Project: ALABAT MET MAST

Subject: ACTUAL ACCOMPLISHMENT 081122

RELATIVE RELATIVE RELATIVE


PREVIOUS THIS PERIOD
ITEM DESCRIPTION WEIGHT (%) PREVIOUS THIS PERIOD TO DATE TO DATE (%)
(%) (%)
WEIGHT (%) WEIGHT (%) WEIGHT (%)

I ALABAT MET MAST

1.0 Excavation Works 13.33% 100.00% 13.33% 0.00% 0.00% 100.00% 13.33%

2.0 Concreting Works 33.33% 6.33% 2.11% 73.67% 24.56% 80.00% 26.67%

3.0 Backfilling Works 3.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4.0 Mast Erection 36.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5.0 Instrument and Sensor 3.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6.0 Lightning Protection 3.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7.0 Anti Climb Installation 3.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8.0 MET Mast Fence 3.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

ACTUAL WEEK ACCOMPLISHMENT 100.00%


ACTUAL CUMMULATIVE WEEKLY ACCOM. 19.67% 20.33% 40.00%

PROJECTED WEEK ACCOMPLISHMENT 6.77%


PROJECTED CUMMULATIVE WEEKLY ACCOM. 6.67% 6.67% 13.34%

AVE. WEEKLY ACCOMPLISHMENT 12.50%

AVE. DAILY ACCOMPLISHMENT 1.79%

VARIANCE IN PERCENTAGE (+/-) 26.66%

VARIANCE IN DAYS (+/-) 15