Transmission Line (115kV built to 230kV standards)

Design Employer Contractor Note


Design of Transmission Line (Pagudpud to Bangui)
1 Transmission Line Route Plan X
2 Transmission Line Preliminary Plan & Profile X
3 Transmission Line Plan & Profile for Construction X
4 Preliminary Transmission Line Tower Locations X
5 Final Transmission Line Tower Locations X
6 Preliminary Transmission Line Foundation Designs X
7 Transmission Line Foundation Designs for Construction X
8 Transmission Line Tower Designs X
9 Transmission Line Electrical Specification X To be in accordance with NGCP's requirements - must include conductor, insulator, OPGW specifications including structure highlighting splicing locations.
10 OPGW Specification for Project Transmission Line X
11 OPGW Splicing plan and box design X
12 Further geotechnical analysis pre-construction and during construction X

Performance
Performance in Transmission Line works
1 Transmission tower transport from Employer yard, segregation, installation X Employer shall supply transmission tower components.
2 Procurement of stockyard - rental and any equipment needed X If additional area is needed outside Project Site Temporary Facilities area.
3 Excavation of transmission towers X
4 Supply and pouring of lean concrete, gravel bedding, or spacers X
5 Supply and installation of transmission tower foundation rebar X
6 Supply and installation of concrete formworks for foundation X
7 Supply of concrete and any equipment or materials needed for pouring X
8 Installation and erection of 3 transmission line towers X To connect to the existing BWPC Line.
9 Quality assurance checking and reports X For Contractor's scope of foundations, tower installation, conductor, insulators, and OPGW installation, commissioning, and testing with a log book kept for each transmission tower.
10 Supply & Install of transmission tower markings and safety signs X In accordance with NGCP standards.
11 Supply & Install of transmission tower anti-climbing devices X In accordance with NGCP standards.
12 Supply of all non-potable water needed for Contractor's work X
13 Procurement of Internet connection inside or outside Project Site Boundary X During construction for Contractor's personnel.
14 Supply of conductor for Transmission Line X
15 Stringing and comissioning of conductor for Transmission Line X Includes plan to minimize conductor splicing and Contractor shall deliver and supply the specialized equipment and manpower to perform the Works.
16 OPGW supply and installation compliant with NGCP standards X
17 OPGW Splicing and box supply X
18 OPGW connection testing (point-to-point) OTDR X
19 Supply & installation of insulators and line hardwares X In accordance with NGCP standards.
20 Transmission Line grounding equipment supply and installation for 3 towers to be erected X
21 Transmission Line conductor testing for losses X
22 Supply of As-built documentation X Within sixty (60) days of Project Take Over with logbook for each tower location.
23 As built testing for line loss confirmation X
24 Trimming of trees X If required, in accordance with Employer's permits.