Professional Documents
Culture Documents
02.specialized Scheduling Processes
02.specialized Scheduling Processes
02.specialized Scheduling Processes
This section of the course discusses special scheduling process capabilities of the Epicor
application.
Saving What-If Schedules
You may want to make several changes and evaluate each of these by printing the Schedule
Impact Report. You can save the What-If changes, make additional changes, and at any time
restore an earlier saved schedule. You can save an unlimited number of What-If reschedules.
Multi-Constraint Scheduling
The base application allows up to two resources to be assigned to each operation, and each of
these resources can be identified as constrained; that is, Finite Capacity is set for each resource.
This means that a job operation cannot be scheduled unless both resources are available at the
same time. This is determined by the calendars assigned to each resource and, if using finite
scheduling, the current load on each resource.
Example: There is a resource or group that is available 16 hours per day (based on the
availability of operators). Any job using that resource or group could be run at any time
during those 16 hours. Let us assume further that the resource requires a setup
operation for each job, but the setup operator is available only 8 hours per day. This
would constrain a job schedule that required the resource to be set up if no setup
resource is available.
Minimize WIP
The Minimize WIP feature allows Scheduling to reduce the gaps that can occur between
operations and assemblies during the Global Scheduling process. It causes this process to run the
scheduling engine an additional time against the jobs that meet a specific condition.
If Scheduling discovers that the Start Date on a job will occur before the Scheduled Start Date, it
forward schedules the job. After the new End Date is calculated for this job, it backward schedules
from that date, which tightens the points where the assemblies are placed within the schedule.
This allows child assemblies to have a Just In Time relationship with their parent assemblies. By
eliminating the unnecessary gaps between the assemblies, the jobs are scheduled more
accurately.
• Batch Scheduling
This section of the course reviews job batching functionality.
• Workshop - Save and Restore a Schedule
In this workshop, save and restore schedule for various jobs.
• Schedule Multi-Job
Use the Scheduling Multi-Job option to schedule a group of associated jobs as if it were a
single job. Jobs are associated via make-to-job relationships. This feature makes it
possible to schedule and re-arrange manufacturing jobs for a parent assembly and its
child subassemblies (called predecessor and successor jobs) all at the same time. Prior to
the introduction of this functionality, the scheduling planner had to watch linked jobs
closely to ensure that they were scheduled together so that all demands were met.
Batch Scheduling
This section of the course reviews job batching functionality.
The job batching feature enables you to combine two or more jobs that either partially, or
completely, use the same routing. It allows you to select an operation shared by the jobs and
indicate from which direction – backwards or forwards – you will combine the routing.
Important: Combine the operations from a start operation and then move backwards
or forwards through the routing. You cannot combine a range of operations that occur
in the middle of routing.
When the batching process is complete, a new job is created that manufactures the part
quantities defined on all the original source jobs.
Note: Always batch jobs that share similar operations. If you batch jobs that do not have similar
operations, you could get unexpected results.
Once you create a batched job, the Epicor application treats the job the same as a regular job. A
batched job can be scheduled and transactions can be placed against it. If necessary, you can
even batch together other batch jobs!
Important: To complete the Batch Scheduling course section, you must have the
Advanced Production License installed.
• Batch Jobs with Identical Methods
You can batch two jobs with identical methods of manufacture so that they can run
together for efficiency.
Create Jobs
In this workshop task, created two jobs for the EAD-400-BLK and EAD-400-RED parts.
Menu Path: Production Management > Job Management > General Operations > Job Entry
5. In the Req By field, select the date one month from today.
6. Click Save.
7. From the New menu, select New Demand Link > Make To Stock. At the bottom of
the Job sheet, the Make To Stock > Detail sheet displays.
9. Click Save.
10. From the Actions menu, select Job > Get Details. The Get Details window displays.
13. From the Actions menu, select Schedule > Job Scheduling. The Schedule Job
XXXX (where XXXX is your job number) window displays.
18. Repeat steps 1-16 to create another job for the EAD-400-RED part.
Batch Jobs
In this workshop task, batch the previously entered jobs.
Menu Path: Production Management > Scheduling > General Operations > Resource Scheduling
Board
Important: This program is not available in Classic Web Access.
1. In the Resource Group field, enter WLDS and press the Tab key. This is the Resource
Group used for Operation 40 on both previously entered jobs. The Operation 50 on both
jobs is subcontracted.
3. In the Operations grid, in the Batch column, select the check boxes for the two jobs
created in the previous workshop task.
4. From the Actions menu, select Batch Operations. The Batch Operations window
displays.
The Job Processing Mode options define if operations should be performed at the same
time or one before the other. Use the Concurrent option when two parts are created at the
same time; use the Sequential option when time for the operation will be accumulated for
the duration of the operation.
7. Select the Auto Receive check box. When selected, this check box indicates that labor or
receipt transactions against this batch operation will create automatic receipts to
inventory. If you use this feature, this receipt updates the quantity on hand on the part
record. The process is triggered when you post labor quantities against this batch
operation that exceed the quantities required for the sales order.
Normally, you will select this check box for the last operation on the assembly or the final
assembly. Parts are received to inventory at the current unit cost, based on the part
costing method (average, standard or last).
9. From the Batch Job Number field, record the job number_____________.
3. In the Job field, enter the batch job created in the Create a Batch workshop task and
press Tab.
5. From the Actions menu, select Schedule > Job Scheduling. The Schedule Job window
displays.
8. Click Save.
Review Jobs
In this workshop task, review all three previously entered jobs to see how the Job Batching
process affected the methods of manufacture used on the jobs.
Menu Path: Production Management > Job Management > General Operations > Job Tracker
2. In the Starting At field, enter the first job number created in the Create Jobs workshop
task and click Search.
3. In the Search Results grid, using the Ctrl key, select all three jobs created in the Create
Jobs and Batch Jobs workshop tasks.
4. Click OK.
5. In the Job field, verify the first job number created in the Create Jobs workshop task
displays. The Open status displays.
6. In the tree view, right-click on ASM: 0 EAD-400-BLK and select Tree > Expand Tree. The
first four operations in the method of manufacture are marked as complete. This is
because the operations 10, 20, 30, and 40 will be completed on the batch job. Operation
50 is subcontracted, so once the EAD-400-BLK part is received back from painting, it will
be received back to the original job. As a result of the job receipt, operations 60 and 70 can
be worked on. Only material 40 (CS-060) in the method of manufacture is marked as
issued, because it belongs to operation 10. The rest of materials belong to operations 50,
60, and 70.
7. In the Standard toolbar, use the arrow button to select the second job created in
the Create Jobs workshop tasks. The Open status displays.
8. In the tree view, right-click on ASM: 0 EAD-400-RED and select Tree > Expand Tree. The
first four operations in the method of manufacture are marked as complete. This is
because the operations 10, 20, 30, and 40 will be completed on the batch job. Operation
50 is subcontracted, so once the EAD-400-RED part is received back from painting, it will
be received back to the original job. As a result of the job receipt, operations 60 and 70 can
be worked on. Only material 40 (CS-060) in the method of manufacture is marked as
issued, because it belongs to operation 10. The rest of materials belong to operations 50,
60, and 70.
9. In the Standard toolbar, use the arrow button to select the job created in the Batch
Jobs workshop task. The Open status display.
10. In the tree view, right-click on ASM: 0 EAD-400-BLK-0-40 and select Tree > Expand
Tree. The method of manufacture includes only first four operations and one material,
material 10 (CS-060). Material 10 is linked to operation 10 in the method. None of the
operations are complete or material issued because the job has not started yet. Once the
job operation 40 is complete, both parts will be sent to a subcontractor for painting. After
the subcontractor paints the parts, they are received back to their original jobs, in order to
complete work on operations 60 and 70.
11. In the tree view, under the Operations node, select Opr: 30 OP: FORM. The Job Details >
Operations > Detail sheet displays.
12. In the Production Per Machine pane, in the Est Hours field, verify 0.10 displays.
14. In the tree view, under the Materials node, select Mtl: 10 CS-060. The Job Details >
Materials > Detail sheet displays.
15. In the Quantity pane, in the Required Qty field, verify 1.60 displays.
17. In the Standard toolbar, use the arrow button to select the first job created in the Create
Jobs workshop task.
18. In the tree view, right-click on ASM: 0 EAD-400-BLK and select Tree > Expand Tree.
19. In the tree view, under the Operations node, select Opr: 30 OP: FORM. The Job Details >
Operations > Detail sheet displays.
20. In the Production Per Machine pane, in the Est Hours field, verify 0.05 displays. The
estimation hours are half the estimation hours on the batch job.
Note: Refer to the previously recorded Estimation Hours value to cross compare.
21. In the tree view, under the Materials node, select Mtl: 10 CS-060. The Job Details >
Materials > Detail sheet displays.
22. In the Quantity pane, in the Required Qty field, verify 0.80 displays. The required
material quantity is half the required quantity on the batch job.
Note: Refer to the previously recorder Required Quantity value to cross compare.
23. Repeat steps 17-22 to review details for the second job created in the Create
Jobs workshop task.
Menu Path: Production Management > Scheduling > General Operations > Job Scheduling Board
2. Move the job out one month. The Advanced Options 2381 window displays.
3. In the Move Option field, select Job - All Operations and click Schedule.
4. To the Schedule Move Warning message, click OK.
5. From the More Actions menu (three dots on the toolbar), select Save Schedule. Schedule
Maintenance displays.
6. In the Description field, enter XXX Class Exercise (where XXX are your initials).
7. Click OK.
Menu Path: Production Management > Scheduling > Reports > Schedule Impact
2. From the Actions menu, select the Restore Schedule command. Schedule
Maintenance displays.
3. In the Description field, search for and select XXX Class Exercise (where XXX are your
initials).
4. Click OK.
Menu Path: Production Management > Scheduling > Setup > Resource Group
Field Data
Calendar D5H8
In Bin MCH
Important: The Input Warehouse and Bin records must be entered only if the
AMM license is installed.
4. Click Save.
5. If the Capacity changed, therefore, the 'Generate Shop Capacity Process' will need to
be run the update ShopLoad records message displays, click OK.
6. From the New menu, select New Resource. The Resources > Detail sheet displays.
Field Data
Calendar D5H8
In Bin MCH
Important: The Input Warehouse and Bin records must be entered only if the
AMM license is installed.
9. In the Scheduling pane, clear the Use Resource Group Values check box.
10. In the Scheduling pane, in the Daily Production Capacity field, enter 8.00.
12. If the Capacity changed, therefore, the 'Generate Shop Capacity Process' will need to
be run the update ShopLoad records message displays, click OK.
Menu Path: Production Management > Job Management > General Operations > Job Entry
3. Click Save.
6. Navigate to the Job Details > Operations > Scheduling Resources > Detail sheet.
Field Data
9. Click Save.
3. Click Save.
Field Data
Schedule Backward
6. Click OK.
5. Click Save.
Menu Path: Production Management > Scheduling > Setup > Scheduling Priority Code
1. Click New.
2. In the Scheduling Code field, enter XXXNMW (where XXX are your initials).
3. In the Description field, enter XXX Normal - Minimize WIP (where XXX are your initials).
4. In the Priority Factor field, enter 30.
5. Verify the Schedule Backwards check box is selected.
6. Select the Minimize WIP check box.
7. Click Save.
8. Exit Scheduling Priority Code Maintenance.
Menu Path: Production Management > Job Management > General Operations > Job Entry
5. Click Save.
6. From the New menu, select New Demand Link > Make to Stock. The Job > Make To
Stock > Detail sheet displays.
9. From the Actions menu, select Job > Get Details. The Get Details window displays.
2. From the Actions menu, select Schedule > Job Scheduling. The Schedule Job window
displays.
4. From the Actions menu, select Schedule > Job Scheduling Board. The Job Scheduling
Board displays.
Note the job's current scheduled and the current start and end dates of the operations
and job.
3. From the Actions menu, select Schedule > Job Scheduling Board. The Job Scheduling
Board displays.
4. Double-click on the job number, all assemblies and subassemblies to expand them.
When a forward schedule is applied to a multi-level job, WIP is not minimized. A non-
critical path child assembly will start at the same time as the start of the lowest critical
path assembly.
In order for WIP to be automatically reduced, the job must bounce. A job will bounce if a
job schedule is prevented from being scheduled in the past.
2. In the Priority field, select XXX Normal - Minimize WIP (where XXX are your initials).
3. From the Actions menu, select Schedule > Job Scheduling. The Schedule Job window
displays.
5. From the Actions menu, select Schedule > Job Scheduling Board. The Job Scheduling
Board displays.
6. Double-click on the job number, all assemblies and subassemblies to expand them.
Because the job schedule was forced to bounce, WIP was minimized regardless of the
Forward schedule.