Download as pdf or txt
Download as pdf or txt
You are on page 1of 42

PETRONAS CARIGALI SDN BHD

SCAFFOLDING ERECTION TO ASSIST IP FOR


PL340: 10” X 1.850 KM OIL TRUNKLINE FROM WLDP-A TO WLP-A

PO NO: 3400332957

CLOSE-OUT REPORT
Report No: P589/2023/SKA/COR REV00
Prepared by:

HALUAN CEKAP SDN BHD


Prepared by Reviewed by Reviewed by Approved by
Pipeline Engineer Project Manager Pipeline Engineer Team Leader
Position
(HCSB) (HCSB)

Signature

WAN MOHD
Name RACHEL ROSPHIA
HIDAYAT

Date 24.05.2023 16/06/2023


CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

TABLE OF CONTENTS Tick - √ /NA

1 Introduction √
2 Objective √
3 Period Work Performed √
4 Summary Scope of Work √
5 Organization & Manning √
6 Safety Statistic √
7 QA/QC Result NA
8 Inspection Findings and Recommendation NA
9 Project Man-hours/Performance Analysis √
10 Progress S-Curve √
11 Outstanding Scope of Work/Punchlist NA
12 Material Management – Surplus Materials NA
13 Drop Scope NA
14 Emergent Work/Construction Work Request (CWR) NA
15 Lesson Learnt & Best Practices √
16 Conclusion √
17 Attachments √

i. Consignments of Goods (COG) √


ii. Daily Progress Report (DPR) √

Note: Additional items can be added based on activities’ requirements.


CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

1. INTRODUCTION
This report highlights the work completed for Scaffolding Erection to Assist IP for
i. PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A
The execution was performed on 4th May 2023. The objective of this report is to describe the work done that
had been carried out throughout the project execution from beginning until the completion of the project
including site findings and lesson learnt during the execution. Moreover, it is also to authenticate that HCSB
had successfully completed the scope of works and handover the pipeline back to PCSB operations.

2. OBJECTIVE
The objective of this project is to assist ROSEN for online IP PL340 in terms scaffolding erection at launcher barrel
door and receiver barrel door.

3. PERIOD WORK PERFORMED


Mobilization and demobilization of equipment during pre-execution and post-execution was load out to LCT MK1.
The date of equipment mobilization and demobilization are as per Table 3.1 below. Further details can be
referred to Appendix A: Consignment of Goods (COG).

Table 3.1: Equipment Mobilization and Demobilization for PL340


NO DATE DESCRIPTION FROM TO
EQUIPMENT MOBILIZATION
FROM
➢ HCSB-OTT-018 - Open Top Tray West Lutong
1 29/4/2023 BPA VIA
(Scaffolding materials (2 set)) Field
LCT MK1
TOTAL: 1 LIFT
EQUIPMENT LIFTED TO PLATFORM
2 1/5/2023 ➢ Scaffolding set LCT MK1 WLP-A
TOTAL: 1 LIFT

EQUIPMENT LIFTED TO PLATFORM


3 1/5/2023 ➢ Scaffolding set LCT MK1 WLP-C
TOTAL: 1 LIFT

EQUIPMENT DEMOBILIZATION
TO BPA VIA
➢ HCSB-OTT-018 - Open Top Tray WLP-A /
5 21/5/2023 LCT SK
(Scaffolding materials (2 set)) WLP-C
SEAHAWK
TOTAL: 1 LIFT

For manpower mobilization, a total of four (4) pax of HCSB mobilized to West Lutong field on 10th April 2023
performing PL220 was utilized for scaffold erection at WLP-A and WLDP-A.
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

4. SUMMARY SCOPE OF WORK (SOW)

Summary of job scope is as below:


Table 4.1: Summary of SOW
FINISH
No. ACTIVITY DATE REMARK
DATE
PRE-EXECUTION
1 Equipment mobilization from BPA 03.05.2023 03.05.2023 Completed
2 Lifting activity at WLP-A 05.05.2023 05.05.2023 Completed
3 Lifting activity at WLDP-C 05.05.2023 05.05.2023 Completed
4 Worksite preparation and scaffolding erection 05.05.2023 05.05.2023 Completed
EXECUTION
PL220 NITROGEN PURGING
1 To assist PL340 online IP 06.05.2023 12.05.2023 Completed
2 Reinstatement 12.05.2023 12.05.2023 Completed
POST-EXECUTION

1 Dismantle scaffolding erections 12.05.2023 12.05.2023 Completed

2 Housekeeping 13.05.2023 18.05.2023 Completed

3 Backloading activity 19.05.2023 21.05.2023 Completed

Details of the summary execution activity can be referred to Appendix B – Daily Progress Report (DPR)
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

JOB SUMMARY DETAILS


1. PL340
i) Scaffolding erection at PL340 (WLDP-C)

Scaffolding erection was successfully erected at WLDP-C and WLP-A to assist IP tools to be launched onto PL340
launcher barrel and IP retrieval to minimize heavy manual handling of IP tools.

Figure 4.4: Scaffold erected at PL340 (WLDP-C) - LAUNCHER

Figure 4.5: Scaffold erected at PL340 (WLP-A) - RECEIVER


CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

5. ORGANIZATION & MANNING

Project Manager
Wan M. Hidayat

Head of Dept
Project Engineer Wong Kang Yuon
Ahmad Shahrul Zulfikli B Razali

Field Engineer Project Engineer


Rachel Rosphia Lily Sulau Merang

Scaffolder Inspector
1 pax

Rigger
3 Pax
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

SAFETY STATISTIC
Items Description Cumulative
A HSE Statistics
Total Man Hours Worked 936
Fatality 0
Near Miss 0
Lost Time Injury (LTI) 0
Restricted Work Case (RWC) 0
Medical Treatment Case (MTC) 0
First Aid Case (FAC) 0
Occupational Illness (OI) 0
Fire / Explosion Case 0
Property Damage 0

B Unsafe Act / Unsafe Conditions


Unsafe Act 0
Unsafe Condition 0
Safe Act 36
Total: 36

C Meetings
Pre-mob Meeting 1
Toolbox Meetings Everyday

D HSE Enhancement Activities


CC Card Compliance – PTW Awareness & e-PTW 1
Escape Route & Mustering Station Briefing at site 1

E Audit / Inspection
Equipment Inspection 0
Function Test on Equipment 0
Safety Walkabout at site 1
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

7. PROJECT MAN-HOURS/PERFORMANCE ANALYSIS

No Description Manhours
1 Lifting Equipment at WLPA / WLDP-C 192
2 Site preparations 288
3 Scaffolding Erections at WLP-A / WLDP-C 302
4 Reinstatement and housekeeping 50
5 Backloading 54
6 Others (including stand-by/mob/de-mob/FCB U-Turn) 50
Total Manhours 936
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

8. PROGRESS S-CURVE
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

9. LESSON LEARNT & BEST PRACTICES


This section includes the recommendations for future. Throughout the equipment mobilization, execution and
demobilization, some lesson learnt are captured and shared in this report.
Subject Issues Consequences Way Forward / Improvement
1. Contract/Purchase 1. No issue at site 1. No issue at site 1. QSM2 to confirm the validity
order of PO issued to HCSB to
proceed with execution.

Pre-execution
1. Procedure 1. No issue at site 1. No issue at site 1. Site visit is required prior to
job execution activity.
2. Work scope to be firmed.

Pre-Execution
1. Mobilization of 1. No issue at site 1. No issue at site 1. Delaying mobilization of
equipment 2. Lifting was 2. Lifting of equipment will be affecting
2. Lifting of equipment to delayed due to equipment was the schedule.
platform space delayed for 2 2. For execution, lifting of
3. Mobilization of constraint, weeks equipment must be
manpower weather 3. No issue at site prioritized and movement of
4. Laydown space area constraint and 4. No issue at site LCT need to be updated to
5. Equipment setup and unavailability avoid delay in activity.
preparation of crane 3. Information regarding FCB
operator/jib movement for the
crane mobilization of crew to be
3. No issue at site firmed
4. No issue at site 4. All contractor needs to
discuss and agree to allow
the execution for
priority/emergency job
5. Equipment setup and
preparation should be done
as per schedule to ensure
execution not delayed.

Execution
1. Crew movement 1. No issue at site 1. No issue 1. Personnel transportation for
2. Project execution 2. No issue at site 2. No issue at site crew must be in good
3. Site planning 3. No issue at site 3. No issue at site condition during
mobilization to MPACCT
2. Work leader/PSS to ensure
work is completed as per
work pack before
demobilization.
HSE No issue No issue 1. Alert to weather forecast
2. No boat transfer should be
allowed during bad weather
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

10. CONCLUSION

Haluan Cekap Sdn Bhd is pleased to confirm the completion of Scaffolding Erection to Assist IP PL340.
Haluan Cekap Sdn. Bhd is honored to be given the privilege to provide and serve PETRONAS Carigali Sdn Bhd
in this activity.

Completion of SKA Pipeline West Lutong Field for to assist ROSEN on scaffolding erection for PL340 was
performed within the given approved schedule to complete the activities.

Throughout the entire duration of the project, Haluan Cekap has never compromise the health and safety of
every personnel involved during the execution. We have undertaken some efforts to exercise HSE which
includes: -

a) Toolbox meeting every morning


b) Record and compile Unsafe Act Unsafe Condition (UAUC) found at site.

The exercise has brought zero LTI and zero incident/accident. In conclusion, this project has been completed
with satisfactory to both PETRONAS CARIGALI SDN.BHD and HALUAN CEKAP SDN.BHD.

11. APPENDICES

APPENDIX a: CONSIGNMENT OF GOODS (COG)


APPENDIX b: DAILY PROGRESS REPORT (DPR)
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

APPENDIX A:
CONSIGNMENT OF GOODS
(COG)
HALUAN CEKAP SDN BHD ( 641632-A )
PIPELINE DEPARTMENT,LOT 2694 & 2695,PERMYJAYA TECHNOLOGY PARK,
BLOCK 6,KUALA BARAM LAND DISTRICT,98100,MIRI-SARAWAK.
OFFICE NO: 085-650100 FAX NO : 085-650400

CONSIGNMENT OF GOODS / SHIPPING INVOICE

CONSIGNEE : HALUAN CEKAP SDN BHD (MIRI) COG NO: HCSB/COG/2/MOB/P679/01

TO LOCATION : WEST LUTONG (WLP-A) DATE: 25/4/2023

PROJECT : PL220 NITROGEN PURGING JOB NO: P679

SHIPPER : HALUAN CEKAP SDN BHD (MIRI) PAGE: 1 OF 1

VESSEL NAME : VIA LCT


Please receive the undermentioned materials:-

TARE MAXIMUM GROSS


DIMENSION COUNTRY OF UNIT PRICE
ITEM NO. TAG ID FULL DESCRIPTION QTY UNIT WEIGHT WEIGHT
L X W X H (M) ORIGIN (RM)
(KG) (KG)

1 HCSB-OTT-018 Open Top Tray C/W 4-legged sling (For scaffolding materials) 1 UNIT 850 4350 1.43 (W) X 3.25 (L) X 1.25(H) MALAYSIA -
2 HCSB-HN- 160bar Nitrogen Racks C/W 4 legged sling 4 UNIT 1300 6500 1.08(W) X 1.08(L) X 1.92(H) MALAYSIA -

Total Nett Weight (Kilograms) :- 2,150.00 10,850.0 Total Amount -


Remarks:-
Total Of Packages We hereby certify this invoice to be true and correct. Received By;
COG PREPARED BY ; MATERIAL ISSUED BY; VERIFIED BY;

5
Name : RACHEL ROSPHIA Name : KHAIRUDDIN MUSTAFA Name : KHAIRUDDIN MUSTAFA Name :
Designate : PIPELINE ENGINEER Designate : LOGISTIC ASSISTANT Designate : LOGISTIC ASSISTANT Designate :
Date : 25/4/2023 Date : 25/4/2023 Date : 25/4/2023 Date :
For HALUAN CEKAP SDN BHD ( PIPELINE DEPARTMENT )
Important**
COPY OF THIS CONSIGNMENT NOTE MUST RETURNED/FAXED UPON ACKNOWLEDGE RECEIPT TO LOGISTIC DEPT, FAX :(085-322654)
For immediate action, please identify if there is any discrepancies found
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00

APPENDIX B:
DAILY PROGRESS REPORT
(DPR)
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 03.04.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 3

2 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 3

3 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 3


4 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 3
5 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 3
6 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 3

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 90 2192
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 03.04.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES

0600 HRS CHECK IN AT MPACCT

MOBILIZE TO WEST LUTONG FIELD

0745 HRS ARRIVED AT WEST LUTONG FIELD

0900 HRS Permit application

1000 HRS Morning meeting with operation and report to OS on lifting activity

1330 HRS Outstation to WL-Charlie

Dismantle scaffolding at WLP-C for PL238

Handover PL238 to operation

Transfer scaffold material to WLDP-C from WLP-C for PL340 table scaffold erection

Scaffold erection for PL340

1630 HRS Lifting activity at WLP-C to FCB Jati Eight to transfer loose N2 to OLVV1 and lift up at WLK-A

Assist operation on lifting activity at WLP-C once jib crane has enough gas supply for material under 500kg

Housekeeping deck area and rearrange all materials and equipment to a designated area

Permit suspension

2100 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 2.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 85.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) ( LILY SULAU MERANG )
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 04.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 2

2 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 2

3 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2


4 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2
5 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 2
6 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 2

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 84 2276
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 04.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES

0600 HRS CHECK IN AT MPACCT

MOBILIZE TO WEST LUTONG FIELD

0745 HRS ARRIVED AT WEST LUTONG FIELD

0900 HRS Permit application

Meeting with operation on today's activity and handover activity

1400 HRS Outstation to WL-Charlie

Awaiting for LCT to alongside the platform for lifting


Due to jib crane has no gas supply, the lifting activity was put on hold and to transfer all material from LCT to OLVV1
Lifting of equipment to Charlie via OLVV1 crane
Assist Riser Maintenance team to carry out lifting activity

Walkabout with SOR on PL340 for preparation of online IP. To discuss on cleaning run for PL340 execution date.

Housekeeping

Permit suspension

2000 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) ( LILY SULAU MERANG )
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 05.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 4

2 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 4

3 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 4


4 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 4
5 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 4
6 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 4

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 96 2372
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 05.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES

0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

0930 HRS Toolbox meeting and handover meeting with operation

Permit application

1100 HRS Outstation to WLP-A

scaffold erection at PL340 receiver barrel door

Communicate with launcher side to inform receiver side are ready.

Monitor possible pressure at receiver and launcher side before pig is launch (witnessed by operations)

1530 HRS Launch Bi-Di Brush Gauge Plate (cleaning run) for PL340 at 0.22m/s for 2 HRS 18MINS

1800 HRS Pig has arrived at receiver barrel.

Unable to perform pig retrieval

Housekeeping

Permit suspension

2200 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 1.6% 1.6%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 5.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 92.6% 91.6%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 06.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 4

2 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 4

3 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 4


4 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 4
5 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 4
6 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 4

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 96 2468
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 06.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES

0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

0930 HRS Toolbox meeting with operation

Permit application

Outstation to WLP-A and WLP-C for Bi-Di Magnet Brush pig launching and retrieve Bi-di gauge plate

1150 HRS Launch Bi-Di Brush pig with Magnet


Continuous monitor pressure gauge

1500 HRS Bi-di brush pig with magnet arrived at receiver barrel
Decontamination of pig

Assist ROSEN to capture debris from the magnet

Results from 2 run of Bi-Di Brush was OK. MFL run will be conduct on the next working hours

Housekeeping

Permit suspension

2200 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 3.2% 3.2%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 94.2% 90.2%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 07.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 2

2 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 2

3 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2


4 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2
5 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 2
6 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 2

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 84 2552
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 07.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

0930 HRS Toolbox meeting with operation

Permit application

1100 HRS Outstation to WLP-A and WLP-C for MFL run

1230 HRS Assist ROSEN on MFL preparation


WL-Charlie was down due to unstable of gas supply

MFL was not charged and its battery level was 13%

Transfer MFL to WL-Alpha for charging after WL-Charlie able to start-up

1530 HRS WL-Charlie able to start-up and MFL was lifted back to WL-Alpha for charging

Lifting MFL to FCB

Outstation back to WL-Alpha

1630 HRS Progress meeting with OS

Housekeeping
Permit suspension

2000 HRS Arrived at MPACCT


ACTIVITIES PLANNED FOR NEXT 12 HOURS
1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 3.2%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 90.2%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 08.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 4

2 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 4

3 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 4


4 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 4
5 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 4
6 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 4

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 96 2648
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 08.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field.

1000 HRS Toolbox meeting with operation

Permit application

1100 HRS Check on MFL battery level


MFL was still charging and cannot be run

As WL-Charlie still unable to start-up, assist operation team on material transfer and lifting activity at WL-Alpha

1400 HRS Lifting from LCT SK Seahawk to WLK-A. Total lifts: 18 lifts

Re-arrange chemical drums at WLK-A main deck upon completion of lifting activity

1630 HRS Backloading HCSB material


Unable to backload as LCT was rushed to the other field

Assist operation to collect all loose items at Alpha as sudden weather pick-up

1800 HRS Final housekeeping

Permit suspension

Awaiting FCB to alongside at WLK-A boat landing (FCB unable to pickup). For safety reason, boat transfer to FCB was done at WLDP-A boat landing

2200 HRS Arrived at MPACCT


ACTIVITIES PLANNED FOR NEXT 12 HOURS
1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 3.2%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 90.2%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 09.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2
3 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 2
4 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 2
5 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 2
6 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 2

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 84 2732
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 09.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

1000 HRS Toolbox meeting with operation

Permit application

1130 HRS Outstation to WLP-C

Assist ROSEN to re-align the scaffold table for MFL launching

Due to WLP-Charlie was suddenly down, HCSB crew were asked to assist operation for housekeeping prior for lifting activity

Re-arrange chemical drums at WLP-C main deck

Re-arrange nitrogen racks and loose bottles to designated area to avoid blocking escape route

Transfer scaffolding materials to designated place on platform to avoid loose tools scattered during adverse weather

1630 HRS At WL-Alpha, attend meeting with Operation

Assist operation to erect scaffolding at drilling platform to provide better surface to access to valve opening

Housekeeping
Permit suspension
2000 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 10.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2
3 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 2
4 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 2
5 RACHEL ROSPHIA FIELD ENGINEER WEST LUTONG OFFSHORE 12 2
6 DESMOND MISIN RECEIVER SUPERVISOR WEST LUTONG OFFSHORE 12 2

TOTAL POB 6

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 84 2816
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 10.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

1000 HRS Toolbox meeting with operation

Permit application

1200 HRS Outstation to WLP-A

Perform scaffolding measurement taking for PL358 (to assist scaffold erection for GASB)

Assist operation to perform lifting activity for chemical drums (10 lifts)

Re-arrange drums at main deck at designated area

1630 HRS Meeting with OS for lifting planning to OLVV1 by using its crane (to help transfer materials from Charlie to Alpha)

Permit application for lifting activity via OLVV1 with OS approval and briefed CO for next working day

Housekeeping

Permit suspension for today activity

Toolbox meeting with crew on tomorrow plan and divide to two group

2000 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 11.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2
3 KELVIN JIMY RIGGER WEST LUTONG OFFSHORE 12 2
4 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 2

TOTAL POB 4

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 56 2872
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 11.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

1030 HRS Toolbox meeting with operation

Permit application

1200 HRS Outstation to WLP-C

Contact OLVV1 for lifting activity for equipment transfer to WLK-A

Submit lifting PTW to OLVV1 to start lifting activity

Start lifting activity at WLP-C

Lifting of operation materials to OLVV1 (12 lifts)

Lifting of HCSB materials (3 lifts)

1630 HRS Outstation to WLK-A


Lifting of materials from OLVV1 to WLK-A (15 lifts)

Arrange all materials at WLK-A and perform Housekeeping

Permit suspension

2000 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 12.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 4
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 4

3 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 4

TOTAL POB 3

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 48 2920
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 12.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

1000 HRS Toolbox meeting with operation and handover meeting (crew change)

Permit application

1100 HRS Outstation to WLP-A and WLP-C

Preparation of MFL launching (online)


Awaiting for WLP‐C to start‐up
Once WLP‐C start‐up, to launch the MFL into PL340

1200 HRS Assist operation for platform start-up

1300 HRS Load MFL into launcher barrel. Assist Operation to open valve to launch the pig by using product

1455 HRS Launch MFL @ 0.22m/s

1800 HRS MFL has arrived at receiver barrel


Due to time constraint and low visibility at work area, the MFL shall be retrieved on the next day (for safety reason)

Housekeeping

Permit suspension

2200 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 4.0%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 91.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 13.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG ONSHORE 8 0
2 CYRIL CHARLES RIGGER WEST LUTONG ONSHORE 8 0

3 VINCENT JANG SCAFFOLDER INS. WEST LUTONG ONSHORE 8 0

TOTAL POB 3

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 24 2944
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 13.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES

0800 - 1700 HRS FATIGUE MANAGEMENT DAY (FMD)

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 4.0%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 91.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 14.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2

3 VINCENT JANG SCAFFOLDER INS. WEST LUTONG OFFSHORE 12 2

TOTAL POB 3

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 42 2986
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 14.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

0930 HRS Toolbox meeting with operation

Permit application

1130 HRS Outstation to WLP-A

1330 HRS Assist ROSEN on pig retrieval (stuck due to a magnet)

1430 HRS Decontamination of MFL upon retrieval and capture results witnessed by site operation

Dismantle scaffolding at WL-Alpha and re-arrange material for backloading at loading bay (unable to backload due to late arrival of LCT)

1645 HRS Progress meeting with operation

Housekeeping

Permit suspension

2000 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 5.0%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 4.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 4.0% 3.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 98.0% 95.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 15.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 0
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 0

TOTAL POB 2

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 24 3010
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - -
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 15.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0800 HRS Mobilize to West Lutong field

0915 HRS Arrive at West Lutong field

Due to heavy rain, boat transfer was put on hold until OS instruct to proceed (for safety reason)

1030 HRS All personnel able to perform boat transfer

1100 HRS Toolbox meeting

Permit application

1300 HRS Outstation to WLP-A for housekeeping

Due to sudden weather pickup, all activity was stop and return to muster station and await FCB to able alongside to platform for pick up

1530 HRS FCB U-Turn due to adverse weather

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 5.0%
4

POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 4.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 94.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 16.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 0800 HRS GOOD WEATHER
1700 HRS GOOD WEATHER

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 LESLEY DING LIHAN RIGGER WEST LUTONG OFFSHORE 12 2
2 CYRIL CHARLES RIGGER WEST LUTONG OFFSHORE 12 2

TOTAL POB 2

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 10.04.2023 28 3038
2 NUMBER OF LOST WORKDAYS (FOR LTIs) - 4
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) - -
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) - -
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) - -
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) - -
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) - -
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) - -
9 NUMBER OF NEAR MISSES (ON JOB SITE) - -
10 MEDICAL EVACUATION (MEDIVAC) - -

No. EQUIPMENT QTY LOCATION STATUS UAUC / BOT


1 TOOLBOX 2 WL OFFSHORE Submission UAUC / BOT ACCUMULATIVE
2 SCAFFOLDING SET 1 WL OFFSHORE
6 6 30

CONSUMABLE QTY LOCATION


160 BAR N2 RACKS 4 OFFSHORE
4 LOOSE CYLINDERS 4 OFFSHORE
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation

Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)


PL340 Scaffold erection to assist IP
Job no: P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 16.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
0600 HRS Check in at MPACCT

0745 HRS Mobilize to West Lutong field

0845 HRS Arrive at West Lutong field

1000 HRS Toolbox meeting with operation

1130 HRS Permit revalidation

1200 HRS Outstation to WLP-A

Transfer scaffolding materials to loading bay and keep it secured to avoid drop objects during lifting to FCB

Re-arrange all HCSB equipment and material to loading bay as LCT will arive in the noon

1500 HRS Outstation to WLK-A

Re-arrange all HCSB equipment along with ROSEN tools for backloading when LCT has arrived

1600 HRS LCT has arrived for backloading


Unable to perform backloading due to LCT main deck was congested and full. LCT has to depart back to BPA on 16.05.2023

Re-arrange back all materials and equipment out from loading bay area to avoid blocking escape route and loading bay

Housekeeping

Permit suspension

2000 HRS Arrived at MPACCT

ACTIVITIES PLANNED FOR NEXT 12 HOURS


1
2
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMP. DATE
PRE‐EXECUTION
1 Lifting activity at TKP-A 5.0 5.0% 5.0%
2 Lifting Activity at TKP-C 5.0 5.0% 5.0%
3 Worksite preparation at launcher site 10.0 10.0% 10.0%
4 Worksite preparation at receiver site 10.0 10.0% 10.0%
5 Worksite preparation at WL-4 (looping point) 5.0 5.0% 5.0%
6 Scaffolding erections for oddbolting at WLP-C 10.0 10.0% 10.0%
7 PL220 Depressurisation 10.0 10.0% 10.0%

EXECUTION FOR PL220 Nitrogen Purging (P679)


1 PL220 gas displacement activity 5.0 5.0% 5.0%
2 PL220 nitrogen purging for leak detection 5.0 5.0% 5.0%
3 Reinstatement of PL220 after Nitrogen Purging 2.0 2.0% 2.0%
EXECUTION FOR PL340 SCAFFOLD ERECTION (P689)
1 Site walkabout at WLP-A and WLP-C 4.0 4.0% 4.0%
2 Erect Scaffolding 5.0 5.0% 5.0%
3 Assist Online IP 5.0 5.0% 5.0%
4
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 4.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 4.0% 3.0%
Backloading 5.0 5.0% 2.0%
TOTAL 100.0 100.0% 95.0%

Prepared by: Acknowledged by:

____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset

You might also like