficiency* As per code %

Thickness* VTA In. Snow Load* NA App. Suppl. Load Spec.* Piping Load (Local) Column Lateral Load N.A

Normal Venting Devices* PVRV Emergency Venting Devices* Yes (As per API 650 & API 2000)

For Non-Frangible Roofs: Seal Weld Roof Plates to Top Angle on the Inside? Yes No Weld Rafters to Roof Plates? Yes No

Roof-to-Shell Detail* As per Code - Fig F2 Detail (i) Radial Projection of Horizontal Component of Top Angle* Inward Outward

12. Bottom: Thickness* VTA Style* Cone up from center Slope* 1 in 100 Weld Joint Type* Single-welded full-fillet lap joint

Provide Drip Ring? Yes No Alternate Spec. NA

Annular Ring? Yes No Annular Ring: Minimum Radial Width* As per Code Thickness* 10mm (Min)

13. Foundation: Furnished by* Tank Contractor Type* Concrete Ring Beam Type
Soil Allow: Bearing Pressure*As per Geotechnical Report Anchors: Size* VTA Qty.* VTA
Foundation Design Loads: Base Shear Force: Wind* TBA Seismic* N.A Overturning Moment: Wind* TBA Seismic* NA
Ring Forces: Weight of Shell + Roof New* TBA Corroded* TBA Roof Live Load* 1 KP a Internal Pressure* 0.1 Barg
Partial Vacuum* -0.05 Barg
Bottom Forces: Floor Wt. New* TBA Corroded* TBA Product Wt.* TBA Water Wt.* TBA Internal Pressure* 0.1Barg
Other Foundation Loads* As per Civil Engineering Design basis Min. Projection of Fdn. Above Grade: 1.8 m
14. Responsibility for Heating Water, if Required: Purchaser Manufacturer
Hydro-Test Fill Height* Upto Curb Angle Settlement Measurements Required? Yes No Extended Duration of Hydro-Test: 7 Days (Min)
Predicted Settlement Profile is Attached Yes No NA

Responsibility for Setting Water Quality: Purchaser Manufacturer Supplemental Test Water Quality Spec. NA
Test Water Source & Disposal Tie-In Locations Tank Contractor Hydro-Test Appendix J Tank? Yes No
Post-Pressure-Test Activities Required of the Manufacturer: Broom Clean Potable Water Rinse Dry Interior
Other As per Approved Procedure
15. Inspection by Tank Contractor /Purchaser / COMPANY/ A.I in Shop; Tank Contractor /Purchaser / COMPANY/ Authorised Inspector in Field
Supplemental NDE Responsibility Tank Contractor Supplemental NDE Spec. Purchaser
(Purch., Contractor., Other)
Positive Material Identification? Yes No PMI Requirements: NA
Max. Plate Thickness for Shearing 10 mm
Must Welds not exceeding 6 mm (1/4 in.) Be Multi-Pass? Yes No Must Welds greater than 6 mm (1/4 in.) Be Multi-Pass? Yes No

Leak Test Mthd: Roof* As per code /Approved ITP Shell* Water fill test/ Approved ITP Shell Noz./Manhole Reinf. Plt* Pneumatic test & LPT / Approved ITP

Bottom* Vacuum box test Floating Roof Components* NA


Modify or Waive API Dimensional Tolerances (see 7.5)? No Yes Specify: NA
Specify Additional Tolerances, if any, and Circumferential and Vertical Measurement Locations: NA
- Allowable Plumbness: Measure
As per API 650 and Record at a Minimum of 8 Locations or Every NA m (ft) around the Tank, at
the Following Shell Heights: (select one box): 1
/3 H, 2/3 H and H Top of Each Shell Course Other: -
- Allowable Roundness:** As per API 650 Measure Radius and Record at a Minimum of 8 Locations or Every NA m (ft)

around the Tank, at the Following Shell Heights (select one box):
1
Top of Tank, H /3 H, 2/3 H and H Top of Each Shell Course Other: -

Page 3 of 9

# Schlumberger-Private
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Contract No 797225
* If box is blank, Contractor shall determine and submit as per Appendix L.

16. Coatings:

Internal Coatings by: Tank Contractor Per Spec.* As Per Purchasers Specification (Note 45)

(Not Req'd., Others, Tank Contractor.)

External Coating by: Tank Contractor Per Spec.* As Per Purchasers Specification (Note 45)

(Not Req'd., Others, Tank Contractor.)

Under-Bottom Coating by: Tank Contractor Per Spec.* As Per Purchasers Specification (Note 45)

(Not Req'd., Others, Tank Contractor.)

---

17. Cathodic Protection System? Yes No Per Spec.* As Per Purchasers Specification (Note 43)

18. Leak Detection System? Yes No Per Spec.* As per Annex I of API 650

19. Release Prevention Barrier? Yes No Per Spec.* NA

20. Tank Measurement System: Required? Yes No Remote Capability Required? Yes No

By:* Purchaser Per Spec.* As Per Purchasers Specification

21. Weight of Tank: Full of Water* VTA Empty* VTA Shipping* NA Brace/Lift Spec.* NA

22. References:* API Std 650, Appendix L

Refer Page 8 of 9

Page 4 of 9

# Schlumberger-Private
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Contract No 797225
* If box is blank, Contractor shall determine and submit as per Appendix L.
Table 1 MATERIALS OF CONSTRUCTION (Note 33)
Component Material*/Thickness* C.A. Component Material* C.A.
Shell 1 A283 Gr. C or Eq. / -- mm 3mm Reinforcing Pads A283 Gr. C or Eq. / -- mm 0 mm
Shell 2 A283 Gr. C or Eq./ -- mm 3mm Manhole/Nozzle Necks A283 Gr. C or Eq. / A 106 gr B 3mm
Shell 3 A283 Gr. C or Eq./ -- mm 3mm Manhole/Nozzle Flanges A283 Gr. C or Eq. / A105 3mm/ 0 MM
Shell 4 A283 Gr. C or Eq./ -- mm 3mm Manhole Flange Covers A283 Gr. C or Eq. 3mm
Shell 5 A283 Gr. C or Eq./ -- mm 3mm Anchor Attachments A283 Gr. C or Eq. 0mm
Roof A283 Gr. C or Eq./ -- mm 3mm Submerged Piping A106 Gr B 3mm (Total)
Bottom A283 Gr. C or Eq./ -- mm 3mm Wetted Structurals (int) A 36/S275 JR /Equivalent 3mm (Total)
Annular Ring A283 Gr. C or Eq./ -- mm 3mm Non-wetted Structurals (ext) A 36/ S275 JR / Equivalent 0 mm
+ Check here if C.A. is to apply to each exposed surface
Table 2 BOLTS and ANCHORS
Component Head Type* Bolt or Anchor Material* Nut Material* Thread Series* C.A.
A193 Gr B7 (Zn-Nickel A194 Gr 2H (Zn-Nickel coated
Flange Bolting Hexagonal UNC Nil
coated with PTFE top coat} with PTFE top coat)
Structural Bolting As per Tank Contractors Design Nil
Anchor Bolts As per Tank Contractors Design 3mm (Total)
++ Total C.A., on the nominal diameter.
Table 3 NOZZLE and MANHOLE SCHEDULE* (for Cone Roof and Shell)
Full
Min Proj. to
Pen. Reinf. Plate
Size, NPS, Neck Sch or Flange Flange Class or FF from
Mark Service Qty On Dimensions Remarks
or Dia. (in.) Wall Thick. Type Thick. Shell/ roof
Open. (OD x Thk)
outside
(Y/N)
N1 Crude Oil Inlet 12 1 TBA Y WNRF 150# TBA 250
With Vortes
N2 Crude Oil Outlet 18 1 TBA Y WNRF 150# TBA 250
Breaker
N3 Foam Pourer 8 1 TBA Y WNRF 150# TBA 250 With Deflector

Deleted
N4C/D/
Sample Point 2 3 TBA Y WNRF 150# TBA 250
E
N5 Open Drain Outlet 4 1 TBA Y WNRF 150# TBA 250 With Dip Pipe

N6 Spare 3 1 TBA Y WNRF 150# TBA 250 Note 46

N8 Temperature Indicator 3 1 TBA Y WNRF 150# TBA 250

N10 Spare 2 1 TBA Y WNRF 150# TBA 250 Note 46

N11 PVRV 8 1 TBA Y WNRF 150# TBA 250 Note 18

N12 Fuel Gas 4 1 TBA Y WNRF 150# TBA 250

N13 To Flare LLP KOD 10 1 TBA Y WNRF 150# TBA 250

N14 A/B Level Gauge 3 2 TBA Y WNRF 150# TBA 250

N15 Dip Hatch 6 1 TBA Y WNRF 150# TBA 250 With dip Hatch

Deleted

N17 Level Transmitter 4 1 TBA Y WNRF 150# TBA 250

N19 Level Transmitter 4 1 TBA Y WNRF 150# TBA 250

N20 Pressure transmitter 2 1 TBA Y WNRF 150# TBA 250

N21 Fire Hatch (Emergency Vent) 24 1 TBA Y WNRF 150# TBA 250 Note 20

N22 Overflow with Blind 16 1 TBA Y WNRF 150# TBA 250 Note 44

N23 Spare 4 2 TBA Y WNRF 150# TBA 250 Note 44

Deleted

N25 Analyser Trans,itter 2 1 TBA Y WNRF 150# TBA 250

N26 Pressure Transmitter 2 1 TBA Y WNRF 150# TBA 250


N27/28/
Sensing Line 2 3 TBA Y WNRF 150# TBA 250
29
Clean Out Door With covert &
COD 24 x 24 1 AS PER API 650 Note 44
davit
Shell Manhole With Cover &
M1 24 1 AS PER API 650 Note 44
Davit
M2A/B Roof Manhole With Davit 24 2 AS PER API 650 Note 44
Page 5 of 9
Schlumberger-Private
#
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Contract No 797225
* If box is blank, Contractor shall determine and submit as per Appendix L.

OTHER TANK APPURTENANCES

24. Platform, Stairway, and Railing: Galvanizing Req'd?* Yes No Stairway Style* Helical Walk Surf. Type* Non Skid Grating
(Note 47) (Straight or Helical)

Stair and Walkway Clear Width* 800mm (Min) National Safety Standards* As per Local Regulations

Architectural/Structural Specification* As per Tank Contractor Design / ASTM Specification

Gaugers Platform Yes No Qty. Req'd* 1 Per Spec.* As per Tank Contractor Design

25. Jacket Required?* Yes No Other Heaters/Coolers Required?* Yes No

Supplemental Jacket, Heater, or Cooler Specifications* NA

26. Mixer/Agitator: Quantity NIL Size* NA Per Spec.* NA

27. Insulation: Required? Yes No Thickness* NA Material* NA

Per Specs* NA (Note 55) Responsibility for Insulation and Installation NA


(Purchaser, Manufacturer, Others)

28. Structural Attachments: Lift Lugs?* Yes No Desc.* NA

Shell Anchorage?* Yes No Type* As per Tank Contractor design Scaffold Cable Support? Yes No

29. Various Other Items: Welded Flush-Type: Shell Connection Cleanout Fitting Waive Application of Appendix P? Yes No

Miscellany #1 Nil Miscellany #2 Nil

Miscellany #3 Nil Miscellany #4 Nil

Miscellany #5 Nil Miscellany #6 Nil

Table 4 OTHER TANK APPURTENANCES*


Service or
Mark Quantity Description Size Flange Type / STD Height from Datum Material Remarks

Page 6 of 9

# Schlumberger-Private
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Contract No 797225
* If box is blank, Contractor shall determine and submit as per Appendix L.

Notes:
01 All dimensions are in millimetres unless otherwise specified.
02 Design and detailed engineering of the storage tank is included in Contractors scope.
03 Tank design and construction work shall be carried out in accordance to API650 and "Mechanical Design Basis"
04 Design liquid level shall be the full height of the shell (including top angle) for fixed roofs with a liquid specific gravity not less than 1.0. Tanks shall
be designed to permit hydrostatic testing as erected in the fully corroded condition (after corrosion allowance is eroded)
05 Nozzle flanges up to 24" NPS shall be as per ASME B 16.5 and flange above 24" NPS shall be as per ASME 16.47 series A/ B.
06 Gasket material for Manholes and COD shall be compressed - Non asbestos fibre and for nozzles spiral wound mettalic gasket as per the
Piping material specifications.
08 Manhole neck and nozzle neck above 300NB may be fabricated from plate and 100% radiographed.
09 Flanges shall have 125 AARH face finish at gasket area.
10 Flange bolt hole shall straddle natural North - south direction of horizontal of tank and vertical centerline unless otherwise specified.
11 Nozzle sizes specified in the data sheet is tentative and to be confirmed during detailed design stage.
12 Nozzle Reinforced pads shall be provided with 6mm tell tale hole. Tell tale hole to be left open and to be filled with room temperature vulcanising
(RTV) silicon sealent
13 Nozzle RF Pad size / thickness shall be by the CONTRACTOR.
14 Specified nozzle projection are measured from outside of Shell/Roof. Final value shall be confirmed by CONTRACTOR during detailed Design Stage
15 The nozzle elevation shall be with respect to top of bottom plate.
16 Contractor to ensure that nozzles provided on the shell plates meets the requirements of Fig 5.6 of API 650.
17 CONTRACTOR shall check the requirement of Secondary Wind Girder in accordance to API 650. Calculations to be performed with corroded
thickness of shell
18 Design of the vents (PVRV & Emergency Vent) shall be in accordance to API 650, API 2000. Emergency vent shall be designed for fire case.
Design and supply of Vents are excluded from Contractors scope.
19 CONTRACTOR shall check the requirement of Anchor bolts based on API 650. Basic design of the anchor bolts shall be according to Cl 5.12of API650.
20 Spiral Staircase with railing, Intermediate and top Platforms, Gaugerus platform, All Around Hand railing on roof periphery & for nozzle access etc
are included in contractors scope.
21 Maintenance Platforms and ladder shall be provided to access Foam Pourer, Manways and instruments
22 Details of Staircase, Ladder, Platform , Accessories, Nozzle Elevation etc shall be furnished later after completion of engineering. Minimum width of
Platform shall be 800 mm
23 Contractor to ensure roof structure is not immerced in the stored liquid. Contractor may increase the free board / tank height to accomediate the roof
according to Contractors design
24 .Nozzle local load shall be analyzed based on external piping load & local stress analysis for cleats to be performed.External loads on the shell nozzles
to be analysed based on Annex P of API 650. Nozzles on the roof to be analysed based in any FEA method approved by the COMPANY.
25 Highest mean windspeed is 145 km/h
26 Anti syphon holes shall be provided for the internal pipes. Dip pipes shall be provided with internal support and pad plate of 10 mm welded with base
plate of diameter of 2 time of dip pipe to avoid erosions
27 4 nos (min) earthing bosses shall be provided at @ 90° (max) apart for the tank to facilitate earthing connection.
28 Gauge hatch shall be spark proof. Supply of gauge hatch is excluded from contractors scope
29 Foam pourer system and fire water spray system for the tank, for cooling purpose. (safety in case of Fire) shall be provided for the Tank
30 Design, supply, Erection and testing of all tank internals (such as pipes, vortex breaker, deflector etc ) are included in contractors scope.
31 All materials shall meet the minimum requirements specified in Section 4 of API 650
32 Negative tolerance is not acceptable for the Tank plates for Bottom, shell and roof
33 All pressure retaining & process wetted components/ parts shall have BS-EN-10204 Certificate type 3.1 and all other materials shall have Type 2.2 certificate.
34 Tank fabrication, erection and dimensional tolerances shall comply with relevant sections of API 650
35 All weld joints on tank bottom and roof shall be vacuum box tested.
36 Cleanout Door to be stress relieved in accordance to section 5.7.4 of API 650
37 Acceptable tolerance shall be in accordance to API 650
38 Requirement of Testing, NDT etc shall be in accordance to API 650 and approved ITP
39 After completion of all hot work and NDT, the tank shall be hydrotested in accordance to API 650 and approved testing procedure. Quality of water
shall be as per approved Hydro test Procedure
40 Tank shall be cleaned and air dried after hydro test.
41 Contractor shall carryout the tank calibration & certification as per approved procedure
42 Blinding of all manholes, Cleanout door,spare nozzles, including supply of blind flage, gasket, N&B are included in contractors scope
43 Tank bottom external surface shall be provided with Impress Current cathodic protection system
44 Internal / external painting / coating shall be done only after completion of NDT and hydro test.
45 Painting / Coating- Internal / External / Underside of bottom plates painting / coating is included in contractors scope. Painting /
coating shall be carried out as per approved specification / procedure
Tank shall be externally painted with logo and Tank number painted on them.
46 Spares= Supply of spares are included in contractors scope. Minimum spares required are as follows
a) 200% of gaskets for all flanged joints (Manholes, cleanout door, spare nozzles etc)
b) 10% of bolts and nuts (Minimum 4 nos for all flanged joints (Manholes, cleanout door, spare nozzles etc)
47 CONTRACTOR to include weight and foundation loading details in the Tank design calculations
Page 7 of 9

Schlumberger-Private
#
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Produced Storage water Tank (HMD-31-T-001)
SLB Doc No 797225-01Z-ME-985-0002
Contract No 797225

* If box is blank, Contractor shall determine and submit as per Appendix L.

Notes- Continued
45 Painting / Coating- Internal / External / Underside of bottom plates painting / coating is included in contractors scope. Painting /
coating shall be carried out as per approved specification / procedure
Tank shall be externally painted with logo and Tank number painted on them.
46 Spares= Supply of spares are included in contractors scope. Minimum spares required are as follows
a) 200% of gaskets for all flanged joints (Manholes, cleanout door, spare nozzles etc)
b) 10% of bolts and nuts (Minimum 4 nos for all flanged joints (Manholes, cleanout door, spare nozzles etc)
47 CONTRACTOR to include weight and foundation loading details in the Tank design calculations
48 Foundation settlement - Any differential settlement greater than 13 mm per 10 m of circumference or a uniform settlement over 50mm
shall be reported to the Purchaser for evaluation. Filling of the tank shall be stopped until cleared by the Purchaser
50 Cable tray routing within the tank and top roof of the tank is included in tank contractors scope
51 Contractor is required to follow all local legislative and regulatory requirements including those applicable to local content requirement
52 Details marked "TBA" shall be provided by Contractor during detailed engineering stage.
53 TBA- To be decided by Contractor based on Design Codes and Specifications
54 Railing to be provided on both sides of the spiral staircase. Inner stringer is for Personal Protection. Bottom portion of shell inside
(upto 2m) is coated with GRE coating, which will act as an insulator and no separate PP is envisaged
55 Name plate on tank is included in Contractor scope.tank shall be externally painted with Client logo
56 Corrosion allowance for internals shall be provided on all surfaces.
57 Produced water storage tank capacity is considered for 24 hours storage. The produced water flowrate is 15000 BPD.
58 Tank is heat traced to maintain temperature above 10°C.
Applicable Specification and Standards
01 API Standard 650 (13th Edition -March 2020)- Welded Tanks for Oil Storage
02 API Standard 2000- Venting Atmospheric and Low-Pressure Storage Tanks: Non-refrigerated and Refrigerated
03 ASME Boiler and Pressure Vessel Code-Section II-Materials
04 ASME Boiler and Pressure Vessel Code-Section V-Nondestructive Examination
05 ASME Boiler and Pressure Vessel Code-Section VIII-Pressure Vessels
06 ASME Boiler and Pressure Vessel Code-Section IX-Welding and Brazing Qualifications”
07 GES D.01 - Atmospheric Storage Tank (API 650)
08 GES D.02 - Accessories for Atmospheric Storage Tanks
09 GES X.01 - Surface Preparation and Painting Application
10 GES X.02- Colour Coding of Equipment and Piping Systems
11 GES X.03 - External Protective Coatings

Legend
01 Contractor / Tank Contractor - Party appointed for the Design, Supply of Material, Fabrication, Erection, Testing and Painting
of the Storage Tanks
02 Legend
TBA - Contractor to advice NA - Not Applicable AI - Authorised Inspector
LALL- Level Low Low LAH- Level High LAHH- Level High High

Page 8 of 9

# Schlumberger-Private
Project Early Production Facility Package Service - HAMADA
Doc Title Mechanical Data sheet - Crude Storage Tank (HMB-21-T-001 A/B )
SLB Doc No 797225-01Z-ME-985-0001
Contract No 797225

ELEVATION

Tank Dia 9500 mm C

Tank Height 9700 mm C

LALL 800 mm

LAL 1000 mm

LAH 9250 mm

LAHH 9450 mm

Notes:
1 Nozzle schedule, orientation and elevation to be reconfirmed during detailed engineering stage

Page 9 of 9