Professional Documents
Culture Documents
Final Id (2017)
Final Id (2017)
COLLEGE OF ENGINEERING
GROUP 9
TEAM MEMBERS
Eugene Bosiako
Dzedze Samuel
Sasu Samuel
Apasnaba Ajara
Adua Daniel
Table of Contents
TABLES................................................................................................................................................ 6
TABLE OF FIGURES........................................................................................................................... 7
1 LITERATURE REVIEW.............................................................................................................. 8
1.1 Geotechnical information:...................................................................................................... 9
3.2 METHODOLOGY............................................................................................................... 14
5 RECOMMENDATIONS............................................................................................................ 25
6 LIQUID WASTE MANAGEMENT........................................................................................... 26
6.1 METHODOLOGY............................................................................................................... 26
6.2 OBSERVATIONS............................................................................................................... 27
7 Drainage design........................................................................................................................... 34
7.1 Objective.............................................................................................................................. 34
8 EXECUTIVE SUMMARY......................................................................................................... 44
9 CHAPTER ONE.......................................................................................................................... 45
9.1 INTRODUCTION................................................................................................................ 45
10 CHAPTER TWO......................................................................................................................... 47
10.1 APPROACH AND METHODOLOGY...............................................................................47
10.4.2.1 Detailed Description of the State of Traffic Flows on the Ayeduase Road..............56
10.5.4 Alternative route from Ayeduase gate to kotei to reduce traffic flow...........................61
10.5.8 Sidewalks...................................................................................................................... 62
TABLES
Table 1 Domestic water requirements per person(students)................................................................11
TABLE OF FIGURES
1 LITERATURE REVIEW
The Government of Ghana, in its bid to promote and build a better Ghana has taken a step to
extend its developmental projects to the remote parts of the country. This it aims to achieve
through the formation of a new ministry – Ministry of Zongo and Inner City Development.
(MZICD). The purpose of this newly formed ministry is to enhance the livelihood of residents
of inner cities through the creation of a clean, habitable and sustainable environments in all
regions including the Ashanti region of Ghana where the focus community of this study –
Ayeduase and Kotei – is founded. Ayeduase and Kotei communities have been chosen to
benefit from this scheme and hence EDC3 2016/2017 Group 09 has been selected as
consultants on this project to undertake design of the civil engineering infrastructural works in
the project area. The components of infrastructural works to be designed include:
Road Network and Traffic management on main roads and at intersections
Drainage network
Water supply and distribution system
Solid and liquid waste management system
Water resources
The inception phase of this project took twelve (12) days – from the 6th to the 17th of
February, 2017. The purpose of this report to recount the methodology adopted on the project
and paint a vivid picture of the current situation in the study communities within allowances
permitted by the project boundaries.
The Ayeduase and Kotei communities and its environs has experienced a massive in
population since the establishment of KNUST in its suburbs. Increasing demands of the
growing population has placed stresses on existing infrastructure – housing, water, electricity
and social amenities such as schools and churches. This presents a major setback to the
development of Ghana as a country as it seeks to eradicate poverty, provide adequate amenities
for its citizenry and generally improve the quality of life of Ghanaians. Because about 90% of
the population in the study community are students it also poses a problem to KNUST in its
bid to be recognized as a leading university not only in Ghana but in Africa and in the world.
The inception aims at assessing the current situation, gathering facts and proposing a feasible
solution. Data gathered during the inception phase includes the following.
Drinking 2
Flushing of closets 24
Other needs 10
118
Total
Number of grids with low rise buildings = 4*20% of 1232 = 985.6 =986
Drinking 5
Total 75
Number of grids = 9
Total average daily water demand for the students and residents:
Provisions for general water requirements = 20% of total average demand = 210.433m 3/day
1
x 1052. 166=263 .042 m3 /day
Provisions for fire demand = 4
Grand total average daily water demand = 1052.166 + 210.433 + 263.042 = 1525.642m 3/day
3 SOLID WASTE MANAGEMENT
The solid waste to be generated at the proposed site will be considered as domestic waste. The
collection, handling and disposal of domestic solid waste shall be considered.
3.1 OBJECTIVES
The following are the objectives that will be considered under waste management.
Paper waste
Food waste
Plastic and rubber
Metals
Bottles and
Miscellaneous waste (mainly foil, takeaway, ceramics, and some food packages).
It was quite observed that plastic waste was going to be most the waste produced by volume
while textile virtually was not found in the domain of research. The main grouping of waste
found were as follows:
Paper waste- paper drinks, paper, sugar boxes, menstrual pads.
Organic Waste- peels of yam, plantain, kenkey.
Plastic and rubber Waste- water sachets, polythene, rubber packages.
Metallic Waste- can drinks, tin fish, milo tins, milk tins.
Bottles- disposable cups, mineral bottles, used pomade containers.
Miscellaneous – toilet roll, wood, takeaway packages.
Papers Plastics
Bottles Boxes
Kitchen wastes
Glass
Cardboard
Toner cartridges
Residents Hostels
Other than this, some of the inhabitants have resorted to the burning of their solid waste on the
premises of their homes. Due to the cost involved in disposing of their waste at the site, others
have also created an unauthorized dumping site locate. The waste at this location is treated
through the process of incineration as shown below.
Figure 3 Unauthorized dumping site
Other homes (mainly middle class) dispose of their waste in the same manner. However, the
difference lies in the location of the dumping site. The waste is sent to an un-engineered site
where the inhabitants pay a user fee of 80pesewas to deposit their waste in the skip on site. The
waste from the student hostels in the vicinity is collected by private services such as contractors
of cleaning services (Zoomlion Ghana, Asadu ventures, Zoom Alliance)
Description of the six main functional elements of solid waste management system:
Waste generation: these are activities in which materials are identified as no longer being of
value and are either thrown away or gathered together for disposal.
On-site handling, storage, and processing: this involves activities associated with the
handling, storage, and processing of solid wastes at or near the point of generation.
Collection: they involve activities association with the gathering of solid wastes and the
hauling of wastes to the location where the collection vehicle is emptied.
Transfer and transport: These activities are associated with
I. the transfer of wastes from the smaller collection vehicle to the larger transport
equipment.
II. the subsequent transport of the wastes, usually over long distance, to the disposal site.
Processing and recovery: These include techniques equipment and facilities used both to
improve the efficiency of the other functional elements and to recover useable materials,
conversion products, or energy from solid wastes.
Disposal: They are activities associated with ultimate disposal of solid wastes Interrelationship
of functional elements comprising a solid waste management system.
Figure 4 overflow at the dumping site
No Weapon 57 171
Jalex 32 96
Stone Castle 25 50
Adom Bi 87 261
Amen 58 174
Shalom 39 117
25 12 300
Low 0.6-1.0
Middle 0.8-1.5
High 1.1-4.5
5451
⇒ volume of waste for residents= =21 .804 m3 / day
250
109. 02
=7 .268=8
Number of 15m skips required = 15
3
We suggested that recycling, re-using and reduction in waste generation was the way
forward.
Other residents suggested that the assembly should employ reasonable number of
sanitary laborer’s in assisting in quarterly clean up exercises and assisting communal
labor once every month.
Ensuring that waste bins are placed at vantage points and regularly emptied would help
a great deal and ensuring that waste containers are always available at all refuse sites
and regularly carted away.
KMA should introduce modern trends in waste management e.g. solicit for funds from
corporate institutions.
Good basic personal hygiene should be imbued in home and school upbringing,
attitudinal change and commitment to keeping a clean city should be a concern for the
citizenry.
Assembly should adopt its own emergency collection unit to cater for failures of
agents.
KMA should embark on effective house to house collection and employ more people
to inspect and collect waste and include experts to monitor agents.
5 RECOMMENDATIONS
The existing high rise buildings should be provided with external chute systems to
easily and effectively move waste to the point of disposal.
The primary storage should be collected at the close of each working day or early
in the morning to avoid over storage which leads to support breeding of inspects
and other pathogens.
6 LIQUID WASTE MANAGEMENT
Wastewater to be collected and treated will be generated from the residents and the proposed
hostels with a systematic administration of activities that provide for the proper handling,
treatment and disposal of liquid waste/wastewater.
6.1 METHODOLOGY
The main problem with wastewater management in the area was with the treatment of the grey
water (sullage). Some of the households collected the grey waste along with the black into the
septic tank for treatment. However, a vast majority of the inhabitant in the area had no system in
place for the safe treatment and disposal of the grey wastewater.
For some of the households, the kitchen and bath wastewater is collected in buckets or basins and
is thrown into the street. Most of the hostels in the vicinity channeled their grey waste into the
existing drainage network which empties out into the Wiwi stream. A bucket had been placed in
the hole and the grey water was channeled into the bucket using a piece of ‘water hose’. The
waste water was then collected in the bucket till it was full and then poured out onto the street as
shown below.
Drinking 2
Flushing of closets 24
Other needs 10
Total 118
Number of grids with low rise buildings = 4*20% of 1232 = 985.6 =986
Drinking 5
Total 75
Number of grids = 9
Total average daily water demand for the students and residents:
Provisions for general water requirements = 20% of total average demand = 210.433m 3/day
1
x 1052. 166=263 .042 m3 /day
Provisions for fire demand = 4
Grand total average daily water demand = 1052.166 + 210.433 + 263.042 = 1525.642m 3/day
6.2.2 Waste Water Estimation
To determine the amount of waste water produced, 80% of the water demands calculated would be
taken.
1220.61
7 Drainage design
Generally, the topography of the site could be said to be gentle but gradually slopes into the stream
that joins the wiwi stream. The school of business which is opposite to the site is generally flat and
slopes into the stream. The drains are made in accordance with the topography of the area and
maximum flood levels.
7.1 Objective
Upgrading of existing drains if capacity of such drains is not satisfactory.
Designing of good drainage systems to ensure that flooding of the site will be avoided
always.
Designing of drains to meet the economic needs of the society and for easy maintenance
at a low cost.
1
Q Hydrology = 360 x 0.85 x 0.73 x 36 = 0.0621m3/s
Table 10 Typical cross section of a drain
2 1
A 3 2
Q= R S
n
2 1
3 2
AxR xS
Q hydraulics = n
2
3 . 142 xW W
+W ( H− )
For a U-drain, Area, A = 8 2
Area = 0.3214m2
3 . 142 xW W
+2( H − )
Perimeter, P = 2 2 = 1.542m
Area 0.3214
= =0.208
R= perimeter 1.542
Since the Q hydraulics is greater than the Q hydrology, the assumed drain size is appropriate and can
accommodate the discharge; hence assumed drain dimensions are chosen and applied to all.
1
Height of tank is assumed as = volume 3 + dead volume (0.15)
3
Height = √ 6102. 496+0. 15=18. 27 m
√ √
V ∗4 6102. 496∗4
D= h∗π
=
18. 27∗π
=20. 62 m
The minimum pressure needed to reach the furthest section of the area is 15m.
The height of the elevated tank is calculated below.
From the energy equation,
p1 + z 1 = p2 + z 2 + h f where;
p1= pressure∈the tank
z 1 = elevation of tank
p2 = minimum pressure
z 2 = elevation of the furthest part = 262 m
h f = head loss
Q=0.015m3/s
Q=v x A
Assume v= 1m/s
2
πd
0.015= 1 x
4
D=
√ 0.015 x 4
π
D = 0.138m
Q= v x A
v x π (0.15)
0.015 =
4
V=0.9m/s
−6
Kinematic viscosity = 497 x 10
¿¿
vD
Re =
v
0.9 x 0.15
Re = −6
1.006 x 10
Re =133663.37
By using Barr’s equation to find lambda
Lambda= 0.034
lambda x l 2
Hf = Q
12.1 x d
Hf = 5.46m
p1 + z 1 = p2 + z 2 + h f
z 1 = 15 + 251.1 +5.46
z 1=271.56
Braithwaite steel
Glass reinforced plastic
7.11.1 Properties of suggested materials
Table 12 properties of material used for elevated tank
After comparing the two materials, it was decided that Braithwater would be the better option
based on its properties.
To this end, the M/s ED C 3 2016/17 Civil Groups have been shortlisted to undertake the design
proposals of the Civil Engineering Infrastructure Works in the area. Civil 3 students (Group 7)
have been assigned to undertake the design proposals of the Civil Engineering Infrastructure
Works in the area. Inception site investigation was held on April 16 and 17, 2014, the site
investigation focused on identifying problems in the area that require
Surface types
Road lengths and width;
Typical cross-sectional features
Extent of deterioration
Show areas to be developed.
8.2.2 Traffic Management
• Provision of a detailed description of the state of traffic flows on the Ayeduase road showing
the main challenges.
The layout of the existing road network showing and types of surfaces to be provided is shown
below.
Six roads were considered from the project area. The width of the roads and the drainages were
taken with the aid of a measurement tape rule. The lengths of the road however were taken using
individual paces of group members.
Description
Based on the field reconnaissance conducted, it was observed that the route one (from
Continental supermarket to Abaase junction) as indicated on the map is paved (bituminous
surface). The length of the road was estimated to be 1082.85m. This was obtained by using
individual pacing. The width of the road was estimated to be 6.7m from Ayeduase gate to
Kotei junction. From Kotei junction to Abaase junction, the width of the road was measured as
9.2m. The road has two lanes, and on both sides of the carriageway are walkways with width
2.3m and 1.5m on the left and right respectfully. Both sides of the carriageway have drains of
size 0.45m. A circular culvert of diameter 0.7m is installed at 186m from Ayeduase gate. Also,
a circular culvert is installed at 105.7m from the intersection. Based on the survey conducted it
was observed the road was recently maintained and for that matter no defects were obtained.
Description
Based on the field reconnaissance conducted, it was observed that the route two (from Abaase
junction to Rising Sun Hostel) as indicated on the map is unpaved. The length of the road was
estimated to be 550.0m. This was obtained by using individual pacing. The width of the road was
estimated to be 8.9m with no designated lanes. On both sides of the carriage, no walkways are
provided on the left and right. Both sides of the carriage have no drains. Based on the survey
conducted it was observed the road has a lot of defects. Some defects on the road are listed
below:
Edge failure
Gulley erosion and Potholes
Description
Based on the field reconnaissance conducted, it was observed that route three (from Helenus
to Rising Sun Hostel) as indicated on the map is unpaved. The length of the road was
estimated to be 578.57m. This was obtained by using individual pacing. The width of the road
was estimated to be 5.68m with no designated lanes. On both sides of the carriage, no
walkways are provided on the left and right. Both sides of the carriage are drains installed of
size 0.6m. A circular culvert of diameter 0.7m is installed at 112m from Ayeduase gate. Based
on the survey conducted it was observed the road has a lot of defects. Some defects on the road
are listed below:
Edge failure
Edge step
Gulley erosion
Potholes
9.2.4 Route Four
Description
Based on the field reconnaissance conducted, it was observed that route four (from Engineering
gate to Nyberg Hostel) as indicated on the map is unpaved. The length of the road was
estimated to be 536.42m. This was obtained by using individual pacing. The width of the road
was estimated to be 6.5m with no designated lanes. On both sides of the carriage, no walkways
are provided on the left and right. Both sides of the carriage have no drains installed. Based on
the survey conducted it was observed the road has a lot of defects. Some defects on the road are
listed below:
Edge failure
Edge step
Gulley erosion
Potholes
9.2.5 Route Five
2.2.5.1 Description
Based on the field reconnaissance conducted, it was observed that the route five (from Ford
hostel to Nyber fast foods) as indicated on the map is unpaved. The length of the road was
estimated to be 393.57m. This was obtained by using individual pacing. The width of the road
was estimated to be 6.2m with no designated lanes. On both sides of the carriage, no walkways
are provided on the left and right. Both sides of the carriage have no drains installed. Based on
the survey conducted it was observed the road has a lot of defects. Some defects on the road are
listed below:
Edge failure
Edge step
Gulley erosion
Potholes
Description
Based on the field reconnaissance conducted, it was observed that the route Six (from Access
bank to Route four) as indicated on the map is unpaved. The length of the road was estimated
to be 221.43m. This was obtained by using individual pacing. The width of the road was
estimated to be 5.6m with no designated lanes. On both sides of the carriage, no walkways are
provided on the left and right. Both sides of the carriage have no drains installed. Based on the
survey conducted it was observed the road has a lot of defects. Some defects on the road are
listed below:
Edge failure
Potholes
Gulley erosion
Traffic volume studies have been conducted to determine the number, movements, and
classifications of roadway vehicles at a given location. Manual volume count. The volume counts
helped to estimate the number of vehicles which will be accessing the facility after completion,
therefore the design should be in accordance to this estimated number.
To obtain the traffic volume, a volume count was conducted at the intersection. The volume
count was conducted for a period of two hours (11:00am-1:00pm) at an interval of 15 minutes.
Prior to the traffic count, the vehicles plying the road were broken down into the following
divisions per the GHA Road Design Guide.
Small vehicle
Large vehicle
Trailer
The following studies were undertaken to evaluate the current situation of the Ayeduase road:
• Traffic Volume and Classification count
• Intersection/Turning Movement and pedestrian Count
9.4.2.1 Detailed Description of the State of Traffic Flows on the Ayeduase Road
The following are some reasons why there is the need to conduct a traffic volume count
To determine the influence of large vehicles on traffic flow
To document traffic volume trends.
To compute expected highway user revenue.
Locating areas where new facilities or improvement existing facilities are needed.
9.4.2.3 Result of Studies
Time Left Straight Right Left Straight Right Left Straigh Right
t
12:15- 50 30 70 50 35 59 0 0 0 294
12:30
12:30- 67 30 20 25 9 10 1 1 0 163
12:45
1:00- 34 30 16 42 6 34 0 0 0 162
1:15
1:15- 27 20 17 19 10 2 0 0 0 95
1:30
9.4.3 2.4.4 Peak Hourly Volume
Table 14 above shows data collected at the Ayeduase-Kotei intersection which would be used to
estimate the peak volumes and turning movement of various classes of vehicles traversing the
intersection as shown in the table below.
11:30-11:45 501
11:45-12:00 453
12:00-12:15 477
1:15-1:30 95 883
9.4.3.1 Peak Hour volume (PHV)
PHV is the maximum number of vehicles that pass a point on a highway during a period
of 60 consecutive minutes. Some uses of Peak hour volume is that they are used for:
Traffic management
Functional classification of roads
Geometric design of features
Justifying, planning and locating traffic control devices
From the above the Peak Hour Volume (PHV) is 1725 vehicles/hour and it occurs from
(11:30pm-12:30pm).
PHV
PHF=
4 xV max
The Peak Hour Volume (PHV) = 1725 vehicles/hour from 11:30pm-12:30pm
The peak flow for 15minutes = 501 vehicles/hour from 11:30pm-11:45pm
1725
PHF= =0. 861
4 x 501
Therefore, the peak hour factor is estimated to be 0.861
Some few facilities required to improve flow, facilitate operations and improve pedestrian safety
on Ayeduase road as listed below:
A lay-by for commercial buses to stop.
Pedestrian sidewalks.
Traffic Signals and Signs.
A larger turning radius at the intersection.
Pedestrian signs (Zebra crossings)
9.4.3.4 Proposed Conceptual Design to Improve Intersection
The figure below presents a conceptual deign to improve the layout or control traffic flow at
the Ayeduase-Kotei intersection.
Design standards & Criteria The design criteria to be used would include the following:
Safety
Functionality
Driver, vehicle and pedestrian characteristics
Aesthetics
Economics
The design standards to be used is GHA Road Design Guide
The classification of the road is done with regards to the functional and terrain type classification of
roads as stated by the GHA road design guide. The class of road to be constructed is Service road or
Access road.
Design speed is the most important consideration in geometric design. It is the design criterion that
is aimed at providing consistent and coordinated alignment. It is related to alignment such as the
curve radius and sight distance. The design speed depends on the functional class of the road and the
topography of the area in which the road is located. The design speeds corresponding to functional
and terrain type is between 40-60 km/h per the GHA Road Design Standard
The design vehicle is the largest vehicle that is expected to use the facility in significant numbers
daily during the design period. Per the data obtained, small vehicles make up most vehicles. Per the
GHA Road Design Guide, small vehicles include private cars, taxis, vans, pick-ups, land rovers and
jeeps with 2- axle single rear wheels. Therefore, the design vehicle to be used would be small
vehicles. Per GHA Road Design Guide a small vehicle has the following dimensions recommended
for design;
Length-4.7m
Width-1.7m
Height-1.5m
9.5.4 Alternative route from Ayeduase gate to kotei to reduce traffic flow
From the reconnaissance survey conducted, it was observed that traffic flow on the Ayeduase-Kotie
road was slow. To take traffic from the Ayeduase-Kotie road there is the need to provide an
alternative route.
Vehicles from Ayeduase gate can be made to move through Route 3(Helenus-Rising Sun) and then
through Route 2(Rising Sun-Abaase Junction) as indicated on the map. This route would be One-
way. Also, Vehicles from Kotei can be made to move through Route 5 and then through Route 6 as
indicated on the map. This route would be One-way
The number of traffic lanes required considering cost, the proposed area and ease of traffic
operation, 2 (two) traffic lanes was chosen.
The selection of a lane width for a road is dependent on the type of road classification, traffic
volume, design vehicle dimensions and the design speed. The lane width selected for the road
design considering the above factors, as stated by the GHA Road Design Guide is 3.25m.
9.5.8 Sidewalks
These are normally provided for pedestrians to prevent traffic conflicts. Sidewalks are to be
provided on all roads. The width of side walk chosen is 2.0m.
The road camber ensures easy drainage of water from the road surface, this prevents road failure
since the water would be drained from the road surface and ensure the safety of running vehicles.
The cross slopes corresponding to surface dressing carriage ways stated by GHA in to be used is
-3.0%.
Surface Course
Binder Couse
Base Course
Sub Base Course
Compacted Subgrade
LANE
WIDTH(6.5m)