Section No. : 4
Revision : 0
QUALITY ASSURANCE MANUAL Date : 01-11-2001
The following are simplified process flow charts to show the execution process through out
the IKL organization :
- IKL Contract Execution Flow Chart (attachment S.4.1)
- IKL Process –Quality Management System (attachment S.4.2)
The process, which is referred to above includes the process performed within IKL
organization or at the supplier / fabricator premises.
/conversion/tmp/activity_task_scratch/687090520.doc
PT. ISTANA KARANG LAUT Page No. : 2 of 7
Section No. : 4
Revision : 0
QUALITY ASSURANCE MANUAL Date : 01-11-2001
Each member of IKL’s staff is responsible for positively checking that when a code; or
recommended practice; a standard; or a Client’s specification is used in document or
drawing preparation it is the latest revision and is still applicable.
The responsibility of IKL staff for receipt, distribution, preparation, checking, approval
and filling of documentation is further defined in Attachment S.4.3. – Documentation
Table of Responsibility.
/conversion/tmp/activity_task_scratch/687090520.doc
PT. ISTANA KARANG LAUT Page No. : 3 of 7
Section No. : 4
Revision : 0
QUALITY ASSURANCE MANUAL Date : 01-11-2001
Each member of IKL’s staff is responsible to ensure the control of documents shall be
established with the following activities :
- To approve documents for adequacy prior to issue
- To review and update as necessary and re-approve documents
- To ensure that changes and the current revision status of documents are
identified.
- To ensure that relevant versions of applicable documents are available at points of
use.
- To ensure that documents remain legible and readily identifiable.
- To ensure that documents of external origin are identified and their distribution
controlled.
- To prevent the unintended use of obsolete documents.
The Engineering Manager is responsible for ensuring that all necessary updated
documentation, design software, codes and standards and applicable Customer
specification are available at the start of any new contract, and for ensuring that
superseded documentation, design software, codes and standards are withdrawn
from the files and kept in an inaccessible storage place.
The Engineering Manager shall also ensure that all codes, software used by IKL in its
normal engineering activities are kept up to date and obsolete copies are removed,
clearly marked “obsolete” and stored in an inaccessible storage place.
The Engineering Manager shall also ensure that all documents of external origin (i.e.
code, standard, Client specification, etc.) are identified and their distribution controlled.
/conversion/tmp/activity_task_scratch/687090520.doc
PT. ISTANA KARANG LAUT Page No. : 4 of 7
Section No. : 4
Revision : 0
QUALITY ASSURANCE MANUAL Date : 01-11-2001
The Project Manager is responsible for issuing updated documentation that which is
generated by IKL or received from the Client, Vendor or other source is issued
internally within IKL. He is also responsible for ensuring that superseded
documentation is withdrawn for :
Requisition(s)
Purchase Specification(s)
For the field / site document control, it is the responsibility of Quality Assurance /
Quality Control Inspector or Senior Quality Assurance/Quality Control Inspector (if
any) to :
(for EPSC project the above will be the responsibility of Engineering Team).
Only controlled copies of the Manual are permitted within the Quality
Management System. Controlled copies shall be issued by the Director who
shall maintain a register of the recipients of such copies. Each controlled copy
shall have a copy number with 01 being reserved for the Master Copy which
shall be retained in record system by the Director. The number of Controlled
copies shall be indicated on the inside cover of each Manual. Recipients of
Controlled copies shall receive all subsequent amendments under cover of a
transmittal note.
/conversion/tmp/activity_task_scratch/687090520.doc
PT. ISTANA KARANG LAUT Page No. : 5 of 7
Section No. : 4
Revision : 0
QUALITY ASSURANCE MANUAL Date : 01-11-2001
When any section of this Quality Assurance Manual has been revised more
than five (5) times, the Quality Assurance Manual shall be revised to a new
edition with all the revised section’s revision number reverted back to zero.
A record shall be made of all amendments by means of the index pages which
shall be part of this section of the Manual.
The Manual is divided into sections. Each page within each section has a page
number.
4.2.4.1 RESPONSIBILITY
a. The Director
The Director shall ensure that master copies of the following documents
are permanently held by IKL up to date.
Quality Assurance Manual
Quality Assurance Procedure
Reports of Quality system reviews
The Procurement Manager shall ensure that the following records are
retained by IKL for at least ten (10) years:
Purchase Order files
Supplier (Vendor) Quality Reports & Performance Follow Up Form
/conversion/tmp/activity_task_scratch/687090520.doc
PT. ISTANA KARANG LAUT Page No. : 7 of 7
Section No. : 4
Revision : 0
QUALITY ASSURANCE MANUAL Date : 01-11-2001
The Finance Manager shall ensure that the following records are retained
by IKL for at least ten (10) years :
Original copy of Purchase Order, Contract or any subsequent
amendments.
Original Budget and Budget Reports
4.4. ATTACHMENT
Attachment S.4.1. – IKL Contract Execution Flow Chart
Attachment S.4.2. – IKL Process – Based Quality Management System
Attachment S.4.3. – Documentation Table of Responsibility