Professional Documents
Culture Documents
Installation of Telephone & Data System
Installation of Telephone & Data System
Installation of Telephone & Data System
Relevant Specification Section / Contract ReferencMethod Statement for the installation Telephone and Data system
Remarks:
Transmitted by :
Name & Signature: Mr.Kumar Devan Designation : Sr.Project Manager Date: 22-Aug-23
Received by :
F-PR-05.4-28
A111-DBS-WK2-ARE-MOS-ELV-003
METHOD STATEMENT
FOR THE INSTALLATION OF TELEPHONE & DATA SYSTEM
SUBMITTED FOR:
CONSULTANT :
EMPLOYER REPRESENTATIVE :
Signature
Date
A111-DBS-WK2-ARE-MOS-ELV-003
CONTENTS
2. REFERENCE DOCUMENTS
3. EQUIPMENT
4. MATERIALS
5. RESPONSIBLE PERSONNEL
6. PROCEDURE
7. QUALITY CONTROL
8. SAFETY
This procedure defines the methods to be adapted for the installation structural cabling
system solution. This document ensures the work to be conducted at site are compliance
with approved architecture diagram and material submittal. work method statement is
prepared for each task on a particular worksite; the group of work method statements are
then packaged and included in the overall Construction Safety Plan. This method statement
deals with Structural Cabling system solution, SCS will be implemented to support data,
voice, and video services under a common physical infrastructure.
2. REFERENCE DOCUMENTS
• Project Specifications
• Approved shop drawings
• Approved material submittals
3. EQUIPMENT
• Tool Box
• Digital Multimeter
• Cable Punching tools
• Wire cutter
• Crimping tool
• Fluke testing tool
• Tracers
• Measuring tape.
• Ladders.
• Scaffolding
• Pulling spring
• Technician Hand tool kit
A111-DBS-WK2-ARE-MOS-ELV-003
4. MATERIALS
5. RESPONSIBLE PERSONNEL
The personnel stated below shall be responsible for the implementation of this method
statement and the installation procedures recommended by the approved drawing &
specification.
6. PROCEDURE
General
Termination
• Cable termination shall be made in accordance with manufacture instruction.
• Termination schedule shall be followed in all types of cable.
• Follow Manufacturer’s Guideline for Angled Entry Cable Terminations in tight
locations.
• The cable must be identified properly on both ends to ensure it is terminated in the
correct position.
• Cables shall be identified at feeders i.e. the sending and receiving ends.
• Using a proper sheath removal tool, remove the cable sheath in accordance with
best practices, applicable standards, and the termination equipment manufacturer's
specifications.
• Cable installation should not significantly deform the cable jacket.
• Termination of data outlets/connectors should be accomplished according to the
manufacturer's specifications.
• Check wiring at the racks and will be have necessary enough length to panels
A111-DBS-WK2-ARE-MOS-ELV-003
Installation of Faceplates
Installing a faceplate for telephone data involves setting up the physical components that allow you
to connect telephone devices to a network. Here's the installation procedure:
• Choose a suitable location on the wall where you want to install the telephone faceplate.
• Place the faceplate against the wall at the chosen location. Ensure that the mounting
holes on the faceplate align with the holes on the wall. If the faceplate has screws and
wall anchors, insert the anchors into the holes on the wall and then screw the faceplate
onto the anchors.
• Connect the Cat-6 cable.
• Once the cables are connected to their respective terminals, use a screwdriver to tighten
the terminal screws. Make sure the cables are securely fastened to prevent accidental
disconnection.
• Open the packaging of the Cat-6 patch panel and remove it from its protective sleeve.
Check the rear of the patch panel for cable management and cable routing options.
• Hold the patch panel in position and align the mounting holes on the patch panel with the
rack mount screws and nuts you placed earlier. Carefully slide the patch panel into place,
ensuring that it's level and properly aligned.
• Use a screwdriver to tighten the screws on the front of the patch panel, securing it to the
rack.
• Organize the network cables that will connect to the patch panel. Strip the outer
insulation of the Cat-6 cables and arrange the individual pairs according to the color-
A111-DBS-WK2-ARE-MOS-ELV-003
coding standards
• Terminate each cable to its corresponding port on the patch panel.
• Use cable management accessories such as cable ties, cable organizers to keep the cables
neat and organized.
• Choose a suitable location for the rack, considering factors like weight distribution,
access to power and networking, and ventilation.
• Ensure the floor is level and can support the weight of the fully assembled rack and its
equipment.
• Carefully unbox the rack and lay out all components to ensure everything is present and
undamaged.
• Place the rack-mount equipment onto the rack's horizontal crossbars. Follow proper
guidelines for spacing and weight distribution.
• Secure the equipment using the provided screws, nuts, and bolts. Make sure the
equipment is securely fastened.
• Adjust the rack's feet or leveling pads to achieve stability.
A111-DBS-WK2-ARE-MOS-ELV-003
QUALITY CONTROL
• QCE along with Project Engineer and Site Supervisor will monitor that all components are
installed as per the contract specifications and approved submittals.
• Inspection Request (IR) shall be submitted to the Main Contractor/Consultant after
completion of installation of riser pipes along with testing.
7. SAFETY
• Work will commence as per safety regulations laid down in the contract specification and
project safety plan under the supervision of safety personnel.
• All personal protective equipment shall be used as appropriate according to the nature of
job and Proper safety harness to be used, if required.
• Housekeeping shall be of good standard and all cut lengths and debris shall be removed.
• Ensure that proper scaffolding/ ladders are available.
• Ensure that shafts are adequately blocked above and below the working level, so that no fall
of debris/ materials takes place.
Fire
• In case of fire call immediately to the fire department.
• All the major or minor accidents to be reported and recorded.
Chemical caution
• No chemical used for in this particular activity
A111-DBS-WK2-ARE-MOS-ELV-003
Others
The above activities are found to be as per contract requirements are ready for The above activities are correct and released for the
release. next activity.
Checked by:
a. Subcon Site or Site Engineer b.MainCon Site or QC Engnr (MEP) Verified by (Consultant Engineer)
Note : Checking and approved by : ………………… shall not relieve the contractor from his obligation to perform the work in accordance with
other contract documents and HSE requirements . This inspection checklist is a guide and shall be considered in the routine inspections
BUT not limited to it
A111-DBS-WK2-ARE-MOS-ELV-003
ARE Drawings
Scope of Work, Material
Approved by ACG, Every Submission: Before Approved Method Statement
1.2 Method Statement Approval, Responsibility, Project Specification QA/QC Engineer H R/A
Approved Material Commencing of activity form
ITP and Risk assessment
Submittal
3 Installation Activities
Approved Shop QA/QC Engineer,
3.1 Preparation of Location Approved Drawings Route, Location, Elevation Drawings and Every installation Setup Site Site Inspection Form H W/R
coordinates Engineer/Supervisor
- Check against applicable
data sheet/ drawings
Mounting of equipment - Where applicable, verify
with complete hazardous area classification
accessories: and IP rating
Complies with QA/QC Engineer,
ONU. Installation details & - Installation as per telephone
3.2 installation details and Every Installation Site Site inspection Form H W/R
Fiber patch panel. Lay out drawing data layout IFC drawing.
layout drawing Engineer/Supervisor
Copper patch panel. - Correct locations, support
RJ45 outlet. details or orientation and
Racks. alignment.
-Correct fixtures tag number
-No obstructions and Verify
A111-DBS-WK2-ARE-MOS-ELV-003
NAME: Mr. Vipin . K NAME: Mr. Baha Mohammed Mr.Tonny Hanna NAME: Mr. Sudhakar
ADDITIONAL COMMENTS:
The Work mentioned above has complied with the Specifications, Approved Drawings and Method Statement.
ACG: Consultant in
ARE: Site Engineer ARE: QA/QC Engineer HAI: Engineer in Charge
Charge
Name
Signature
A111-DBS-WK2-ARE-MOS-ELV-003
12.RISK ASSESSMENT
TASK HAZARD INITIAL MITIGATION RESIDUAL RISK
Sr.
Description of Task Step Hazard Description Hazard Effect Who or What might be harmed? C P R Controls Measures and/or Recovery Measures C P R ALARM LEVEL
No.
-Ensure is any special training required shall be given prior
to site mobilization (scaffolders, UL inspector, crane
Unfamiliar with the operators, Hand power tools, ladder inspection, Riggers,
location, situation Injury and equipment handling etc.)
and site regulations violation of Equipment, materials and
1 Manpower mobilization 3 2 M -HSE orientation shall be carried out for all personnel prior 3 1 L LOW
that may result to site safety workers involved to mobilization.
slipping and tripping rules
-Toolbox talk/site induction awareness.
hazard
-All personnel to be fully briefed on the task and
responsibility
-Personnel will be trained on manual handling techniques.
-Use of Mechanical handling equipment where possible.
Injury to back, -Good Housekeeping measure will be enforced in order to
Manual handling of Slips, trips and fall All workers involved in the
2 sprains and 3 2 M prevent slips, trips and falls. 3 1 L LOW
materials or equipment hazard activity
fracture -Materials will be stored in designated areas.
-Provide adequate PPE such as hand glove, google and full
coveralls.
-Place appropriate signage to warn of workers and
Entry of passerby.
3 Signs and barricade unauthorized Injury Workers 2 2 L -Only workers connected to the work should be allowed at 2 1 L LOW
person the area.
-Place barricade around the work area.
-Only essential personnel will be in the vicinity of transport
operations.
Vehicle running into Injury to -All personnel to wear high visibility clothing. All
4 Vehicle movement Workers 3 3 M 3 1 L LOW
personnel personnel movements to be barricade off
-Heavy equipment maneuvering is not allowed without
Banks man.
Overturning of -Only trained and authorized personnel to carry out of the
mobile Scaffold fall task
of person falling -Ensure the PTW in place and task briefing by supervisor to
objects angle work force
grinder for GI tray Injury due to -Ensure proper working platform with complete fall
cutting Hot work slips, Fall due protection
5 Scaffolding Workers 4 4 H 1 5 5 LOW
entanglement using to uneven -Secure the tools and objects kept on the platform
solvent for PVC floor surfaces -Ensure the full body harness and 100% tie off
conduit joints dust -Ensure the safe access working platform
Use of threading Die -Ensure the scaffold platform is properly erected with “safe
for GI conduit sharp to use “tag
edge of existing tray -Hot work permit to be obtained and ensure that there is no
A111-DBS-WK2-ARE-MOS-ELV-003
major injury combustible material near cutting work
1)Only light work off short duration and work in which the
Injury due to operative can maintain secure hand and foot hold can be
slips, Fall due undertaken from a ladder
6 Use of Ladder Falling from Height All personnel’s 3 4 H 2 4 L LOW
to uneven 2)Never try to overreach with any ladder
floor surfaces 3)Check the ladder is of suitable quality for industrial use
and is in good condition.
-Replace/repair floor surface to maintain an even surface
Injury due to -Report any unsafe condition
slips, Fall due -Report all accidents, injuries and illness
to uneven
7 General work area Unsafe conditions, All personnel’s 3 3 M -Do not store excess number of combustibles in work area. 3 1 L LOW
floor surfaces,
debris, -Keep an aisle clear.
blocked aisles -Know location of fire extinguisher and alarm devices.
-Practice evacuation procedures.
Lifting
Sandstorm &Heavy activity
wind (Adverse executing in Major injury or fatality Loss of -Do not allow any lifting operations at time of heavy wind
8 Environment Aspects 4 4 H 4 2 M MEDIUM
Working heavy wind property speed.
environment). speed
condition
-The work area shall be kept clean and clear of debris and
waste material as far as is possible, and shall be cleaned as
the work progresses.
- Good housekeeping at all areas is maintained & observed
Health risk to
10 Housekeeping Waste Workers 3 3 M - All the generated waste should be collected & disposed to 3 1 L LOW
personnel
their designated waste bin.
- Maintain emergency accesses, entrances, exits & aisle free
from any obstruction/blockage
- Maintain a good cable and hose management at all times