Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

COVER FEATURE

Spliced Bulb-Tee Girders Bring


Strength and Grace to Pueblo's
Main Street Viaduct
The new $7.6 million Main Street Viaduct in Pueblo, Colorado, is a
six-span precast prestressed concrete bulb-tee girder bridge, spliced
together with post-tensioning. The overall length of the structure is
807ft (246 m) with a maximum central span of 774 ft (53 m). There
are eight girder lines with girders varying in depth from 72 in. (7 829
mm) at the ends to 96 in. (2438 mm) at the center, creating an
attractive haunched effect. The project was constructed within the
designated 72-month time frame and was under budget. This article
Jessie B. Fitzgerald, P.E.
Bridge Department Manager
discusses the design alternatives and structura l design considerations.
LONCO, In c. Production, transportation and erection of the precast concrete
Denver, Colorado components are also highlighted.

he city of Pueblo, Colorado, has This refocu s in the city's outlook

T a rich heritage going back to the


era when mining, railroads and
steel mills provided the main liveli-
has raised the awareness of the livabil-
ity of the urban area, and projects that
enhance and beautify the town are
hood for its people. With a current given the highest priority. As a symbol
population of 100,000, Pueblo is well of a new future for this revitalized
known for its inherent natural beauty, city , a new bridge was to be built to
vibrant history , cultural diversity and replace an old deteriorated steel truss
classic buildings. structure, which did not meet the high
In the last decade, however, with the standards of the community.
Thomas W. Stelmack downsizing of the steel industry , the Named the Main Street Viaduct, the
P.E., S.E. citizens of Pueblo have been forced to bridge crosses over 12 railroad tracks ,
Senior Bridge Engineer search for alternate avenues of eco- the Arkansas River and "B" Street.
Finl ey McN ary En gineers, Inc.
Denve r, Colorado nomic development. Fortunately , in Because of the bridge ' s significance,
the past several years , tourism has function, aesthetics and cost became
been growing and retirement commu- extremely important requirements.
nities are on the rise. Beyond that, Several challenges were presented
however, there is a spirit of revitaliza- to the planners in the preliminary de-
tion in the city and a civic renaissance. sign phase:

40 PCI JOURNAL
Fig. 1. Main Street Viaduct, Pueblo, Colorado. This award w inning spliced precast, prestressed concrete bulb-tee girder bridge is
only the second structure of its kind to be built in th e state of Co lorado .

• The old bridge would have to be de- crete bulb-tee girders spliced together A steel structure was also investi-
molished without disrupting existing with post-tensioning. gated, but following a life cycle cost
facilities or polluting the environ- The advantages of this latter system study, the city found the precast con-
ment. are structural efficiency , guaranteed crete structure to be a more durable
• The new bridge would need to be in quality control, a fast track construc- system with a lower long-term mainte-
harmony and complement the adja- tion schedule, long-term durability and nance cost.
cent structures. economy. The new Main Street Viaduct (see
• Delicate negotiations were to be Comparative costs of the variou s Fig. I) is a six span, bulb-tee girder
conducted with various railroad of- structural systems were prepared and bridge spliced together with post-
ficials and other agencies with re- the advantages of the precast bulb-tee tensioning. There are eight girder lines
gard to right-of-way and financial system soon became apparent. Be- with girders varying in depth from
participation. cause of the overall geometry and 72 in. (1829 mm) at midspan to 96 in.
• The bridge would need to meet alignment, the rai lroad right-of-way (2438 mm) at the piers, thus creating
strength requirements set by limits , and the complex and skewed an attractive haunched effect. The
AASHTO and the Colorado Depart- configuration of rai !road tracks be- overall length of the structure is 807 ft
ment of Transportation (CDOT). neath the structure, the opportunity to (246 m) and the largest span at the
• The long-term durability of the place a pier in this location was re- centerline of the bridge is 174 ft (53
structure and maintenance costs stricted to only one spot. This created m). Fig. 2 shows the plan and eleva-
were an important issue. the need to span long distances with- tion of the bridge.
• The bridge had to be built on a fast out shoring and to skew the railroad In addition to the bulb-tee girders,
construction schedule. pier, resulting in two spans with vary- permanent precast, prestressed deck
• Lastly , but most importantly, the ing length girders. panel s were used instead of conven-
structure was to be constructed With this substructure arrangement, tional forming. The stress in g of the
within a tight budget. a traditional system of precast !-gird- post-tensioning tendons in the girders
LONCO, Inc . (the Engineer of ers spanning pier-to-pier was investi- was done in three phases: first, to con-
Record) , Denver, Colorado, was com- gated . However , the girders would nect the precast girder segments; next,
missioned to assess potential structural have to have been spaced so closely to apply additional force to the girders
systems for the replacement bridge. [20 girder lines in an 80 ft (24.4 m) after placing the deck panels; and
This included a steel girder option, a wide structure] that the scheme was lastly to stress the composite section
precast 1-girder option and a third op- considered unreasonable from a cost after the final deck topping and di-
tion, namely, precast, prestressed con- standpoint. ap hragms were cast. Thus , the deck

November-December 1996 41
STA. 6+68.00

"'"'

!
2Ho:l
_ _ _ _ L_ _ _ ___ -ti-
J:
1!
I'
I:

;
. \
+
l t\
i
\~
I
i \
l ~

EXTOO OF RAIIJ\().1.0 RAil TVJI . EClll SlOES

~
SCIJ..E: 1" • JO'

907'-2 1 2" B.F. ABuT. 1 10 l!.F. ABUT. 7

...1... ...1... ...1... ...1... ...1... ...1... ...1... ...1...

-u ELEVATION
Q Sc.-.LE: 1" • JO'
c....
0 * fi£VAOON AT FINISHED GIWlE {:Z " A90V£ TOP OF DECK)
c 0 q_ ERJOC[

:D
z
l> Fig. 2. Genera l layout plan and elevation of bri dge.
r
z
0
<
<D
3
0"
<D
1--- - - - - ---------- ---- - -···-- ·- ·------ !'?'-<>" ........ ------- ------- -- ·------ ........ - .. - . -- -----------· ----· -- ---- -------- - - --
6
<D
,.....
C)
<D ........ +- - - - ------- ------~- ··----- - -- - - - ----+'l;...
iir-r---.-.!''"'-<>"!;.
, ---t-+,!;::U,-0"~--
3
0"
~
I f------........,.
~·~...-~-+-----'';';~~
....!-------+-----··\1~~~
· ~..___ ------- .1 ._ ._ ._
(()
(()
CJ)

I

'r... -- I
!
I
~ I
...'r I

cb 1 'A. e to' .... • 7Y-4'


cb
m!!£AL IECTIOII
ll:llldi'I/F·'f'---

~---· t'""' t .... ' \ .PD:


\
4 ~ ....
I I I
U0113
\
'
'
rr-------,~~~~~~~-+--~~~~----~~~._~~~~--~~~~~~~-----~~--~~~~0

~--:--~-~-- ·- ~~--~----~..--~~~~~--~----~..~~~~---------__:__:___~------~~----~------~-t----r~

..,. Fi g. 3. Typical secti on and slab plan of bridge.


w
____8____ _
t
·rt··------_. _. . .!.!: ~ .!=~ ·

:.!:.!'!~~. ":::::~ ~: !::' !~::.:. ·:!..!~:::• !..~"~· '"~~:.~·~~~-=~j":.:!r·:~ ~:.::.:":!"'":o:~-;:.:~·!=:7'


l:f IHolncl~cl In U•o 11\d prtco to r lt-l'kl . 111, Pr .. tn..ecl Buill T Unit.
'M!oft opprovod by tho ["1!\M or o flll n l - of tock "loll nt Will H por•IUe4
rolnforclntoiMI .
Ofl A$Ttll A708 llftOOOlod

·h · 1.1. Rtolnforo l nt projootlnt fr• tiM to, of tho tlrd.r oiM\1 M


r ol ntotco\ntn.... notMr.,..lr o<ll .
..,,~,. oootecl . O... . d ooe~tlllt"" g lrO.r

-jL...+-- __,. ,•"'---------------j


- --t-----'•c:·-o-.____ . g: ~~.,~~'"ch.;)'':,•t~,•~:-~~~~~;'~i:~:: ·~=•,;:-!::~,.~ . "'t -"- o - t l o r . - l r o ( d - . . lo .. U•-

\,.. = U.(tGl ' 2J


L.II . Str onch \o tho .-.rowlcatlon uood lor LOlli
Tho tope of oil '11\rct.n ohali boro~J9h
R'llo~at\011 Stronch '"tho plano .
1\oatiMiot oppro•l-tol'/1 /4• -..1\tude .

PLAII

--- P1R 4 PLAIII!!WJ.,,.. U.e 1/2• otl-ler on oil oernere, exo.pt .. noted .

::E~e:,:;:~~~~~~::~~:f::~:!~!~;:~r ~=~ ~=~::::~o~O:~':~;:::-~!I~::::::~~::r~ 1 !~t

[[J}3
I ;.-~- ~ .
c_..r• ..oeedlnt tiM eJ,.chd Hrllber II)' •r• tMn
-.1 tiM Hole elruotlone •Y lleetl t• 1te eodJ'I"'hd.
ti2' bee-• tiM Glltlo\pahd llouMh . .,. 110t e•f:t

~:u:~:J~~~~~::~~~::!:~~:n£:~!r.,~!iiUi!:or~:~:.~~.~~~ f~'r=~~ ·~,. to

-i--~- -! ~ f~~~re:::'!r~.-='~!:': 1 ::' .!::;..v::tooed. T-.poror)' broolnt eMil H -eoted to tiMo tlrHre prior

~~!ol'::'~='t:;.':,~~rr;:·~~!: !: !:!:r:~"!:.t.7:~::or~ ~oo~::~~~~:~, :":,!:~ ''~o:::~::, ~te


I
I
I
I
T
~
POST-Tn81Cfi! IC KQI..IOC[1

a o;rf, ,'b·-1 J./4~0


'J: str PM-TENSUI4:
Conoreh ttrentth t
,.,
f ' •l .. 4&00
,_,.,
pel

,.
I ·-·· I ·!e t'e ~eoo·,,,u.7t kiSill~7c:;r~:':~~;~:::{!!d:~!!:T.,.~
"
~[ [
---+'
.! ]
' 'I'
- !_: - ,_
~ I!I.IY A11011
1!111 ILOCI( DETM£. •
- 7000 ,.,
...,
170 !lei Lw Rei•Jot lon Slr.,..

---
..,J i,.., "'J J."'"
P!ll PLATI!!g'fs. •'"

'" ~~
~
•'I ,. .~ ···. g:

i.7t---------~),a~~~~------ ··o.NW ...... _


3/4..........
e !!iWI....
e .......
iJ
Q
<-
0
e~ ... e·•··"
c
JJ
z
)>
r
Fig. 4. Precast bulb-tee girder detail s.
panels played an important role in
supplying dead load to overcome 3'-7''
stresses from the second phase of
post-tensioning.
The preliminary and final design
phases of the bridge occurred from
May 1993 to August 1994. The project
was let out for bids on September 20,
1994, and the bridge was completed in
December 1995.
The total cost of the bridge project
(including ancillaries) was $7.6 mil-
lion.The new bridge is only the second
of its kind to be built in the state of
Colorado and the first in the Pueblo
area.

DESIGN ALTERNATIVES
The Structural Engineer, Finley Mc-
Nary Engineers, Inc., Denver, Col-
orado, performed the analysis of the
structure and assisted in the detailed
structural design of the precast, pre-
stressed concrete girders.
Preliminary design work for the pro-
ject began in May 1993, with the final
design beginning in December of that
year. A number of different structure
types and span arrangements were
considered in the conceptual phase of
the project. Due to the restrictions of
the river dike and the numerous rail 0 0 0 0 0

0 0 0 0 0
tracks, there were not many options 0 0 0 0 0
for span layouts . The two basic
choices were a long span in the 250 to
300 ft (76.2 to 91.4 m) range over the 4" 4 Spa.
....
Arkansas River with shorter spans in
2'-3"
the railyard area (due to the limited
structure depth from the vertical clear-
ance available) and the chosen layout. Fig. 5. Typical prestress ing strand layout of bulb-tee girder.

Fig. 6. Girder segment layout showing stressing sequence for Girders D, E, F, C, B, G, H, A.

November-December 1996 45
...L
IMJO

! ILL
Ikl ...L
IMJO
..L
C<XJ
~~ JI<XJ

"U
Q
c....
0
c
J)
z
~ Fig. 7. Bridge erection Sequence 1.
z
0
<
CD
3
rr
CD

6
CD
()
CD
3
rr ,_.--"1
~
I I

....CD
CD
0>

·--------------- ----------------------- --------------------


!
'
i

-
i
...L ~

~
a.,_~IJ«JtPrltrl&
H. Sfrw s.:.td IWI-Tflflklnal Ttn:*ln.

, ...(?,_, I

:!:J Fig. 8 . Bridge erection Seq uence 2.


very close spacing required of the
standard girders, they were not as eco-
nomical as the other two options and
were discarded.
The steel plate girders were esti-
mated to be slightly higher in initial
cost than the spliced bulb-tee girders.
However, once the life-cycle cost
analysis including maintenance was
done, and the aesthetic preferences of
the client were taken into account,
spliced concrete girders were chosen
as the recommended alternate for final
design.
The first spliced and post-tensioned
girder bridge in Colorado was de-
signed by the Colorado Department of
Transportation (CDOT) Staff Bridge
Fig. 9. Reinforcing cage with post-tensioning ducts for fabricating bulb-tee girder. section. The spans were 164, 183 and
164 ft (50, 55.8 and 50 m). The piers
The longer span layout was not eco- span layout was determined, the only were skewed at approximately 45 de-
nomical because it saved only one pier feasible structure types were steel grees and it spanned over 1-76 and a
and because of the constructability im- plate girders, standard precast concrete railroad track just north of Denver.
pacts of erecting a long span in a diffi- girders, and spliced and post-tensioned Therefore, accurate price information
cult access area. Once the approximate precast bulb-tee girders. Due to the was available on a bulb-tee system

Fig. 10. Formwork for bulb-tee girder and stressing arrange- Fig . 11. Front view of bulb-tee girder showing protruding pre-
ment prior to concreting. tensioning strands and ducts for post-tensioning.

48 PCI JOURNAL
and the cost estimate was thought to be
on target. The owner felt comfortable
with this bridge type because a similar
structure had recently been built
successfully.

DESIGN CONSIDERATIONS
The following considerations had a
major impact on the design and layout
of the spliced bulb-tee girder design:

River Pier Locations


The piers near the Arkan sas River
were importa nt in determining the
structural type. It was desirable to keep
the piers out of the river as much as
possible and also to minimize the im- Fig. 12 . Side view of new ly fabricated bulb-tee girder.
pact to the dike on the north side of the
ri ver for pier construction. Therefore, a
main span of about 175 ft (53 .3 m) was
selected, which put the south pier at
the edge of the river during spring and
summer (while out of the water during
the winter month s when construction
would take place) and the north pier at
the north toe of the dike. Thi s span
length fit well with a spliced bulb-tee
girder design using 72 in. (1829 mm)
girders and haunching to 96 in. (2438
mm) at the piers.

Railroad Restrictions
The railroad owners had several re-
strictions concerning the new bridge
and its construction. First, the standard
horizontal clearance to the pier walls
Fig. 13. Bulb-tee gi rd ers were haul ed usi ng precaster' s standard tandem axle units.
and the temporary clearance to the
foundation excavation limited the pier
locations for the northern half of the
bridge. The alignment of the tracks
(curving with a tangent at about a 66-
degree skew) further limited the place-
ment of the piers. Due to the limited
vertical height available, spanning the
railroad was not even an option. There
was basicall y only on e location for
Pier 4 within the sets of tracks that met
the criteria and Pier 5 was located just
beyond the last track.
Another cri tical factor was the re-
striction against falsework. Again, due
to the closeness of the track spacing,
there was no space available to place
falsework for girder support prior to
completing the splices. Therefore, the
girder layout and erection sequence Fig. 14. Special precautions were taken by the precaster when hau ling the lengthy
were designed to allow for overhead bulb-tee girders in congested c ity streets.

November-December 1996 49
strong-back beams to be used. The
final factor was the impact of con-
struction on train scheduling. The
tracks are fairly active and the design
allowed the contractor to place the
girders in the time windows allowed
by the train schedules and still be able
to move the cranes out of the way
when trains passed.

Vertical Clearance at Railyard


The vertical profile of the bridge
had been set in the preliminary phase
and due to the existing touchdown
points of the bridge , a fairly steep
grade was required at the north end of
the bridge to obtain the minimum ver-
Fig. 15 . 154ft (47 m) long bulb-tee girder being hauled along highway in countryside.
tical clearance over the tracks for a
structure depth using the 72 in. (1829
mm) deep girders. When the last sur-
vey was done for final design and the
railroad made its final decision on pier
locations, the span layout had changed
from 150, 175, 152.5, 152.5 and 91 ft
(45.7, 53.3, 46.5, 46.5, and 27.7 m) in
preliminary design, to the final layout
of 152, 174, 164.5 , 155.5 and 88 ft
(46.3, 53, 50.1, 47.4, and 26.8 m).
Given the skew angle of Pier 4,
Span 3 actually varied from 180 to
149 ft (54.9 to 43 .7 m) and Span 4
varied from 171.3 to 140 ft (52.2 to
42.7 m). Due to the vertical clearance
restriction over the tracks di sc ussed
above, the increase in Span 3 became
critical because additional structure
Fig. 16. Post-tensioning of bulb-tee gi rders at bridge site. depth was not possi ble. The problem
was solved by using the standard bulb-
tee end block section [2 ft (0.61 m)
web width] over Piers 4 and 5. This
provided the required flexural and
shear capacity without requiring an in-
crease in structure depth or new forms
for the precaster.

Girder lengths and Weights


During the design of the bridge, it
was apparent that the girders would
probably be cast in Denver, approxi-
mately 120 miles ( 193 km) north of
Pueblo. Therefore, the shipping length
and weight of the girders were impor-
tant. This also played an important
role in the layout and design of the
girders, as the assumed limits for de-
sign were 175,000 lbs (79380 kg) and
Fig . 17. Erection of bulb-tee girders . 160ft (48.8 m).

50 PCI JOURNAL
Fig . 18. Bulb-tee girders in place.

STRUCTURAL SCHEME Some of the key features of the design


include: Fi g. 19. Diaphragms for brac ing bulb-
The basic structural scheme con-
1. Only two temporary bents were tee girders.
sisted of precast bulb-tee girders that
were spliced in place and post-ten- required for erection. All other sup-
sioned. Various structural details ofthe ports were provided by overhead depth. At Pier 4 (Girder Segment 5),
bridge are shown in Figs. 3, 4 and 5. strong-back beams. The beams were the section extended 15 ft (4.57 m) to
The girders were 72 in. (1829 mrn) attached to one girder at the precasting each side of the pier and 17.5 and 7.5
deep and haunched to 96 in. (2438 yard and then placed onto the previous ft (5 .33 and 2.29 m) at Pier 5 (Girder
mm) deep at Piers 2 and 3. The girders girder for support. Segment 7). In each case, the girder
contained pretensioned strands in the 2. At two critical areas of the struc- cantilevered beyond the pier and the
top and bottom of the girders and three ture, the standard end block section closure joint con s isted of the end
continuous post-tensioned tendons was used over Piers 4 and 5 for the re- block section, while the drop-in girder
with 19 0.6 in . (15.2 mm) diameter quired additional flexural and shear (Girder Segment 6) contained the end
strands in each . The erection scheme capacity . As stated above, no height block transition section.
is shown in detail in Figs. 6, 7 and 8. was available for additional structure 3. The closure joints also consisted
of 1 ft 4 in. (406 mm) wide, full depth
diaphragms between the girders. All
joints, except that near Pier 4, were
normal to the bridge centerline. At the
skewed Pier 4, the joint was a constant
15.5 ft (4.72 m) from the pier and the
diaphragm con sisted of two wall s in
each bay and stair-stepped across the
bridge. The joints and diaphragms
were reinforced with mild reinforcing
steel. The closure joint also consisted
of conventional mild reinforcing steel,
which provided moment capacity
across the joint prior to stressing the
tendons. This was critical due to the
erection sequence, which minimized
the number of falsework bents and
thus required some continuity across
the joint prior to placing the next
girder.
4. The erection sequence consisted
of three phases of stressing the longi-
tudinal post-tensioning. This was re-
Fig. 20. The stay-in-place panels were post-tensioned for continuity. quired in order not to overstress the

November-December 1996 51
to be stressed without overstressing
the girders.
All of the tendons extended the full
length of the bridge [approximately
740 ft (226 m) with major vertical de-
viations] and were stressed from each
end. The tendons were installed and
stressed by AVAR Construction Sys-
tems, Inc . from California and no
problems were encountered.

LONGITUDINAL GIRDER
DESIGN
The longitudinal girder analysis and
design was done using a two-dimen-
sional frame program with time-de-
pendent analysis capabilities. The pro-
Fig. 21. After stressing the deck panels, a cast-in-p lace topping was placed.
gram's name is Bridge Designer II and
it is also capable of easily analyzing a
girders during construction. Each ten- lowed the deck to be placed with a structure that is constructed in many
don duct was coupled across the clo- minimum amount of work occurring phases. In addition to the normal
sure joint between the girder pieces. over the rail tracks (i.e. , minimum frame program input of nodal coordi-
The first phase consisted of stressing labor in setting the form panels and no nates, section properties, element defi-
the first tendon after the closure joint labor required to remove the perma- nitions and applied loads, this program
had been cast. The second tendon was nent forms, as would be required for also allows time-dependent material
stressed after the precast deck panels standard forms). This was very desir- properties, prestressing tendons , and
had been placed on the girders. The able to the railroad because it also multiple erection phases by date.
last tendon was stressed on the com- minimized the possibility of dropping The details of the erection sequence
posite girder and deck section after the anything on the tracks below. Sec- are given in Figs. 6, 7 and 8 but the se-
cast-in-place deck slab had cured. ondly, the panels provided an interme- quence is basically as follow s:
The precast deck panels served two diate step of adding the weight of the 1. Erect the precast girder sections
purposes for this project. First, they al- deck slab, allowing the second tendon in pieces.

Fig. 22. Finished bridge.

52 PCI JOURNAL
2. Cast closure joints and di-
aphragms.
3. Stress the first tendon.
4. Place the precast deck panels.
5. Stress the second tendon.
6. Cast the deck.
7. Stress the third tendon.
8. Cast barriers and place wearing
surface.
Each of the above steps is modeled
in the analysis and the time schedule is
also taken into account. The girders
are made composite with the deck by
connecting the girders to the deck ele-
ments using vertical rigid links . The
centroids of both elements are offset
by the correct amount to result in the
proper composite section property.
Due to the skew of Pier 4, the span
lengths of all the girders vary in Spans
3 and 4. Therefore, a separate analysis
was made of the girders furthest north
and south and a hypothetical girder at
the structure centerline. The informa-
tion was then interpolated to design all
of the girders.
The General Contractor for the pro-
ject was Lawrence Construction Co.,
Littleton, Colorado.
The total contract amount between
the owner and Lawrence Construction
was $6,106,555 . The total contract
amount to fabricate, deliver and erect
the precast concrete products was
$1 ,076,830.
Fig. 23. Side vi ew of finish ed bridge.
PRODUCTION
HIGHLIGHTS
96 in. (2438 mrn) at the center. pulling a "rabbit" through the ducts.
The precast, prestressed concrete • 40 components [4553 lineal ft (1388 Any obstructions in the ducts were re-
components were fabricated at Rocky m)] of precast, prestressed concrete moved before shipping the girders to
Mountain Prestress, Inc. , at their plant BT -72 bulb-tee girders. the jobsite.
in Denver, Colorado. The company, a • 9 components [616 lineal ft (188 The haunched bulb-tee girders were
PCI Certified Producer Member, has m)] of 72 x 24 in. (1829 x 610 mm) cast in an adjustable soffit form that
had a long history for furnishing high precast, prestressed concrete box allowed for the girder depth to vary
quality products and superior delivery girders. These girders were used in from 72 to 96 in. ( 1829 to 2438 mm).
service in Colorado and other states. Span 6 but were not post-tensioned. Similar procedures were followed
A total of 731 precast, prestressed The concrete girder compressive with the post-tensioning duct.
concrete components were fabricated strength was 7500 psi (52 MPa). The Figs. 9, I 0, 11 and 12 show the vari-
for this project. A breakdown of the maximum girder length was 154ft 4 1/ 4 ous sequences in the fabrication of the
number and types of components is as in . (47 m) and the maximum girder bulb-tee girders .
follows: weight was 176 kips (782 kN.)
• 665 components [37 ,953 sq ft (3530 The BT -72 girders were cast during
m2) ) of 3 1h in. (89 mm) thick precast, the winter of 1994-95. Special care
HAULING PROCESS
prestressed concrete deck panels. was taken to accurately and firmly po- Special measures were taken by
• 16 components [1280 lineal ft (390 sition the three continuous post-ten- Rocky Mountain Prestress to ensure
m)] of haunched precast, prestressed sioning ducts and anchor plate assem- that the precast components would be
concrete bulb-tee girders , varying blies. After casting , the clearance transported safely from the plant to the
from 72 in. (1829 mrn) at the ends to through the ducts was checked by project site (see Figs. 13, 14 and 15).

November-December 1996 53
The 120 mile (193 km) journey south behind Abutment I. Segment I was CONCLUDING REMARKS
to Pueblo proved to be uneventful. erected by picking directly from the
This award winning bridge was
Most of the girders were hauled truck and placing in position with
completed on schedule in December
with the precaster' s standard tandem Crane I. Erection of Segments 2, 3
1995 and the facility is now fully op-
axle jeep units in front and back. The and 4 was accomplished by passing
erational. The finished structure met
four heaviest girders, ranging in girders in mid-air from Crane 1 to
all of the city's objectives:
weight from 164 to 176 kips (729 to Crane 2.
• The bridge is aesthetically pleasing
782 kN), required the use of a three- Erection of Segments 5, 6 and 7 was
and is in harmony with the sur-
axle jeep unit at the front of the girder completed after repositioning both
rounding buildings.
attached to the tractor and a tandem cranes to the railroad side of the struc-
• The project was finished within the
steering/dolly tandem jeep unit at the ture. Erection of these segments re-
allotted 12-month construction time
rear of the girder to limit wheel loads. quired setting times to be closely coor-
dinated with train schedules of two frame.
Moreover, because the total loaded
• It met budget.
weight of the tractor trailer assembly railroad lines running beneath Spans 5
In retrospect, the owner and all par-
exceeded 200 kips (889 kN), the Col- and 6. The free end of Segment 5 was
supported by a strong-back assembly ties involved in the design and con-
orado Department of Transportation
from the cantilevered end of Segment struction of the bridge are very
was involved in verifying that the
4. Segment 6 was supported by em- pleased with the end result. This was
route used to transport the precast
bedded corbel assemblies cast in the made possible because of the coopera-
components to the bridge site would
cantilevered ends of Segments 5 and tive team effort.
not overload any bridge structures
7. Segment 8 (box girders) was The Main Street Viaduct is already
along the way.
erected after all post-tensioning was a popular landmark in the City of
completed on Segments I through 7. Pueblo. Indeed, it is one more symbol
ERECTION SEQUENCE reflecting the resurgence of the city.
The erection of the precast compo-
Various construction stages of the nents, together with the various post-
bridge are shown in Figs. 16 through 21. tensioning operations took less than 5 CREDITS
Erection was accomplished using months to accomplish. Figs. 22 and 23
two 4100 Manitowac Track cranes be- show the finished bridge. Owner: City of Pueblo, Pueblo, Col-
ginning with the first two spans orado
(Spans I and 2) over the Arkansas AWARD WINNER
River. The erection was performed by Engineer of Record: LONCO, Inc.,
Stone River Inc. of Sandia Park, New In June I996, the bridge was given a Denver, Colorado
Mexico. Temporary support towers design award for "Best Bridge With a
Span Greater than I35 ft (41 m)" in Structural Engineer: Finley MeN ary
were erected by Lawrence Construc-
the I996 PCI Design A wards Pro- Engineers, Inc., Denver, Colorado
tion in Span I to support the ends of
Segments I and 2 and in Span 2 to gram. The jury's citation read:
General Contractor: Lawrence Con-
support the ends of Segments 3 and 4. "The use of precast concrete al- struction Co., Littleton, Colorado
Strong-back assemblies were used to lowed the designers to minimize
support the free end of Segment 3 the amount of falsework necessary, Precast Concrete Manufacturer: Rocky
from the cantilevered end of Segment especially compared to that needed Mountain Prestress, Inc., Denver,
2 and the free end of Segment 5 from if cast-in-place hammerheads Colorado
the cantilevered end of Segment 4. had been used. The erection pro-
Erection of Segments I through 4 cess respected a complicated site. Illustrations: The line drawings for
was accomplished by positioning The finished project blends well this article were supplied by
Crane I behind Abutment I. Crane 2 with the adjacent architecture and LONCO, Inc. The photographs were
was positioned down in the river bed the haunched girders, which are furnished by LONCO, Inc., Finley
between Piers 2 and 3. Trucks ac- difficult to make aesthetically McNary Engineers, Inc., and Rocky
cessed the site to a picking position pleasing." Mountain Prestress, Inc.

54 PCI JOURNAL

You might also like