COR SKA - Scaffolding Erection To Assist IP PL340 - Signed
COR SKA - Scaffolding Erection To Assist IP PL340 - Signed
PO NO: 3400332957
CLOSE-OUT REPORT
Report No: P589/2023/SKA/COR REV00
Prepared by:
Signature
WAN MOHD
Name RACHEL ROSPHIA
HIDAYAT
1 Introduction √
2 Objective √
3 Period Work Performed √
4 Summary Scope of Work √
5 Organization & Manning √
6 Safety Statistic √
7 QA/QC Result NA
8 Inspection Findings and Recommendation NA
9 Project Man-hours/Performance Analysis √
10 Progress S-Curve √
11 Outstanding Scope of Work/Punchlist NA
12 Material Management – Surplus Materials NA
13 Drop Scope NA
14 Emergent Work/Construction Work Request (CWR) NA
15 Lesson Learnt & Best Practices √
16 Conclusion √
17 Attachments √
1. INTRODUCTION
This report highlights the work completed for Scaffolding Erection to Assist IP for
i. PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A
The execution was performed on 4th May 2023. The objective of this report is to describe the work done that
had been carried out throughout the project execution from beginning until the completion of the project
including site findings and lesson learnt during the execution. Moreover, it is also to authenticate that HCSB
had successfully completed the scope of works and handover the pipeline back to PCSB operations.
2. OBJECTIVE
The objective of this project is to assist ROSEN for online IP PL340 in terms scaffolding erection at launcher barrel
door and receiver barrel door.
EQUIPMENT DEMOBILIZATION
TO BPA VIA
➢ HCSB-OTT-018 - Open Top Tray WLP-A /
5 21/5/2023 LCT SK
(Scaffolding materials (2 set)) WLP-C
SEAHAWK
TOTAL: 1 LIFT
For manpower mobilization, a total of four (4) pax of HCSB mobilized to West Lutong field on 10th April 2023
performing PL220 was utilized for scaffold erection at WLP-A and WLDP-A.
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
Details of the summary execution activity can be referred to Appendix B – Daily Progress Report (DPR)
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
Scaffolding erection was successfully erected at WLDP-C and WLP-A to assist IP tools to be launched onto PL340
launcher barrel and IP retrieval to minimize heavy manual handling of IP tools.
Project Manager
Wan M. Hidayat
Head of Dept
Project Engineer Wong Kang Yuon
Ahmad Shahrul Zulfikli B Razali
Scaffolder Inspector
1 pax
Rigger
3 Pax
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
SAFETY STATISTIC
Items Description Cumulative
A HSE Statistics
Total Man Hours Worked 936
Fatality 0
Near Miss 0
Lost Time Injury (LTI) 0
Restricted Work Case (RWC) 0
Medical Treatment Case (MTC) 0
First Aid Case (FAC) 0
Occupational Illness (OI) 0
Fire / Explosion Case 0
Property Damage 0
C Meetings
Pre-mob Meeting 1
Toolbox Meetings Everyday
E Audit / Inspection
Equipment Inspection 0
Function Test on Equipment 0
Safety Walkabout at site 1
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
No Description Manhours
1 Lifting Equipment at WLPA / WLDP-C 192
2 Site preparations 288
3 Scaffolding Erections at WLP-A / WLDP-C 302
4 Reinstatement and housekeeping 50
5 Backloading 54
6 Others (including stand-by/mob/de-mob/FCB U-Turn) 50
Total Manhours 936
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
8. PROGRESS S-CURVE
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
Pre-execution
1. Procedure 1. No issue at site 1. No issue at site 1. Site visit is required prior to
job execution activity.
2. Work scope to be firmed.
Pre-Execution
1. Mobilization of 1. No issue at site 1. No issue at site 1. Delaying mobilization of
equipment 2. Lifting was 2. Lifting of equipment will be affecting
2. Lifting of equipment to delayed due to equipment was the schedule.
platform space delayed for 2 2. For execution, lifting of
3. Mobilization of constraint, weeks equipment must be
manpower weather 3. No issue at site prioritized and movement of
4. Laydown space area constraint and 4. No issue at site LCT need to be updated to
5. Equipment setup and unavailability avoid delay in activity.
preparation of crane 3. Information regarding FCB
operator/jib movement for the
crane mobilization of crew to be
3. No issue at site firmed
4. No issue at site 4. All contractor needs to
discuss and agree to allow
the execution for
priority/emergency job
5. Equipment setup and
preparation should be done
as per schedule to ensure
execution not delayed.
Execution
1. Crew movement 1. No issue at site 1. No issue 1. Personnel transportation for
2. Project execution 2. No issue at site 2. No issue at site crew must be in good
3. Site planning 3. No issue at site 3. No issue at site condition during
mobilization to MPACCT
2. Work leader/PSS to ensure
work is completed as per
work pack before
demobilization.
HSE No issue No issue 1. Alert to weather forecast
2. No boat transfer should be
allowed during bad weather
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
10. CONCLUSION
Haluan Cekap Sdn Bhd is pleased to confirm the completion of Scaffolding Erection to Assist IP PL340.
Haluan Cekap Sdn. Bhd is honored to be given the privilege to provide and serve PETRONAS Carigali Sdn Bhd
in this activity.
Completion of SKA Pipeline West Lutong Field for to assist ROSEN on scaffolding erection for PL340 was
performed within the given approved schedule to complete the activities.
Throughout the entire duration of the project, Haluan Cekap has never compromise the health and safety of
every personnel involved during the execution. We have undertaken some efforts to exercise HSE which
includes: -
The exercise has brought zero LTI and zero incident/accident. In conclusion, this project has been completed
with satisfactory to both PETRONAS CARIGALI SDN.BHD and HALUAN CEKAP SDN.BHD.
11. APPENDICES
APPENDIX A:
CONSIGNMENT OF GOODS
(COG)
HALUAN CEKAP SDN BHD ( 641632-A )
PIPELINE DEPARTMENT,LOT 2694 & 2695,PERMYJAYA TECHNOLOGY PARK,
BLOCK 6,KUALA BARAM LAND DISTRICT,98100,MIRI-SARAWAK.
OFFICE NO: 085-650100 FAX NO : 085-650400
1 HCSB-OTT-018 Open Top Tray C/W 4-legged sling (For scaffolding materials) 1 UNIT 850 4350 1.43 (W) X 3.25 (L) X 1.25(H) MALAYSIA -
2 HCSB-HN- 160bar Nitrogen Racks C/W 4 legged sling 4 UNIT 1300 6500 1.08(W) X 1.08(L) X 1.92(H) MALAYSIA -
5
Name : RACHEL ROSPHIA Name : KHAIRUDDIN MUSTAFA Name : KHAIRUDDIN MUSTAFA Name :
Designate : PIPELINE ENGINEER Designate : LOGISTIC ASSISTANT Designate : LOGISTIC ASSISTANT Designate :
Date : 25/4/2023 Date : 25/4/2023 Date : 25/4/2023 Date :
For HALUAN CEKAP SDN BHD ( PIPELINE DEPARTMENT )
Important**
COPY OF THIS CONSIGNMENT NOTE MUST RETURNED/FAXED UPON ACKNOWLEDGE RECEIPT TO LOGISTIC DEPT, FAX :(085-322654)
For immediate action, please identify if there is any discrepancies found
CLOSE OUT REPORT 24th May 2023
SCAFFOLDING ERECTION TO ASSIST IP FOR
PL340: 10” X 1.850KM Oil Trunkline from WLDP-A to WLP-A P589/2023/SKA/COR
HALUAN CEKAP SDN BHD Rev. 00
APPENDIX B:
DAILY PROGRESS REPORT
(DPR)
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 03.04.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 03.04.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
1000 HRS Morning meeting with operation and report to OS on lifting activity
Transfer scaffold material to WLDP-C from WLP-C for PL340 table scaffold erection
1630 HRS Lifting activity at WLP-C to FCB Jati Eight to transfer loose N2 to OLVV1 and lift up at WLK-A
Assist operation on lifting activity at WLP-C once jib crane has enough gas supply for material under 500kg
Housekeeping deck area and rearrange all materials and equipment to a designated area
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 85.0%
____________________________________
(RACHEL ROSPHIA) ( LILY SULAU MERANG )
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 04.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
PL220 NITROGEN PURGING / PL340 Scaffold erection to assist
Project Title: To: Petronas Carigali Sdn Bhd (Sarawak Asset)
IP
Job no: P679 / P689 Attn: LILY SULAU MERANG
Client: PCSB - SKA (QSM 2 Pipeline & Structural Engineering) CC: Haluan Cekap Sdn Bhd
Date: 04.05.2023 WAN MOHD HIDAYAT/AHMAD SHAHRUL
Location: WEST LUTONG FIELD
Contract no: SKO/BTS-32/2017/1002 From: RACHEL ROSPHIA
PROGRESS NARRATIVE
TIME ACTIVITIES
Walkabout with SOR on PL340 for preparation of online IP. To discuss on cleaning run for PL340 execution date.
Housekeeping
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%
____________________________________
(RACHEL ROSPHIA) ( LILY SULAU MERANG )
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
Monitor possible pressure at receiver and launcher side before pig is launch (witnessed by operations)
1530 HRS Launch Bi-Di Brush Gauge Plate (cleaning run) for PL340 at 0.22m/s for 2 HRS 18MINS
Housekeeping
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 5.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 92.6% 91.6%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
Outstation to WLP-A and WLP-C for Bi-Di Magnet Brush pig launching and retrieve Bi-di gauge plate
1500 HRS Bi-di brush pig with magnet arrived at receiver barrel
Decontamination of pig
Results from 2 run of Bi-Di Brush was OK. MFL run will be conduct on the next working hours
Housekeeping
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 94.2% 90.2%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
MFL was not charged and its battery level was 13%
1530 HRS WL-Charlie able to start-up and MFL was lifted back to WL-Alpha for charging
Housekeeping
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 90.2%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
As WL-Charlie still unable to start-up, assist operation team on material transfer and lifting activity at WL-Alpha
1400 HRS Lifting from LCT SK Seahawk to WLK-A. Total lifts: 18 lifts
Re-arrange chemical drums at WLK-A main deck upon completion of lifting activity
Assist operation to collect all loose items at Alpha as sudden weather pick-up
Permit suspension
Awaiting FCB to alongside at WLK-A boat landing (FCB unable to pickup). For safety reason, boat transfer to FCB was done at WLDP-A boat landing
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 90.2%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
Due to WLP-Charlie was suddenly down, HCSB crew were asked to assist operation for housekeeping prior for lifting activity
Re-arrange nitrogen racks and loose bottles to designated area to avoid blocking escape route
Transfer scaffolding materials to designated place on platform to avoid loose tools scattered during adverse weather
Assist operation to erect scaffolding at drilling platform to provide better surface to access to valve opening
Housekeeping
Permit suspension
2000 HRS Arrived at MPACCT
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 6
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
Perform scaffolding measurement taking for PL358 (to assist scaffold erection for GASB)
Assist operation to perform lifting activity for chemical drums (10 lifts)
1630 HRS Meeting with OS for lifting planning to OLVV1 by using its crane (to help transfer materials from Charlie to Alpha)
Permit application for lifting activity via OLVV1 with OS approval and briefed CO for next working day
Housekeeping
Toolbox meeting with crew on tomorrow plan and divide to two group
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 4
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 91.0% 87.0%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 3
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
1000 HRS Toolbox meeting with operation and handover meeting (crew change)
Permit application
1300 HRS Load MFL into launcher barrel. Assist Operation to open valve to launch the pig by using product
Housekeeping
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 91.0%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 3
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 2.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 91.0%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 3
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Permit application
1430 HRS Decontamination of MFL upon retrieval and capture results witnessed by site operation
Dismantle scaffolding at WL-Alpha and re-arrange material for backloading at loading bay (unable to backload due to late arrival of LCT)
Housekeeping
Permit suspension
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 4.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 4.0% 3.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 98.0% 95.0%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 2
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Due to heavy rain, boat transfer was put on hold until OS instruct to proceed (for safety reason)
Permit application
Due to sudden weather pickup, all activity was stop and return to muster station and await FCB to able alongside to platform for pick up
POST‐EXECUTION
Dismantle Scaffolding 5.0 5.0% 4.0%
PL286 Nitrogen top up (to reflow) - to assist operation 5.0 5.0% 5.0%
Housekeeping 4.0 2.0% 2.0%
Backloading 5.0 3.0% 2.0%
TOTAL 100.0 96.0% 94.0%
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: 10.10.2016
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 2
Document Type: Supporting Documentation
TOTAL POB 2
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 2
Document Type: Supporting Documentation
Transfer scaffolding materials to loading bay and keep it secured to avoid drop objects during lifting to FCB
Re-arrange all HCSB equipment and material to loading bay as LCT will arive in the noon
Re-arrange all HCSB equipment along with ROSEN tools for backloading when LCT has arrived
Re-arrange back all materials and equipment out from loading bay area to avoid blocking escape route and loading bay
Housekeeping
Permit suspension
____________________________________
(RACHEL ROSPHIA) (RICKY SEBIT)
FIELD ENGINEER ENGINEER / CLIENT SITE REPRESENTATIVE
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ Sarawak Asset