ITP3002 - HDPE Liner Recovery Pond
ITP3002 - HDPE Liner Recovery Pond
T Testing CS
P Perform CEM
I Inspection QI
CWI
R Review & Approve: Documents are to be submitted for review. Work shall not proceed until approval of the document has
been obtained.
RI
NDE
W Witness Point: Notification of authorized personel required.
AQ
H Hold Point: Mandatory, do not proceed without presence of authorized inspection personnel or sign waiver. CON
S Surveillance: Sub-Project Inspector may carry out Surveillance of work in progress. No notification is required.
FORM 000.509.F70001 1
INSPECTION TEST PLAN
FOR HDPE LINER INSTALLATION - RECOVERY POND
DESCRIPTION PROJECT NAME PROJECT NUMBER
2 of 4 Pages
UMM WU'AL PHOSPHOGYPSUM STACK SYSTEM UMM WU'AL PHOSPHATE PROJECT 14-KB-075
CLIENT CONTRACTOR DOCUMENT NUMBER ISSUE DATE
FLUOR/MA'ADEN M.M.AL-HARBI & Partners Co. Ltd. MD-512-0721-QD-QC-ITP-3002 10-Jul-15
W Witness Point: Notification of authorized personel required. RFI - Request for Inspection
C70101A - Soil Inspection Checklist
C70102A - Field Compaction Test Record
H Hold Point: Mandatory, do not proceed without presence of authorized inspection personnel or sign waiver. C70103A - Density of Soil in place by the sand-Cone Method
C70104A - Survey Report
C70105A - Soil Density Test Log
S Surveillance: Sub-Project Inspector may carry out Surveillance of work in progress. No notification is required.
INSPECTION TEST PLAN
FOR HDPE LINER INSTALLATION - RECOVERY POND
DESCRIPTION PROJECT NAME PROJECT NUMBER
3 of 4 Pages
UMM WU'AL PHOSPHOGYPSUM STACK SYSTEM UMM WU'AL PHOSPHATE PROJECT 14-KB-075
CLIENT CONTRACTOR DOCUMENT NUMBER ISSUE DATE
FLUOR/MA'ADEN M. M. AL-HARBI & Partners Co. Ltd. MD-512-0721-QD-QC-ITP-3002 10-Jul-15
3.2 Surface Water Control & Base MD-512-07ZZ-EG-CV-SPC- Visual The base of of the construction are shall be maintained well- CONS, QA/QC & RFI H S R -
Maintenance 2107 Rev A01 , Section 3.0 drained prior to and during liner installation. Liner work QI
areas shall be maintained well-drained and dry to prevent
uplift of the liner installation.
INSPECTION TEST PLAN
FOR HDPE LINER INSTALLATION - RECOVERY POND
DESCRIPTION PROJECT NAME PROJECT NUMBER
4 of 4 Pages
UMM WU'AL PHOSPHOGYPSUM STACK SYSTEM UMM WU'AL PHOSPHATE PROJECT 14-KB-075
CLIENT CONTRACTOR DOCUMENT NUMBER ISSUE DATE
FLUOR/MA'ADEN M. M. AL-HARBI & Partners Co. Ltd. MD-512-0721-QD-QC-ITP-3002 10-Jul-15
4.1 On Site Storage MD-512-07ZZ-EG-CV-SPC- Visual On-site storage shall be as needed to protect the liner rolls CONS, QA/QC & RFI H W S -
2107 Rev A01 , Section from excessive accumulations of soil, gypsum or water on QI
4.0,4.1, 4.2 the liner surfaces, heat, mechanical abrasion, puncture and
vehicular traffic. Liner rolls shall be stored on a firm, dry,
elevated surface in a protected storage area designated by
the Owner. The liner rolls shall not be stacked more than
three rolls high, or as otherwise recommended by the Liner
Manufacturer.
4.2.4 Equipment, Personnel & Mat'l MST-3006 Visual/Review MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 Section 4.2, 4.3, CONST RFI H W S -
4.2.5 Welding of Joints MST-3006 Visual 4.3.1, 4.3.2 QA/QC/QI Panel Seaming form
4.2.6 Check cleanliness & joint lappi MST-3006 Visual H W S -
4.2.7 Joints Information MST-3006 Visual/Review MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 Section CONST Panel Placement Form
4.2.8 Trial Welds MST-3006 Test/ Review/Visual 5.0,5.1,5.2,5.3, 5.4, 5.5, 5.6, 5.7 QA/QC/QI Trial Weld Information H W S
4.2.9 Welded Joint check MST-3006 Test/ Review/Visual Non-destructive Test Form
4.2.10 Weld Repair check MST-3006 Test/ Review/Visual Non-destructive Test Form
5.0 Field & Laboratory Test
Requirement
5.1 Shear Test ASTM D6392 /MST-3006 Test/ Review/Visual MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 section 4.3.1 (i) QA/QC & QI Test Report H W S -
5.2 Peel Test ASTM D6392/MST-3006 Test/ Review/Visual MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 section 4.3.1 (ii) QA/QC & QI Test Report H W S -
5.3 Air PressureTesting ASTM D5820/MST-3006 Test/ Review/Visual MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 section 5.3 QA/QC & QI Test Report H W S -
5.4 Vacuum BoxTesting ASTM D4437 & D5641/ Test/ Review/Visual MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 section 5.3 And as QA/QC & QI Test Report H W S -
MST-3006 per manufacturer recommendation
5.5 Sampling Destructive Testing MST-3006 Test/ Review/Visual MD-512-07ZZ-EG-CV-SPC-2107 Rev A01 section 5.4 QA/QC & QI Test Report H W S -
DOCUMENT NUMBER
INSPECTION TEST PLAN FOR HDPE LINER
INSTALLATION - RECOVERY POND MD-512-0721-QD-QC-ITP-3002
Revision A01
Umm Wu'al Phosphate Project Umm Wuál Phosphate Project
Umm Wuál Phosphogypsum Stack System
Issue Date 10-Jul-15 1 Of 4 pages
Contract No.: 14-KB-045
A01 10-Jul-15 Issued for Review and Approval CTPeril QA/QC RTGloria
Document No.
MD-512-0721-QD-QC-ITP-3002
MAADEN ALUMINUM
COMPLEX
SPECIFICATIONS