Professional Documents
Culture Documents
Estimate For Tarbella-Islamabad Water Supply
Estimate For Tarbella-Islamabad Water Supply
Estimate For Tarbella-Islamabad Water Supply
EXCAVATION IN ROCK
2.4.7 Supply and fix wire mesh of specified grade cut to size tonne 128,788 146
as reinforcement for shotcrete
2.4.12 Supply & installation of steel rib supports as specified at tonne 81,454 117
locations indicated on the Drawings.
GROUTING
2.4.13 Drilling grout holes of depth and diameter as specified in lin.m 360 5,250
any direction.
2.4.14 Cement used in grouting. kg 10 455,000
2.4.15 Bentonite used in grouting. kg 12 5,000
2.4.16 Chemical used in chemical grouting. kg 18,000 100
2.4.17 Hourly rate for grouting. hour 3,218 3,600
2.4.18 Set up and removal of grouting equipment for each no 7,972 600
session of grouting as instructed by Engineer.
2.4.19 Drilling of drain holes 50 mm diameter, length 1.0 m in lin.m 122 700
walls and roof.
2.4.21 Supply and fix flexible plastic pipes for collection of lin.m 88 3,500
water at drainage holes drilled in walls & roof prior to
concreting secondary lining.
MONITORING
2.4.24 R.C.C grade 30 for secondary lining of 5m internal cu.m 14,764 14,012
diameter thickness as shown on the Drawings. (25cm-avg)
2.4.26 Supply and fix reinforcement of minimum yield strength tonne 67,113 573
400 N/mm² for secondary lining bent and cut to size and
including all ties and spacers.
2.4.27 Supply and install 3.10 m internal diameter steel pressure lin.m 86,065 -
lining with external ring stiffeners in the existing
underground stilling basin and stub tunnel shell and
stiffener thicknesses as shown on the Drawings
2.4.28 Supply and install 3.10 m internal diameter steel pressure lin.m 107,536 -
lining at the downstream end of the rock tunnel shell
thickness as shown on the Drawings
2.5.1 Underground excavation for soft ground tunnel including cu.m 5,805 89,311.6
control of ground water and transportation of spoil to
tipping areas at any distance.
LINING
2.5.2 Supply & instalation of precast concrete bolted tunnel lin.m 71,392 3,500
lining rings as specified complete with all bolts,washers,
nuts,parkers, grommets,sealing gaskets, lifting sockets,
grout plugs etc. including cavity grouting.
2.5.3 Supply and install 3.1m internal diameter steel pressure lin.m 98,849 3,500
lining in soft ground tunnel shell tickness as shown on
the Drawings.
EXCAVATION
2.6.1 Excavate trench in soft ground for cut and cover tunnel cu.m 165 2,250,000
including disposal of soil depth not exceeding 5.0m
2.6.2 Ditto depth exceeding 5.0m not exceeeding 10.0m cu.m 165 112,500
2.6.3 Back fill trench for cut and cover tunnel using selected cu.m 282 1,775,880
excavated material to the limits shown on the Drawings
LINING
2.6.4 Supply & install 2.0m internal diameter steel pressure lin.m 84,160 45,000
lining as permanent internal shutter in cut and cover
tunnel wall thickness as shown on the Drawings.
2.6.6 PCC of grade 20 for fixing on the saddle, to encase half cu.m 5,902 157,626
of the pressure lining in cut and cover section
MASONRY
2.6.8 Supply and install Riprap type III launching apron as scour cu.m 927 60,000
protection to the cut and cover tunnel to the depths,
levels and limits shown on the Drawings.
m2
m3
ESTIMATED AMOUNT
64,967,995
159,965,165
203,018,289
119,786,414
13,457,500
19,110,000
18,781,583
9,945,510
40,957,532
43,296,204
11,201,008
9,502,967
1,890,000
4,550,000
60,000
1,800,000
11,584,800
4,783,200
85,400
35,000,000
308,000
880,740
2,669,800
206,876,859
38,480,357
196,834
3,444,700
895,563
665,933
516,688
255,880
482,230
1,755,210
1,031,172,361
518,453,560
249,872,000
345,971,500
1,114,297,060
m2
m3
CONTRACT AMOUNT
371,250,000
18,562,500
500,798,300
3,787,200,000
147,150,000
930,309,628
4,262,700
55,620,000
5,815,153,128
total shotcrete 61,544 m2
QUANTITY TO DATE
ORIGINAL QUANTITYCOMPLETION %
area
3,561.81 10,308 34.55% 26376 m2
13.5040
369 42 878.57%
2,230.90 2,934 76.04%
100.00%
*100*923083423491*55#
59 44 134.09%
468 44 1063.64%
108.75 80 135.94%
1 100.00%
2 2 100.00%
20 20 100.00%
20 20 100.00%
20 20 100.00%
- 15 0.00%
20 5 400.00%
20 15 133.33%
1 1 100.00%
17,186,206 22,342,068
294,620.67 372,368
383,006.88
CONTRACT AMOUNT
0.05
109,408
33,750
23
0.0714
8.5 km INLET TUNNEL + 17 km OPEN CHANNEL FLOW + 25 km CUT&COVER PIPE LINE + 5 km SIPHON
+ 2.5 km OUTLET TUNNEL total length (km) = 58
TUNNEL WORKS
2.4.7 Supply and fix wire mesh of specified grade cut to size tonne 128,788 425 54,734,900
as reinforcement for shotcrete
2.4.8 Shotcrete as required for underground application sq.m 808 89,457 72,281,135
thickness 50mm.
2.4.12 Supply & installation of steel rib supports as specified at tonne 81,454 425 34,617,950
locations indicated on the Drawings.
GROUTING
2.4.13 Drilling grout holes of depth and diameter as specified in lin.m 360 25,500 9,180,000
any direction.
2.4.14 Cement used in grouting. kg 10 1,020,000 10,200,000
2.4.15 Bentonite used in grouting. kg 12 5,000 60,000
2.4.16 Chemical used in chemical grouting. kg 18,000 100 1,800,000
2.4.17 Hourly rate for grouting. hour 3,218 12,000 38,616,000
2.4.18 Set up and removal of grouting equipment for each no 7,972 2,000 15,944,000
session of grouting as instructed by Engineer.
2.4.19 Drilling of drain holes 50 mm diameter, length 1.0 m in lin.m 122 1,700 207,400
walls and roof.
CARE AND HANDLING OF WATER
2.4.20 Supply, instalation and operation of underground lump sum 8,500,000
dewatering pumps including depreciation, repairs, spare
parts and maintenance of pumps and all equipment during
construction period. Dewatering capacity > 1 liter/sec <10
litre/sec per 100m of tunnel
2.4.21 Supply and fix flexible plastic pipes for collection of lin.m 88 8,500 748,000
water at drainage holes drilled in walls & roof prior to
concreting secondary lining.
MONITORING
2.4.22 Convergency measurements including installation of no 12,582 170 2,138,940
stations (5/section) at 50 m intervals or at locations
selected by the Engineer, surveying, all auxiliary
equipment, measuring insrruments and monitoring.
2.4.26 Supply and fix reinforcement of minimum yield strength tonne 67,113 1,417 95,076,750
400 N/mm² for secondary lining bent and cut to size and
including all ties and spacers.
2.4.27 Supply and install 3.10 m internal diameter steel pressure lin.m 86,065 - -
lining with external ring stiffeners in the existing
underground stilling basin and stub tunnel shell and
stiffener thicknesses as shown on the Drawings
2.4.28 Supply and install 3.10 m internal diameter steel pressure lin.m 107,536 - -
lining at the downstream end of the rock tunnel shell
thickness as shown on the Drawings
LINING
2.5.2 Supply & instalation of precast concrete bolted tunnel lin.m 71,392 8,500 606,832,000
lining rings as specified complete with all bolts,washers,
nuts,parkers, grommets,sealing gaskets, lifting sockets,
grout plugs etc. including cavity grouting.
2.5.3 Supply and install 3.1m internal diameter steel pressure lin.m 98,849 8,500 840,216,500
lining in soft ground tunnel shell tickness as shown on
the Drawings.
3,186,693,514
EXCAVATION
2.6.1 Excavate trench in soft ground for cut and cover tunnel cu.m 165 850,000 140,250,000
including disposal of soil depth not exceeding 5.0m
2.6.2 Ditto depth exceeding 5.0m not exceeeding 10.0m cu.m 165 42,500 7,012,500
2.6.3 Back fill trench for cut and cover tunnel using selected cu.m 282 310,165 87,466,530
excavated material to the limits shown on the Drawings
LINING
2.6.4 Supply & install 2.0m internal diameter steel pressure lin.m 84,160 - -
lining as permanent internal shutter in cut and cover
tunnel wall thickness as shown on the Drawings.
2.6.6 PCC of grade 20 for fixing on the saddle, to encase half cu.m 5,902 113,985 672,739,470
of the pressure lining in cut and cover section
MASONRY
2.6.8 Supply and install Riprap type III launching apron as scour cu.m 927 102,000 94,554,000
protection to the cut and cover tunnel to the depths,
levels and limits shown on the Drawings.
1,084,111,200
EXCAVATION
2.6.1 Excavate trench in soft ground for cut and cover tunnel cu.m 165 2,250,000 371,250,000
including disposal of soil depth not exceeding 5.0m
2.6.2 Ditto depth exceeding 5.0m not exceeeding 10.0m cu.m 165 112,500 18,562,500
2.6.3 Back fill trench for cut and cover tunnel using selected cu.m 282 1,775,880 500,798,300
excavated material to the limits shown on the Drawings
LINING
2.6.4 Supply & install 2.0m internal diameter steel pressure lin.m 84,160 45,000 3,787,200,000
lining as permanent internal shutter in cut and cover
tunnel wall thickness as shown on the Drawings.
2.6.6 PCC of grade 20 for fixing on the saddle, to encase half cu.m 5,902 157,626 930,309,628
of the pressure lining in cut and cover section
MASONRY
2.6.8 Supply and install Riprap type III launching apron as scour cu.m 927 60,000 55,620,000
protection to the cut and cover tunnel to the depths,
levels and limits shown on the Drawings.
5,815,153,128
SIPHON
pipe line dia (for 600 MGD) m= 5 area of 2 pipes= 18.850 m2
5,000 length (km)= 5 volume of pipes= 94,248 m3
m depth (m)= 5
width (m)= 10
total volume for excavation (m3)= 250,000
PART NO 6.1 SIPHON INLETS
PAY ITEM NO DESCRIPTION OF WORK UNIT UNIT RATE
ESTIMATED QUANTITY
ESTIMATED AMOUNT
CARE AND HANDLING OF WATER
6.1.1 Maintenance of flow ( No of structures 2) lump sum Included in prices
EARTHWORK
6.1.4 Excavation unclassified and compaction of suitable cu.m 155 250,000 38,750,000
material to 95% maximum dry density including formation
of specified slopes with disposal and haulage of surplus
as required.
6.1.6 Fill in embankment compact to 95% max dry density cu.m 155 155,752 24,141,594
including formation of specified slopes
6.1.8 Reinforced cement concrete in structures grade 20. cu.m 6,556 5,254 34,446,571
6.1.9 Reinforcement, minimum yield strength 275 N/mm² tonne 59,226 357 21,152,143
METALWORK
6.1.10 Supply and fix trashrack and built in parts for siphon intels tonne 76,028 2 152,056
6.2.4 Plain cement concrete grade 20 with light mesh cu.m 5,902 32,000 188,864,000
reinforcement in surround to siphons
6.2.6 Precast reinforced cement concrete grade 30 cu.m 15,011 5,254 78,870,879
6.2.8 Mesh reinforcement, minimum yield strength 400 N/mm² tonne 85,254 -
METALWORK
6.2.9 Supply and install ladders in washout / access chambers tonne 92,064 2 184,128
PIPES
6.2.10 Steel barrel for siphon 5000mm I.D. with 8mm wall lin.m 128,623 5,000 643,115,385
6.2.11 Steel barrel for Badri siphon 3350mm I.D. with 8mm wall lin.m 84,161 deleted
SCOUR PROTECTION
6.2.13 Riprap type I in scour protection launching apron cum 927 10,000 9,270,000
6.2.14 Stone pitching cu.m 1,089 5,000 5,445,000
1,057,201,756
6.3.1 Excavation unclassified, backfill and compaction of cu.m 155 1,265 196,075
suitable material to 95% maximum dry density including
formation of specified slopes with disposal and haulage
of surplus as required.
6.3.3 Fill in embankment and under structures, compact to 95% cu.m 155 2,632 407,960
max dry density including formation of specified slopes
6.3.4 Plain cement concrete grade 10 as blinding 50mm thick. sq.m 218 980 213,640
6.3.5 Reinforced cement concrete in structures grade 20. cu.m 6,556 2,336 15,314,816
6.3.6 Reinforced cement concrete in bridge and beams grade 20 cu.m 6,556 58 380,248
6.3.7 Reinforcement, minimum yield strength 275 N/mm² tonne 59,226 234 13,858,884
6.3.8 Reinforcement, minimum yield strength 400 N/mm² tonne 61,293 6 367,758
6.3.9 Second stage concrete grade 20 including installation of cu.m 5,249 2 10,498
all built in parts
6.3.10 Supply and fix 3 bulb PVC 225mm water stop lin.m 2,226 75 166,950
MASONRY
6.3.11 Brick masonry in 1:4 sand cement mortar for outlet cross cu.m 6,838 40 273,520
regulator gate enclosure
METALWORK
6.3.12 Supply and fix steelwork in stoplog grooves and crest tonne 76,028 4 304,112
angles for outlet cross regulator
6.3.13 Supply and fix galvanised mild steel handrail to top of lin.m 2,830 76 215,080
head tank of outlet cross regulator
6.3.14 Supply and fix galvanised mild steel open mesh flooring sq.m 4,424 158 698,992
( working load 5 kN/mm² ) to top of head tank outlet
cross regulator
33,826,114
238,486,183
369 2,941,668 42 9 6
59 742,338 44 1 50
468 3,569,904 44 11
109 11,694,540 80 1
1 759,000 1
2 196,834 2 1
20 196,840 20 1 100
20 204,700 20 1 200
20 228,320 20 1 400
0 0 15 0 600
20 255,880 5 4 10
20 275,560 15 1 1,000
1 2,952 1 1
$ $
395,108,384 11,972,981 52,893,664
5,701 6,223
7,412 8,090
OUNT
5%
17,850 cum
23
0.1429 ton/m
OUNT
0.05
33,750
23
0.0714 ton/m
QUANTITY
PREVIOUSLY
AMOUNT
TOCERTIFIED
PREVIOUSLY
DATE QUANTITY
TO CERTIFIED
DATE AMOUNTQUANTITY AMOUNT
THIS IPC COMPLETION
THIS IPC %
0 0 0 0 0.00%
0 0 0 0 0.00%
QUANTITY
PREVIOUSLY
AMOUNT
TOCERTIFIED
PREVIOUSLY
DATE QUANTITY
TO CERTIFIED
DATE AMOUNTQUANTITY AMOUNT
THIS IPC COMPLETION
THIS IPC %
0
32.5 km INLET TUNNEL + 17 km OPEN CHANNEL FLOW + 25 km CUT&COVER PIPE LINE + 5 km SIPHON
+ 2.5 km OUTLET TUNNEL total length (km) = 58
TUNNEL WORKS
2.4.7 Supply and fix wire mesh of specified grade cut to size tonne 128,788 1,625 209,280,500
as reinforcement for shotcrete
2.4.8 Shotcrete as required for underground application sq.m 808 342,041 276,369,047
thickness 50mm.
2.4.12 Supply & installation of steel rib supports as specified at tonne 81,454 1,625 132,362,750
locations indicated on the Drawings.
GROUTING
2.4.13 Drilling grout holes of depth and diameter as specified in lin.m 360 97,500 35,100,000
any direction.
2.4.14 Cement used in grouting. kg 10 3,900,000 39,000,000
2.4.15 Bentonite used in grouting. kg 12 5,000 60,000
2.4.16 Chemical used in chemical grouting. kg 18,000 100 1,800,000
2.4.17 Hourly rate for grouting. hour 3,218 12,000 38,616,000
2.4.18 Set up and removal of grouting equipment for each no 7,972 2,000 15,944,000
session of grouting as instructed by Engineer.
2.4.19 Drilling of drain holes 50 mm diameter, length 1.0 m in lin.m 122 6,500 793,000
walls and roof.
CARE AND HANDLING OF WATER
2.4.20 Supply, instalation and operation of underground lump sum 32,500,000
dewatering pumps including depreciation, repairs, spare
parts and maintenance of pumps and all equipment during
construction period. Dewatering capacity > 1 liter/sec <10
litre/sec per 100m of tunnel
2.4.21 Supply and fix flexible plastic pipes for collection of lin.m 88 32,500 2,860,000
water at drainage holes drilled in walls & roof prior to
concreting secondary lining.
MONITORING
2.4.22 Convergency measurements including installation of no 12,582 650 8,178,300
stations (5/section) at 50 m intervals or at locations
selected by the Engineer, surveying, all auxiliary
equipment, measuring insrruments and monitoring.
2.4.26 Supply and fix reinforcement of minimum yield strength tonne 67,113 5,417 363,528,750
400 N/mm² for secondary lining bent and cut to size and
including all ties and spacers.
2.4.27 Supply and install 3.10 m internal diameter steel pressure lin.m 86,065 - -
lining with external ring stiffeners in the existing
underground stilling basin and stub tunnel shell and
stiffener thicknesses as shown on the Drawings
2.4.28 Supply and install 3.10 m internal diameter steel pressure lin.m 107,536 - -
lining at the downstream end of the rock tunnel shell
thickness as shown on the Drawings
LINING
2.5.2 Supply & instalation of precast concrete bolted tunnel lin.m 71,392 32,500 2,320,240,000
lining rings as specified complete with all bolts,washers,
nuts,parkers, grommets,sealing gaskets, lifting sockets,
grout plugs etc. including cavity grouting.
2.5.3 Supply and install 3.1m internal diameter steel pressure lin.m 98,849 32,500 3,212,592,500
lining in soft ground tunnel shell tickness as shown on
the Drawings.
12,184,416,375
EXCAVATION
2.6.1 Excavate trench in soft ground for cut and cover tunnel cu.m 165 850,000 140,250,000
including disposal of soil depth not exceeding 5.0m
2.6.2 Ditto depth exceeding 5.0m not exceeeding 10.0m cu.m 165 42,500 7,012,500
2.6.3 Back fill trench for cut and cover tunnel using selected cu.m 282 310,165 87,466,530
excavated material to the limits shown on the Drawings
LINING
2.6.4 Supply & install 2.0m internal diameter steel pressure lin.m 84,160 - -
lining as permanent internal shutter in cut and cover
tunnel wall thickness as shown on the Drawings.
2.6.6 PCC of grade 20 for fixing on the saddle, to encase half cu.m 5,902 113,985 672,739,470
of the pressure lining in cut and cover section
MASONRY
2.6.8 Supply and install Riprap type III launching apron as scour cu.m 927 102,000 94,554,000
protection to the cut and cover tunnel to the depths,
levels and limits shown on the Drawings.
1,084,111,200
EXCAVATION
2.6.1 Excavate trench in soft ground for cut and cover tunnel cu.m 165 2,250,000 371,250,000
including disposal of soil depth not exceeding 5.0m
2.6.2 Ditto depth exceeding 5.0m not exceeeding 10.0m cu.m 165 112,500 18,562,500
2.6.3 Back fill trench for cut and cover tunnel using selected cu.m 282 1,775,880 500,798,300
excavated material to the limits shown on the Drawings
LINING
2.6.4 Supply & install 2.0m internal diameter steel pressure lin.m 84,160 45,000 3,787,200,000
lining as permanent internal shutter in cut and cover
tunnel wall thickness as shown on the Drawings.
2.6.6 PCC of grade 20 for fixing on the saddle, to encase half cu.m 5,902 157,626 930,309,628
of the pressure lining in cut and cover section
MASONRY
2.6.8 Supply and install Riprap type III launching apron as scour cu.m 927 60,000 55,620,000
protection to the cut and cover tunnel to the depths,
levels and limits shown on the Drawings.
5,815,153,128
SIPHON
pipe line dia (for 600 MGD) m= 5 area of 2 pipes= 18.850 m2
5,000 length (km)= 5 volume of pipes= 94,248 m3
m depth (m)= 5
width (m)= 10
total volume for excavation (m3)= 250,000
PART NO 6.1 SIPHON INLETS
PAY ITEM NO DESCRIPTION OF WORK UNIT UNIT RATE ORIGINAL QUANTITY CONTRAC
EARTHWORK
6.1.4 Excavation unclassified and compaction of suitable cu.m 155 250,000 38,750,000
material to 95% maximum dry density including formation
of specified slopes with disposal and haulage of surplus
as required.
6.1.6 Fill in embankment compact to 95% max dry density cu.m 155 155,752 24,141,594
including formation of specified slopes
6.1.8 Reinforced cement concrete in structures grade 20. cu.m 6,556 17,514 114,821,904
6.1.9 Reinforcement, minimum yield strength 275 N/mm² tonne 59,226 357 21,152,143
METALWORK
6.1.10 Supply and fix trashrack and built in parts for siphon intels tonne 76,028 2 152,056
EARTHWORKS
6.2.1 Excavation unclassified and compaction of suitable cu.m 719 92,000 66,148,000
material to 95% maximum dry density including formation
of specified slopes with disposal and haulage of surplus
as required.
6.2.4 Plain cement concrete grade 20 with light mesh cu.m 5,902 32,000 188,864,000
reinforcement in surround to siphons
6.2.5 Reinforced cement concrete in structures grade 20. cu.m 6,556 92 603,152
6.2.7 Reinforcement, minimum yield strength 275 N/mm² tonne 59,226 9 533,034
6.2.8 Mesh reinforcement, minimum yield strength 400 N/mm² tonne 85,254 360 30,691,440
METALWORK
6.2.9 Supply and install ladders in washout / access chambers tonne 92,064 1 92,064
PIPES
6.2.10 Steel barrel for Kundal siphon 3250mm I.D. with 8mm wall lin.m 83,605 1,475 123,317,375
6.2.11 Steel barrel for Badri siphon 3350mm I.D. with 8mm wall lin.m 84,161 2,017 169,752,737
SCOUR PROTECTION
6.2.13 Riprap type I in scour protection launching apron cum 927 2,716 2,517,732
592,599,790
6.3.1 Excavation unclassified, backfill and compaction of cu.m 155 1,265 196,075
suitable material to 95% maximum dry density including
formation of specified slopes with disposal and haulage
of surplus as required.
6.3.3 Fill in embankment and under structures, compact to 95% cu.m 155 2,632 407,960
max dry density including formation of specified slopes
6.3.4 Plain cement concrete grade 10 as blinding 50mm thick. sq.m 218 980 213,640
6.3.5 Reinforced cement concrete in structures grade 20. cu.m 6,556 2,336 15,314,816
6.3.6 Reinforced cement concrete in bridge and beams grade 20 cu.m 6,556 58 380,248
6.3.7 Reinforcement, minimum yield strength 275 N/mm² tonne 59,226 234 13,858,884
6.3.8 Reinforcement, minimum yield strength 400 N/mm² tonne 61,293 6 367,758
6.3.9 Second stage concrete grade 20 including installation of cu.m 5,249 2 10,498
all built in parts
6.3.10 Supply and fix 3 bulb PVC 225mm water stop lin.m 2,226 75 166,950
MASONRY
6.3.11 Brick masonry in 1:4 sand cement mortar for outlet cross cu.m 6,838 40 273,520
regulator gate enclosure
METALWORK
6.3.12 Supply and fix steelwork in stoplog grooves and crest tonne 76,028 4 304,112
angles for outlet cross regulator
6.3.13 Supply and fix galvanised mild steel handrail to top of lin.m 2,830 76 215,080
head tank of outlet cross regulator
6.3.14 Supply and fix galvanised mild steel open mesh flooring sq.m 4,424 158 698,992
( working load 5 kN/mm² ) to top of head tank outlet
cross regulator
33,826,114
QUANTITY TO DATE
AMOUNT TO ORIGINAL
DATE QUANTITY
COMPLETION %required %
or no. /m
238,486,183
369 2,941,668 42 9 6
59 742,338 44 1 50
468 3,569,904 44 11
109 11,694,540 80 1
1 759,000 1
2 196,834 2 1
20 196,840 20 1 100
20 204,700 20 1 200
20 228,320 20 1 400
0 0 15 0 600
20 255,880 5 4 10
20 275,560 15 1 1,000
1 2,952 1 1
$ $
395,108,384 11,972,981 199,568,747
5,701 6,141
7,412 7,983
CONTRACT AMOUNT
5%
17,850 cum
23
0.1429 ton/m
CONTRACT AMOUNT
0.05
33,750
23
0.0714 ton/m
QUANTITY
PREVIOUSLY
AMOUNT
TO
CERTIFIED
PREVIOUSLY
DATE QUANTITY
TOCERTIFIED
DATE AMOUNT QUANTITY AMOUNT
THIS IPC COMPLETION
THIS IPC %
0 0 0 0 0.00%
QUANTITY
PREVIOUSLY
AMOUNT
TO
CERTIFIED
PREVIOUSLY
DATE QUANTITY
TOCERTIFIED
DATE AMOUNT QUANTITY AMOUNT
THIS IPC COMPLETION
THIS IPC %
DELETED DELETED
0 0 0 0 0.00%
1,448 121,096,492 1,448 120,485,527 610,965 98.20%
QUANTITY
PREVIOUSLY
AMOUNT
TO
CERTIFIED
PREVIOUSLY
DATE QUANTITY
TOCERTIFIED
DATE AMOUNT QUANTITY AMOUNT
THIS IPC COMPLETION
THIS IPC %
0
ITEM NO DESCRIPTION OF WORK UNIT UNIT RATE
EXCAVATION IN ROCK
2.4.7 Supply and fix wire mesh of specified grade cut to size tonne 128,788
as reinforcement for shotcrete
2.4.12 Supply & installation of steel rib supports as specified at tonne 81,454
locations indicated on the Drawings.
GROUTING
2.4.13 Drilling grout holes of depth and diameter as specified in lin.m 360
any direction.
2.4.14 Cement used in grouting. kg 10
2.4.15 Bentonite used in grouting. kg 12
2.4.16 Chemical used in chemical grouting. kg 18
2.4.17 Hourly rate for grouting. hour 3,218
2.4.21 Supply and fix flexible plastic pipes for collection of lin.m 88
water at drainage holes drilled in walls & roof prior to
concreting secondary lining.
MONITORING
2.4.24 R.C.C grade 30 for secondary lining of 4.41m internal cu.m 14,764
diameter thickness as shown on the Drawings. (25cm-avg)
2.4.26 Supply and fix reinforcement of minimum yield strength tonne 67,113
400 N/mm² for secondary lining bent and cut to size and
including all ties and spacers.
2.4.27 Supply and install 3.10 m internal diameter steel pressure lin.m 86,065
lining with external ring stiffeners in the existing
underground stilling basin and stub tunnel shell and
stiffener thicknesses as shown on the Drawings
2.4.28 Supply and install 3.10 m internal diameter steel pressure lin.m 107,536
lining at the downstream end of the rock tunnel shell
thickness as shown on the Drawings
2.4.34 Reinstall wedges and packers to existing steel rib lump sum
supports
2.5.1 Underground excavation for soft ground tunnel including cu.m 5,805
control of ground water and transportation of spoil to
tipping areas at any distance.
LINING
2.5.2 Supply & instalation of precast concrete bolted tunnel lin.m 71,392
lining rings as specified complete with all bolts,washers,
nuts,parkers, grommets,sealing gaskets, lifting sockets,
grout plugs etc. including cavity grouting.
2.5.3 Supply and install 3.1m internal diameter steel pressure lin.m 98,849
lining in soft ground tunnel shell tickness as shown on
the Drawings.
ESTIMATED QUANTITY
ESTIMATED AMOUNT
0 - 3,348.15 2,705,305
0 - 6,201.27 17,450,374
0 - 958.29 3,488,176
238,486,183
5,000,000 5,998,000
20 251,640 59 742,338
- - 1,477.52 8,470,622
- - 151.30 13,021,893
- - 108.75 11,694,540
154,502,115
500,000 1 759,000
0 - -
0 - -
0 - -
0 - -
673,000 -
0 - 604.56 1,012,033
2 196,834 2 196,834
10 98,420 20 196,840
10 102,350 20 204,700
10 114,160 20 228,320
5 59,050 - -
5 63,970 20 255,880
5 68,890 20 275,560
1 29,525 1 29,525
290,609,444 3,158,692
396,146,990 ###
- - 1,326.78 131,150,876
251,927,500 317,879,921
PART NO 6.1 SIPHON INLETS
PAY ITEM NO DESCRIPTION OF WORK UNIT
EARTHWORK
METALWORK
6.1.10 Supply and fix trashrack and built in parts for siphon intels tonne
UNIT RATE ORIGINAL QUANTITY CONTRACT QUANTITY
AMOUNT TO DATE
PREVIOUSLY
AMOUNTCERTIFIED
PREVIOUSLY
QUANTITY
TO DATE
CERTIFIED AMOUNT
Included in prices
Included in prices
Included in prices
- - 0.00% -
- - 151.16% -
- - 59.83% -
-
ITEM NO UNIT
DESCRIPTION OF WORK UNIT
RATE
INTAKE SHAFT (30m diameter, 100m depth)
EXCAVATION IN ROCK
2.4.30 Fully mortared rock bolts SN - Type or any other type no 3,076
approved by the Engineer, capacity 100 KN, all directions:
length 1.5 m
2.4.31 Supply and fix wire mesh of specified grade cut to size tonne 123,966
as reinforcement for shotcrete
2.4.32 Shotcrete as requried for underground application sq.m 768
thickness 50mm
2.4.33 Ditto thickness 100mm sq.m 1,201
2.4.34 Reinstall wedges and packers to existing steel rib lump sum
supports
2.5.2 Supply & instalation of precast concrete bolted shaft lin.m 71,392
lining rings as specified complete with all bolts,washers,
nuts,parkers, grommets,sealing gaskets, lifting sockets,
grout plugs etc. including cavity grouting.
3,534 31,617,774 5%
0 -
0 - 20
9,425 7,238,229
471 565,958 5%
100 7,139,200
707 1,183,281
407,386,899