ITP and CHECKLIST FOR BASE STATIONS
ITP and CHECKLIST FOR BASE STATIONS
PM Authorisation:
APPROVALS
Rev Issue Date Pages Revision Description Prepared Checked Approved
A01 02/05/17 ISSUED FOR APPROVAL Gabi A.Abuelmaati A. Dahman
Hold Record
Specify any Holds within the document.
Hold
Section Description of Hold
No.
Revision Tracking
Specify significant change from previous revisions of the document. (From Rev. A onwards)
Rev. Section Description of Change
A01 ISSUED FOR APPROVAL
Project Name:
UMM WU'AL PHOSPHATE PROJECT
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
DOCUMENT
1.0
REVIEW
MD-101-SMEM-EG-EL-SPC-
Ensure All Drawings are issued
1.1
for Construction
0001 Visual Check Approved Drawing R R R
Section 4.5
MD-101-SMEM-EG-EL-SPC-
Ensure Materials Approved Prior Material Approved
1.2
to Installation
0001 Visual Check
Document
R R R
Section 5.2
Cable Termination and MD-101-SMEM-EG-EL-SPC-
1.3 Splicing Special Work 0001 Visual Check Approved MS R R R
Procedure Section 5.9.12
MV Cable Termination and MD-101-SMEM-EG-EL-SPC-
1.4 splice personal Qualification 0001 Review Qualification Certification R R R
Certification Section 5.9.12
MATERIAL
2.0
RECEIVING
Cable Storage, Handling & MD-101-SMEM-EG-EL-SPC-
2.1 Preservation Visual 0001 Visual Check QC-CL-E-017 H W R
Inspection Section 5.3
Cable Reel Material & MD-101-SMEM-EG-EL-SPC-
2.2 Accessories Receiving 0001 Visual Check QC-CL-E-017 H W R
Visual Inspection Section 5.3
Cable Material Receiving MD-101-SMEM-EG-EL-SPC-
QC-CL-E-017 /
2.3 Cable Reel Continuity and 0002 Visual Check / Measure
QC-CL-E-022
H W R
Insulation Testing (MV cable) Section 5.2
Page 1 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
Page 2 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Ensure that cable tray /
0001
6.1 conduit installed as per
Section 5.9.5
Visual Check QC-CL-E-018 H W R
drawing or specification
Section 5.9.6
MD-101-SMEM-EG-EL-SPC-
Cable ties are installed as
0001
6.3 per drawing and
Section 5.9.5
Visual Check QC-CL-E-018 H W R
specification
Section 5.9.6
Page 3 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Inspection of cable layout in
7.1
trench
0001 Visual Check QC-CL-E-019 H W R
Section 5.9.8
MD-101-SMEM-EG-EL-SPC-
5KV IR test will be
0002 Measure and Visual
7.2 performed on underground
Section 4.3 Check
QC-CL-E-025 H W R
cables prior to any backfill
Section 4.4.1
MD-101-SMEM-EG-EL-SPC-
Installation of cable marking
7.4
tape / protective tiles
0001 Visual Check QC-CL-E-019 H W R
Section 5.9.8
MD-101-SMEM-EG-EL-SPC-
5KV IR test will be performed to
0002 Measure and Visual
7.5 confirm no damage of cable after
Section 4.3 Check
QC-CL-E-022 H W R
laying/backfilling works
Section 4.4.1
Page 4 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Verify correct cable origin &
8.1
destination point
0001 Visual Check QC-CL-E-020 H H R
Section 5.9.12
MD-101-SMEM-EG-EL-SPC-
Cable glands are of correct
8.2
type & size
0001 Visual Check QC-CL-E-020 H H R
Section 5.9.12
MD-101-SMEM-EG-EL-SPC-
Cables / wires properly
8.3
dressed
0001 Visual Check QC-CL-E-020 H H R
Section 5.9.12
MD-101-SMEM-EG-EL-SPC-
Cable lugs are correct type
8.5
& size
0001 Visual Check QC-CL-E-020 H H R
Section 5.9.12
Page 5 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Check if splicers are trained
9.1
and approved by client
0001 Visual Check QC-CL-E-021 H W R
Section 5.9.12
MD-101-SMEM-EG-EL-SPC-
Check cable set-up prior to
9.2
splice
0001 Visual Check QC-CL-E-021 H W R
Section 5.9.12
MD-101-SMEM-EG-EL-SPC-
Traceability record for every
9.4
splice is provided
0001 Visual Check QC-CL-E-021 H W R
Section 5.9.12
10.0 PRE-COMMISSIONING
MD-101-SMEM-EG-EL-
Visual and mechanical
10.1
check of low voltage cables
SPC-0002 Visual Check QC-CL-E-018 H W R
Section 5.2
MD-101-SMEM-EG-EL-
Phase identification test as Measure and Visual
10.2
required
SPC-0002
Check
QC-CL-E-022 H W R
Section 5.2
Page 6 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
MD-101-SMEM-EG-EL-
Measure and Visual
10.3 Insulation resistance test SPC-0002
Check
QC-CL-E-022 H W R
Section 5.2
MD-101-SMEM-EG-EL-
Measure and Visual
10.4 Torque test as required SPC-0002
Check
QC-CL-E-024 H W R
Section 5.2
MD-101-SMEM-EG-EL-
Measure and Visual
10.6 Phase identification test SPC-0002
Check
QC-CL-E-022 H W R
Section 5.2.3
MD-101-SMEM-EG-EL-
Measure and Visual
10.7 Shield continuity test SPC-0002
Check
QC-CL-E-022 H W R
Section 5.2.3
MD-101-SMEM-EG-EL-
Measure and Visual
10.8 Insulation resistance test SPC-0002
Check
QC-CL-E-022 H W R
Section 5.2.3
MD-101-SMEM-EG-EL-
Measure and Visual
10.9 VLF AC Hi-pot test SPC-0002
Check
QC-CL-E-023 H W R
Section 5.2.3
Page 7 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR MV, LV, CONTROL CABLE EL-ITP-006 2-Feb-17 ELECTRICAL
INSPECTION RESPONSIBILITY
PROJECT PHASE
ITEM ACCEPTANCE Verifying Document & ASSIGNMENTS
& Quality Related Activity Reference REMARKS
NO. CRITERIA Form #
ACTIVITY CODE SBM JACOBS PMC
MD-101-SMEM-EG-EL-
Measure and Visual
10.10 Torque test as required SPC-0002
Check
QC-CL-E-024 H W R
Section 5.2.3
LEGEND
W Witness Inspection/Test H Hold Point for QC Inspection or Test RH Review and Approval of Documents
R Review of Documents
GENERAL NOTES
1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not
2 present.
3 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4 REVIEW POINT: Is processed through the Reviewing and result of Inspection or test report as a method of Ensuring the Inspection or test is in comfirmity with the Data
Page 8 of 8
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR CONDUITS & FITTINGS EL-ITP-007 ELECTRICAL
INSPECTION
PROJECT PHASE RESPONSIBILITY
ITEM ACCEPTANCE Verifying Document &
& Quality Related Activity Reference ASSIGNMENTS REMARKS
NO. CRITERIA Form #
ACTIVITY CODE
SBM JACOBS PMC
DOCUMENT
1.0
REVIEW
MATERIAL
2.0
RECEIVING
Page 1 of 4
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR CONDUITS & FITTINGS EL-ITP-007 ELECTRICAL
INSPECTION
PROJECT PHASE RESPONSIBILITY
ITEM ACCEPTANCE Verifying Document &
& Quality Related Activity Reference ASSIGNMENTS REMARKS
NO. CRITERIA Form #
ACTIVITY CODE
SBM JACOBS PMC
MD-101-SMEM-EG-EL-
Conduit & Fittings to
SPC-0001
3.1 conform project
Section 5.8.1
Visual Check QCL-004 or 005 H W W
specification.
Section 5.8.2
MD-101-SMEM-EG-EL-
Check conduit spacing from
SPC-0001
3.2 other utilities
Section 5.8.1
Visual Check QCL-004 or 005 H W W
section 5.8.2
MD-101-SMEM-EG-EL-
Conduit support snd spacing SPC-0001
3.3
as per specification Section 5.8.1
Visual Check QCL-004 or 005 H W W
Section 5.8.2
MD-101-SMEM-EG-EL-
Field bend and radius are SPC-0001
3.4
correct as per specification Section 5.8.1
Visual Check QCL-006 OR 007 H W W
Section 5.8.2
MD-101-SMEM-EG-EL-
Proper fittings installed as
SPC-0001
3.5 per drawings &
Section 5.8.1
Visual Check QCL-006 OR 007 H W W
specifications.
Section 5.8.2
Page 2 of 4
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR CONDUITS & FITTINGS EL-ITP-007 ELECTRICAL
INSPECTION
PROJECT PHASE RESPONSIBILITY
ITEM ACCEPTANCE Verifying Document &
& Quality Related Activity Reference ASSIGNMENTS REMARKS
NO. CRITERIA Form #
ACTIVITY CODE
SBM JACOBS PMC
MD-101-SMEM-EG-EL-
SPC-0001
Conduit permanently &
3.6
effectively grounded.
Section 5.8.1 Visual Check QCL-004 or 005 H W W
Section 5.8.2
MD-101-SMEM-EG-EL-
Finall inspection of conduit prior SPC-0001
3.8
to cable pulling / installation Section 5.8.1
Visual Check QCL-004 or 005 H W W
Section 5.8.2
Page 3 of 4
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR CONDUITS & FITTINGS EL-ITP-007 ELECTRICAL
INSPECTION
PROJECT PHASE RESPONSIBILITY
ITEM ACCEPTANCE Verifying Document &
& Quality Related Activity Reference ASSIGNMENTS REMARKS
NO. CRITERIA Form #
ACTIVITY CODE
SBM JACOBS PMC
4.0 Pre-Commissioning
LEGEND
W Witness Inspection/Test H Hold Point for QC Inspection or Test RH Review and Approval of Documents
R Review of Documents
GENERAL NOTES
1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
2 is not present.
3 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4 REVIEW POINT: Is processed through the Reviewing and result of Inspection or test report as a method of Ensuring the Inspection or test is in comfirmity with the Data
Page 4 of 4
ITP No. DATE DISCIPLINE
INSPECTION AND TEST PLAN
ITP- PVC Pipes Sleeves EL-ITP-008 2-Feb-17 ELECTRICAL
INSPECTION
RESPONSIBILITY
ITEM PROJECT PHASE & ACCEPTANCE Verifying Document &
Quality Related Activity Reference ASSIGNMENTS REMARKS
NO. ACTIVITY CODE CRITERIA Form #
SBM JACOBS PMC
DOCUMENT
1.0
REVIEW
MD-101-SMEM-EG-EL-SPC-
Ensure All Drawings are issued
1.1
for Construction
0001 Visual Check Approved Drawing H R R
Section 4.5
MD-101-SMEM-EG-EL-SPC-
Ensure Materials Approved Material Approved
1.2
Prior to Installation
0001 Visual Check
Document
H R R
Section 5.2
MATERIAL
2.0
RECEIVING
MD-101-SMEM-EG-EL-SPC-
Storage, Handling and
2.1
Preservation Visual Inspection
0001 Visual Check QCL-001 H W R
Section 5.3
Manufactured Rigid Heavy Duty
MD-101-SMEM-EG-EL-SPC-
PVC Conduit
2.2
Material Receiving Visual
0001 Visual Check QCL-001 H W R
Section 5.3
Inspection
3.0 INSTALLATION
LEGEND
W Witness Inspection/Test H Hold Point for QC Inspection and Test RH Review and Approval of Documents
R Review of Documents
GENERAL NOTES
1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
2 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
3 attendance.
4 REVIEW POINT : Is Processed through the Reviewing and Result of Inspection or test report as a method of Ensuring the Inspection or test is in comfirmity with the Data
Page 1 of 1
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR OIL AND DRY TYPE DISTRIBUTION TRANSFORMER EL-ITP-009 2-Feb-2017 ELECTRICAL
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ACCEPTANCE Verifying Document & ASSIGNMENTS
Quality Related Activity Reference REMARKS
NO. ACTIVITY CODE CRITERIA Form #
SBM JACOBS PMC
DOCUMENT
1.0
REVIEW
MD-101-SMEM-EG-EL-SPC-
Ensure All Drawings are issued for
1.1
Construction.
0001 Visual Check Approved Drawing R R R
Section 4.5
MD-101-SMEM-EG-EL-SPC-
Ensure Materials Approved Prior to Material Approved
1.2
Installation.
0001 Visual Check
Document
R R R
Section 5.2
MATERIAL
2.0
RECEIVING
MD-101-SMEM-EG-EL-SPC-
Transformer Storage, Handling, and
2.1
Preservation Visual Inspection
0001 Visual Check QC-CL-E-064 H W R
Section 5.3
MD-101-SMEM-EG-EL-SPC-
Transformer Material Receiving Visual
2.2
Inspection
0001 Visual Check QC-CL-E-064 H W R
Section 5.3
MD-101-SMEM-EG-EL-SPC-
Transformer Accessories Material
2.3
Receiving Visual Inspection
0001 Visual Check QC-CL-E-064 H W R
Section 5.3
MD-101-SMEM-EG-EL-SPC-
Check the area are clean and free of
3.1
debris. Ready for installation.
0001 Visual Check QC-CL-E-065 H W R
Section 5.4.1
Check complete assembly for MD-101-SMEM-EG-EL-SPC-
3.2 mechanical damage and missing parts 0001 Visual Check QC-CL-E-066 H W R
as equipment inventory Section 5.5.1
Concrete foundation for MD-101-SMEM-EG-EL-SPC-
3.3 proper level and orientation 0001 Visual Check QC-CL-E-066 H W R
of cables Section 5.5.1
Page 1 of 5
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR OIL AND DRY TYPE DISTRIBUTION TRANSFORMER EL-ITP-009 2-Feb-2017 ELECTRICAL
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ACCEPTANCE Verifying Document & ASSIGNMENTS
Quality Related Activity Reference REMARKS
NO. ACTIVITY CODE CRITERIA Form #
SBM JACOBS PMC
Page 2 of 5
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR OIL AND DRY TYPE DISTRIBUTION TRANSFORMER EL-ITP-009 2-Feb-2017 ELECTRICAL
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ACCEPTANCE Verifying Document & ASSIGNMENTS
Quality Related Activity Reference REMARKS
NO. ACTIVITY CODE CRITERIA Form #
SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Check the area are clean and free of
4.1
debris. Ready for installation.
0001 Visual Check QC-CL-E-065 H W R
Section 5.4.1
Dry-type transformers shall be suitable
MD-101-SMEM-EG-EL-SPC-
for indoor or outdoor installation as
4.2
specified on the
0005 Visual Check QC-CL-E-067 H W R
Section 5.5.1
data sheets.
Each transformer shall be fitted with a
nameplate. The name plate shall not be MD-101-SMEM-EG-EL-SPC-
4.3 fixed to any portion of the transformer 0005 Visual Check QC-CL-E-067 H W R
that is required to be removed for Section 5.1.6
maintenance.
All metal parts of each transformer shall
MD-101-SMEM-EG-EL-SPC-
be electrically bonded. Transformer
4.4
shall be connected to the main earth
0005 Visual Check QC-CL-E-067 H W R
Section 5.1.5
grid
All terminals shall be clearly marked to
MD-101-SMEM-EG-EL-SPC-
identify the phase connections in
4.5
accordance with the connection
0005 Visual Check QC-CL-E-067 H W R
Section 5.5.8
diagram on the rating plate.
MD-101-SMEM-EG-EL-SPC-
Identification and warning
4.6
labels installed.
0005 Visual Check QC-CL-E-067 H W R
Section 5.1.6
Page 3 of 5
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR OIL AND DRY TYPE DISTRIBUTION TRANSFORMER EL-ITP-009 2-Feb-2017 ELECTRICAL
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ACCEPTANCE Verifying Document & ASSIGNMENTS
Quality Related Activity Reference REMARKS
NO. ACTIVITY CODE CRITERIA Form #
SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Visual and mechanical 0002
5.1
check of Transformer. Section 5.1
Visual Check QC-CL-E-066 H W R
Section 5.5
MD-101-SMEM-EG-EL-SPC-
Contact resistance
0002 Measure and
5.2 measurement for all bolted
Section 5.1 Visual Check
QC-CL-E-069 H H R
connection.
Section 5.5
MD-101-SMEM-EG-EL-SPC-
Insulation resistance and 0002 Measure and
5.3
polarization index test. Section 5.1 Visual Check
QC-CL-E-068 H H R
Section 5.5
MD-101-SMEM-EG-EL-SPC-
Power factor test on 0002 Measure and Test forms will be submitted at the
5.4
bushing and windings Section 5.1 Visual Check
Vendor Test Form H H R time of testing
Section 5.5
MD-101-SMEM-EG-EL-SPC-
0002 Measure and Test forms will be submitted at the
5.5 Winding resistance test
Section 5.1 Visual Check
Vendor Test Form H H R time of testing
Section 5.5
MD-101-SMEM-EG-EL-SPC-
0002 Measure and Test forms will be submitted at the
5.6 Turn ratio test
Section 5.1 Visual Check
Vendor Test Form H H R time of testing
Section 5.5
Page 4 of 5
ITP No. DATE DISCIPLINE:
INSPECTION AND TEST PLAN
ITP FOR OIL AND DRY TYPE DISTRIBUTION TRANSFORMER EL-ITP-009 2-Feb-2017 ELECTRICAL
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & ACCEPTANCE Verifying Document & ASSIGNMENTS
Quality Related Activity Reference REMARKS
NO. ACTIVITY CODE CRITERIA Form #
SBM JACOBS PMC
MD-101-SMEM-EG-EL-SPC-
Over potential test(AC high 0002 Measure and Test forms will be submitted at the
5.7
pot test) Section 5.1 Visual Check
Vendor Test Form H H R time of testing
Section 5.5
MD-101-SMEM-EG-EL-SPC-
0002 Measure and Test forms will be submitted at the
5.8 Oil filtrations
Section 5.1 Visual Check
Vendor Test Form H H R time of testing
Section 5.5
MD-101-SMEM-EG-EL-SPC-
0002 Measure and Test forms will be submitted at the
5.9 Oil sample test
Section 5.1 Visual Check
Vendor Test Form H H R time of testing
Section 5.5
MD-101-SMEM-EG-EL-SPC-
Functional testing of
0002 Measure and Test forms will be submitted at the
5.10 auxiliary wiring and
Section 5.1 Visual Check
Vendor Test Form H H R time of testing
components.
Section 5.5
LEGEND
W Witness Inspection/Test H Hold Point for QC Inspection or Test RH Review and Approval of Documents
R Review of Documents
GENERAL NOTES
1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
2 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
3 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4 REVIEW POINT: Is processed through the Reviewing and result of Inspection or test report as a method of Ensuring the Inspection or test is in comfirmity with the Data
Page 5 of 5
CHECKLIST NUMBER DATE RFI NUMBER
INSPECTION CHECKLIST
LV Power & Control Cables Termination Checklist QC-EL-A-004 2-Feb-17 15KB-64-RFI-000
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
MD-101-SMEM-EG-EL-
1 The construction drawings and documents is the final edition.
SPC-0001
The cable rating, size, number of core is complying with cable MD-101-SMEM-EG-EL-
2
schedule / connection drawings SPC-0001
The cable tag installed, and the tag description is complying MD-101-SMEM-EG-EL-
3
with termination schedule SPC-0001
The type and size of cable lug is correct. The crimping of lug is MD-101-SMEM-EG-EL-
4
good without loose or crack. SPC-0001
The cable/wires dressing inside terminal chamber is MD-101-SMEM-EG-EL-
5
acceptable. SPC-0001
The terminal block, wire marker and cable number is according MD-101-SMEM-EG-EL-
6
to the connection list and meet specification requirement. SPC-0001
The terminal block, terminal and lug is fastened without loose MD-101-SMEM-EG-EL-
7
and no stress on terminals. SPC-0001
MD-101-SMEM-EG-EL-
8 The entrance of cable is sealed
SPC-0001
Cable gland size & installation is correct and the gland is MD-101-SMEM-EG-EL-
9
bonded with grounding grid. SPC-0001
After termination of cable, Insulation resistance test has been MD-101-SMEM-EG-EL-
10
carried out SPC-0001
All wires are restored after insulation /continuity test and MD-101-SMEM-EG-EL-
11
terminations are tight well SPC-0001
All the cable is fastened and aligned properly where the cable MD-101-SMEM-EG-EL-
12
enters in to the panel or terminal box. SPC-0001
The torque test has been checked and recorded in QC Form # QC-CL-E- MD-101-SMEM-EG-EL-
13
024 as per specification and vendor recommendation. SPC-0001
The surround of work area is kept clean and the inner of panel MD-101-SMEM-EG-EL-
14
is clean. SPC-0001
REMARKS:
Contractor Jacobs
Construction Department
Work is Complete and Ready for Inspection:
QC Supervisor
Quality Record Approved:
Page 1 of 1
CHECKLIST NUMBER DATE RFI NUMBER
INSPECTION CHECKLIST
Dry-type Transformer Installation Checklist QC-EL-A-005
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
MD-101-SMEM-EG-EL-
1 Check the area clean and ready for installation.
SPC-0001
MD-101-SMEM-EG-EL-
4 Check transformer nameplate against data sheet.
SPC-0002
MD-101-SMEM-EG-EL-
6 Check all cable connection for tightness.
SPC-0002
MD-101-SMEM-EG-EL-
7 Check cable glands for waterproofing.
SPC-0002
MD-101-SMEM-EG-EL-
8 Check terminal box sealed correctly and terminal .
SPC-0002
Check terminal box sealed correctly and clearly marked to identify the
MD-101-SMEM-EG-EL-
9 phase connections in accordance with the connection diagram on the rating
SPC-0002
plate.
MD-101-SMEM-EG-EL-
10 Identification and warning labels installed.
SPC-0002
MD-101-SMEM-EG-EL-
11 Earthing as per detailed drawings.
SPC-0002
MD-101-SMEM-EG-EL-
12 Check earthing connections to main grid.
SPC-0002
MD-101-SMEM-EG-EL-
13 Check transformer are clean, dry and dust-free.
SPC-0002
REMARKS:
Contractor Jacobs
Construction Department
Work is Complete and Ready for Inspection:
Name, Initials and Date:
QC Supervisor
Quality Record Approved:
Name, Sign and Date:
Page 1 of 1
CHECKLIST NUMBER DATE RFI NUMBER
INSPECTION CHECKLIST
Electrical Aboveground Cable Pulling Checklist QC-EL-A-006 2-Feb-17
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
WITNESS HOLD
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
MD-101-SMEM-EG-EL-
3 Bend radius correct as per specification and free of deformity
SPC-0001
MD-101-SMEM-EG-EL-
4 Cable support spacing as per drawing and specification
SPC-0001
MD-101-SMEM-EG-EL-
5 Installation neat and evenly spaced
SPC-0001
MD-101-SMEM-EG-EL-
7 Cable ties as per drawing and specification
SPC-0001
Junction boxes size and type are levelled and positioned MD-101-SMEM-EG-EL-
8
correctly as per drawing. SPC-0001
MD-101-SMEM-EG-EL-
9 Verify cable is free of surface damage
SPC-0001
Insulation Test record for all power, control and instrumentation wire MD-101-SMEM-EG-EL-
10
and cables ( QC form # QC-CL-E-022) SPC-0001
MD-101-SMEM-EG-EL-
11 All revisions recorded on "As built" drawing
SPC-0001
REMARKS:
Contractor Jacobs
Construction Department
Work is Complete and Ready for Inspection:
QC Supervisor
Quality Record Approved:
Page 1 of 1
CHECKLIST NUMBER DATE RFI NUMBER
INSPECTION CHECKLIST
Electrical Underground Cable Pulling Checklist QC-EL-A-007
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
WITNESS HOLD
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Inspect, IR test and record all cables on reels before they are MD-101-SMEM-EG-
3
laid in trench EL-SPC-0001
The cable drum has been set up to ensure the cable pulling is in accordance
MD-101-SMEM-EG-
4 with the direction of pull indicated on the drum
EL-SPC-0001
(The lead end of the cable coming from the top of the drum)
Cable Rollers installed as required and additional cable rollers installed at any MD-101-SMEM-EG-
11
change of direction EL-SPC-0001
After cable installation ensure the cable ends are sealed to prevent ingress of MD-101-SMEM-EG-
13
moisture or foreign matter EL-SPC-0001
MD-101-SMEM-EG-
14 All revisions recorded on "As built" drawing
EL-SPC-0001
REMARKS:
Contractor Jacobs
Construction Department
Work is Complete and Ready for Inspection:
Name, Initials and Date:
QC Supervisor
Quality Record Approved:
Page 1 of 1
CHECKLIST NUMBER DATE RFI NUMBER
INSPECTION CHECKLIST
Conduit Checklist - RGS (Above Ground) QC-EL-A-008
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
WITNESS HOLD
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
MD-101-SMEM-EG-
10 Seals and drains installed per drawings
EL-SPC-0001
MD-101-SMEM-EG-
11 Conduit permanently and effectively earthed
EL-SPC-0001
Screwed, ABS and PVC-coated conduits installed as per MD-101-SMEM-EG-
12
drawing EL-SPC-0001
PVC insulated steel flexible conduit installed with proper bending MD-101-SMEM-EG-
13
radius and with standard fittings EL-SPC-0001
Junction boxes levelled and supported as per drawing with MD-101-SMEM-EG-
14
proper hubs, locknuts and bushings installed EL-SPC-0001
Installation in accordance with specification, referenced code MD-101-SMEM-EG-
15
and standards EL-SPC-0001
MD-101-SMEM-EG-
16 Relative deficiencies list closed out
EL-SPC-0001
REMARKS:
Contractor Jacobs
Construction Department
Work is Complete and Ready for Inspection:
Name, Initials and Date:
QC Supervisor
Quality Record Approved:
Name, Sign and Date:
Page 1 of 1
CHECKLIST NUMBER DATE RFI NUMBER
INSPECTION CHECKLIST
Conduit Checklist (Under Ground) QC-EL-A-009
PROJECT TITLE CONTRACTOR / SUBCONTRACTOR
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Trenching checked for location, elevation and level, and it is free MD-101-SMEM-EG-
1
of debris EL-SPC-0001
Trench location, elevation, depth, form and conduit size conform MD-101-SMEM-EG-
2
to drawing EL-SPC-0001
MD-101-SMEM-EG-
3 Dimensions checked for cable protection conduit
EL-SPC-0001
Conduit field bend radius is correct as per drawing. Check that MD-101-SMEM-EG-
4
bends are free of any defect, as per specification. EL-SPC-0001
MD-101-SMEM-EG-
5 Trenching checked for interference with underground piping
EL-SPC-0001
MD-101-SMEM-EG-
6 Conduit seals are installed on all exposed concrete pouring pipe ends
EL-SPC-0001
Road crossings for installation of spare sleeves as called for on MD-101-SMEM-EG-
7
drawing. These spare pipes shall have caps on the ends EL-SPC-0001
After concrete is in place, conduits checked for free of damage or MD-101-SMEM-EG-
8
deformation. EL-SPC-0001
MD-101-SMEM-EG-
9 Backfill work and compaction test performer as per specification
EL-SPC-0001
MD-101-SMEM-EG-
10 Pipe ends filled with specified sealant (after cable installation)
EL-SPC-0001
MD-101-SMEM-EG-
11 Installation of cable sleeve, Cable marker under roadways
EL-SPC-0001
MD-101-SMEM-EG-
12 All revisions recorded on "As built" drawing
EL-SPC-0001
MD-101-SMEM-EG-
13 Relative deficiencies list closed-out
EL-SPC-0001
REMARKS:
Contractor Jacobs
Construction Department
Work is Complete and Ready for Inspection:
Name, Initials and Date:
QC Supervisor
Quality Record Approved:
Name, Sign and Date:
Page 1 of 1