Procurement Plan Template QuickUserGuide - E - March2021
Procurement Plan Template QuickUserGuide - E - March2021
Planning is a critical part of the procurement process, enabling the correct setting of objectives, priorities and management of allocated resources
Worksheets for the Procurement Plan Worksheets for Guidance and timelines
Guidance: quick reference guidance on how
to use the template.
Goods, Works, Consulting: used to enter procurement plan data.
Note: Non-consulting services should be inserted in any of the
Time Estimation: estimated timelines by
categories for Goods, Works and Consulting depending on the
procurement methods, based on experience
nature of the services.
and guidance in the Procurement Handbook
Summary: displays a summary of amounts by category, and where specified.
procurement thresholds.
STEP 1: To add a new procurement where rows are still available, fill out all the items in
the Plan until you get to the date.
This is the “Basic Data” section, and reference to the corresponding AWPB, Procurement No., Description, Funding, Number
of Lots, Project Area (where applicable), Procurement/selection methods and the Planned Amount in USD or Local Currency.
The date cells for Goods and Works start with the cell directly under Submission of PreQual docs, and for the Consulting
Services worksheet, the cell directly under Submission of REOI.
Planning from Finish to Start: As long as no manual entries have been made to the planned dates and the
formulas are still in place, you can adjust the timeline based on an END DATE as follows:
Cont’d
2
IFAD Project Procurement Plan Template Quick User Guide
Modifying the number of days in the timeline: This can be done in two ways:
o Using the Time Estimation worksheet: Modifying the approximate (Approx) number of days for specific
processes (by procurement methods) within the Time Estimation worksheet. Note: this timeline applies
to all items in the procurement worksheet using that method.
o Directly modifying planned dates for a procurement item within the procurement plan worksheet.
Note: modifying dates in the worksheets should be done from earliest to latest date, to ensure
remaining dates are adjusted accordingly by the formulas.
This spreadsheet provides estimated timelines by procurement methods, for each step of the procurement
process based on experience and guidance in the Procurement Handbook where specified.
3
IFAD Project Procurement Plan Template Quick User Guide
In cases of multiple LOTS, insert a new Actual Row for each LOT. The Actual Dates will likely be the same until the
Submission of Technical Evaluation Report.
STEP 1: Select and Copy the Actual Row (Row 2) from the STEP 2: In the Lot No./Description section of the
top section of the worksheet, and insert the copied row in Planned Row, indicate the number of LOTS in the Plan
your worksheet to create another Actual row as shown in row, and individual lots in each Actual row. Fill in the
the screenshot below. information as shown in the example below.
NOTE: The Amount entered on the Plan row is the total amount for all the lots, while the amount entered
in the Actual row reflects the amount for each lot.
4
IFAD Project Procurement Plan Template Quick User Guide
For all worksheets (Goods, Works, Consulting), 3 rows (Planned row, Actual
row, and the blank row) are provided at the top of the worksheet, before the
start of the Procurement Plan.
Scroll to the top of the worksheet and select the first 3 rows. Copy the selected rows
Quick tip:
Right click anywhere within the selected
Hover the mouse over the first row
area and select Copy on the dropdown
number until you see a small black
menu.
arrow, then click and drag down to OR press CTRL + C on the keyboard.
the 3rd row.
Things to Note: