R.G. SIMBULAN AND PARTNERS CORP.

Method Statement For


Adjustment of Installed
Steel Doors from Finish Floor Line
Solaire North Project

I. OBJECTIVE

The purpose of this construction method statement is to outline and describe in the sequence of works in
detail, to be strictly executed and complied by all concerned contractors to ensure complete, safe, and quality
implementation from preparation up to completion and lessen, if not avoid, rendering rectification works
later on. Works shall be carried out in compliance with the drawings, project specifications, and materials.

II. PREPARATION
1 Site Condition
1.1 Provide Layout to the perimeter of Door jamb to be chipped
1.2 Detached all door accessories especially hinges and door closer

2 Submittals
2.1 Approved Material
2.1 Approved Product Data Sheet
2.2 Signed- Off Notice for Inspection

Site boundaries must be well defined. MEP installations must be checked and approved. Site must be clear
from debris and materials by other trade contractors. All tools, materials, and consumables necessary for
installation should be hauled out from storage and securely placed in the dry area of the designated work
space.

III. TOOLS, MATERIALS, & CONSUMABLES

TOOLS MATERIALS & CONSUMABLES (As per approved)

1. Chipping gun
2. Welding Machine
3. Grinder

IV. MANPOWER
1. Operator (Chipping Gun)
2. Welder
R.G. SIMBULAN AND PARTNERS CORP. Method Statement For
Adjustment of Installed
Steel Doors from Finish Floor Line
Solaire North Project

V. EXECUTION

1. Chipped the perimeter of door jamb until the rebar is exposed


2. Ensure that the rebars connected on door jamb is intact
3. Safely Remove the Door jamb and put it on undisturb area
4. Chipped the excess Concete on the Door Opening
5. Provide layout of the 20mm adjusted Finish Floor line
6. Check to ensure the frame has not moved away from the layout lines
7.
8. Verify
Recheck that
thethe head
level of of the frame
accuracy is level
after you make every adjustment. With the frame in place, re install the
door hinges and dor closer
place, re install the door hinges and dor closer
9. Fill the gaps with mortar evenly up both sides. Lightly tap the frame to
settle the mortar

VI. Protection
1. Provide warning signs, protective barriers, and warning lights as necessary
adjacent to the work as approved or required. Maintain these items during
the demolition period.
2. Undertake no demolition work until all mechanical and electrical services in
service either permanently or temporarily in a manner that will not interfere
with the operation of the remaining facilities.
3. Provide dust control

VII. Inspection
1. Contractor will request for the inspection at every phase of the work.
2. Contractor will request for the final acceptance of the floor finish.