TOMBIM Claims - VPSS Jobs - CO Yomi Edith Rev.2
TOMBIM Claims - VPSS Jobs - CO Yomi Edith Rev.2
STORAGE OF FABRICATED SPOOLS & SCOPE GROWTH ON FIREWATER LINE SPOOL MODIFICATION (COST IMPACT)
Tombim- Demobilized Equipment withheld @ WAV 20th March 2022 - 26th Tombim Equipment was trapped in WAV
3 N/A yard at Onne after demobilization from USD 22,993.59
jetty after Offshore Demobilization March 2022
Offshore
Vendor (Kenergy) -Demobilized Equipment withheld 20th March 2022 - 26th Vendor (Kenergy) Equipment was trapped in
4 N/A WAV yard at Onne after demobilization from USD 6,945.76
@ WAV jetty after Offshore Demobilization March 2022
Offshore
Tombim- Unsuccessful initial mobilization of
23rd April 2022 - 27th Not allowed access to idoho,return via eket to
5 N/A personnel and equipment in respect to the shutdown USD 21,531.63
April 2022 PH stayed in the hotel then went back
scope
offshores on the 28th April
Legend
Cleared
Not Cleared
Meeting Remarks
ACT)
ass
)
ee attached breakdown cost
Discounted
Milestone Payment Schedule - IDOHO BP Topside Tie-in Fabrication (Agreement No: VPSS/ETF/TNO/001)
STORAGE OF FABRICATED SPOOLS & SCOPE GROWTH AND FIREWATER LINE SPOOL MODIFICATION (COST IMPACT)
S/N Claim Description Breakdown Timing Justification of Claims Due Amount INVOICE NO Meeting Remarks
Vendor (Kenergy) -Demobilized Equipment withheld 20th March 2022 - 26th Vendor (Kenergy) Equipment was trapped in
4 WAV yard at Onne after demobilization from USD 6,945.76 None yet ass
@ WAV jetty after Offshore Demobilization March 2022
Offshore
Tombim- Unsuccessful initial mobilization of
23rd April 2022 - 27th Not allowed access to idoho,return via eket to
5 personnel and equipment in respect to the shutdown USD 21,531.63 None yet See attached mail correspondence + Breakdown cost
April 2022 PH stayed in the hotel then went back
scope
offshores on the 28th April
Grand Total
USD 303,655.71
USD 255,000.00
USD 133,845.05
USD 48,655.71
Already approved by TenOil