WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
Document No
Rev No R0
Prepared By Reviewed By Approved By
Name
Sign
Page 1 of 7
DOC NO
REV NO :R0
REV DATE
WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
LIST OF CONTENTS
1. Introduction
2. Scope
3. Reference
4. Responsibilities
6. Excavation Procedure
6.1.Survey marking
6.2.Safety-barricading
6.4.Excavation sequence
7. Backfilling Procedure
7.1.Safety-barricading
7.2.Backfilling sequence
8. Safety in construction
10.Escalation matrix
Page 2 of 7
DOC NO
REV NO :R0
REV DATE
WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
1.0 Introduction
Work methodology statement details the step by step procedure and this document refers the
process of Excavation and Backfilling work to be carried out on Design & construction of Main
Spine road Package Project from RBT1 to RBT-2 /INT-2 with allied civil & electrical works with
the reference of suitable approved drawings, technical specifications and standards
respectively in a planned .
2.0 Scope
The present methodology of work refers of Excavating ordinary soil and Backfilling for Design
& construction of Main Spine road Package Project from RBT1 to RBT-2 /INT-2 with allied civil
& electrical works and includes facilitating other preliminary and secondary constructions
3.0 Reference
Following Drawing / codes have been referred for preparation of this method statement.
Approved Drawings
Contract Documents
Code practice of safety IS-3764:1992
4.0 Responsibilities
Project Manager:
Responsible for Organizing and managing required resources for the field activities to achieve
efficient completion of the activities
Site-In-Charge:
Shall reports to Project manager. Site in-charge is responsible to oversee the operations
involved in a project and also control, supervise and direct for implementation of this
procedure.
Site Engineer:
Shall report to Site-In-Charge. Shall carry out the work as per the approved drawings and
specification and make sure all the required inspection, tests and checks are done, as required.
QA/QC Engineer:
Shall report to Project Manager, shall be performing QA/QC related works at project. Conduct
audit/observation of the ongoing and completed activities, and inform site engineer about non-
compliance when found in the work done, review of method statements, preparation of test
reports and inspection records, third party lab coordination.
Page 3 of 7
DOC NO
REV NO :R0
REV DATE
WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
Safety Engineer:
Shall facilitate in maintaining a good safe working practices at site. Shall facilitate in risk
analysis and required preventive measures.
For Excavation:-
Excavator
Mini excavator
Tipping trucks
Survey Instrument
Safety Items: Materials for barricading, safety ribbons etc.
Hand tools: Measuring tape, line-dori, etc.
For Backfilling:-
Mini excavator
Tipping trucks
Plate compactor or Baby Roller
Safety Items: Materials for barricading, safety ribbons etc.
Hand tools: Crow bar, Shovel, trowel, etc…
Survey marking
Safety-barricading
Planning for disposal
Excavation sequence
Leveling and compaction of bottom soil
6.2 Safety-barricading
Page 4 of 7
DOC NO
REV NO :R0
REV DATE
WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
Safety cones and safety tapes are used as a safety barrication. Ladders are installed to
excavated footing for the access for employees and labours.
Excavated surplus soil and debris obtained shall dispose to designated area which will be
decided by GMR_GGIAL.
Survey indicating Points shall be set out before starting excavation. And using of suitable
calibrated survey instruments shall be ensured.
Excavation shall be done not beyond the boundary marking of survey with the reference of GFC
drawings.
Buried cables, pipelines and other underground services are found and made diverted.
No excess cutting will be allowed and loose soil will be removed to prevent the sliding.
Permission shall be taken by coordinating with Landscape department to replant the removed
plants and trees.
Suitable drainage or dewatering arrangements are made to ensure, to drain – off the surface
water.
If any reusable excavated earth shall be stacked at the designated area shown by GMR_GGIAL
engineer.
Once the excavation is completed till required level of foundation, the bed soil shall be levelled
and compacted using earth compactor.
Page 5 of 7
DOC NO
REV NO :R0
REV DATE
WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
Safety-barricading
Leveling & compaction for the m-sand laid below Hume pipes & HDPE pipes.
Leveling and compaction of soil filled above Hume pipes & HDPE pipes.
7.1 Safety-barricading
Safety cones and safety tapes are used as a safety barrication. Ladders are installed to
excavated footing for the access for employees and labours.
7.2 Backfillingsequence
Approved material such as M-SAND shall be used as sand bedding for bottom of pipes.
Cleaning of excavated material, levelling of bed prior to backfill shall be strictly maintained.
Layer wise compaction shall be carried and ensured for any backfilling i.e. at an average depth
of 300mm.
Care shall be taken during operation that should lead to any damages to cables, pipelines and
any other resources.
The final layer will be paved to required level with respect to GFC drawing.
The material filled shall be compacted suitable means like Baby roller/Plate compactor
Appropriate barrication and lightings are maintained at site at the excavation area.
Page 6 of 7
T
E
G
N
A
M DOC NO
REV NO :R0
REV DATE
WORK METHOD STATEMENT FOR
EXCAVATION,SAND FILLING AND BACKFILLING
Ramp shall be given to the excavated pits for the proper access for workers
Cutting shall be done from top to bottom
Excavation material shall not be kept at the edge of excavation and loaded to dumper.
There shall not be any vehicle movement close to the edge of excavation trench.
Parking or Halting shall be avoided at side slopes. Excavated materials shall be stacked at
minimum 1m distance from the slope to avoid collapse and sliding. Fixing net or placing sand
bags shall be done at slope areas
Arrangements shall be made for de-watering in case there is interface with ground water
All the manpower and staff engaged at work shall use necessary PPE as applicable to the work
All the vehicles and equipment engagement at work shall be duly certified by safety engineer
prior to development at work.
Arrangements for adequate illumination shall be made for work during night shift
Check-list of work shall be duly filled-up and maintained during the excavation.
Tests and Inspections shall be carried out in accordance to Inspection Testing Plan.
Heavy compaction test shall be carried out to determine OMC and MDD for the material.
After compaction the field density and moisture content are determined by Sand
replacement method in order to ensure that the dry density is not less than 95% of lab
density.
Page 7 of 7