Onshore Fabrication and Installation of Pipeline Signage For PL358 & PL106 and PL346 & PL232 - Closed Out Report (COR)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 166

HALUAN

CEKAP SDN BHD (641632-A)


LOT 2964 & LOT 2965, BLOCK 6, PERMYJAYA TECHNOLOGY PARK,
KUALA BARAM LAND DISTRICT 98000,
MIRI, SARAWAK.

REF. NO OPM/23/004

TRANSMITTAL NOTE DATE 18‐May‐23

PAGE 1 OF 1

CONTRACT TITLE PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICE FOR PETRONAS CARIGALI SDN BHD

TO PETRONAS CARIGALI SDN BHD

LOCATION OUTSIDE PERIMETER MCOT

ATTENTION TO Asyraf Wadjidee Bin Mohamad Adaham

SUBJECT Onshore Fabrication and Insulation of Pipeline Signage at Outside Perimeter MCOT

ITEM DOCUMENT NO / REF NO PO NO QUANTITY DESCRIPTION

Onshore Fabrication and Insulation of Pipeline


Signage for
Pipeline Signage for PL358 & PL106
1 P610/2023/SKA/004 3400264335 165 PCS (High Pressure Oil Pipeline)
&
Pipeline Signage for PL346 & PL232
(High Pressure Gas Pipeline)

FOR:

APPROVAL / RETURN

INFORMATION FILE

REVIEW / COMMENTS

FURTHER ACTION

AS PER REQUEST

APPROVED

REMARKS

Transmitted by; Delivered by; Acknowledge Received by;

_____________________________ _____________________________ ______________________________


Name : FRANCIS JALONG SELING Name : Name :
Position : CIVIL ENGINEER Position : Position :
Date : 18/5/2023 Date : Date :
PETRONAS CARIGALI SDN BHD
PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES
FOR PETRONAS CARIGALI SDN BHD
For
Onshore Fabrica�on And Installa�on Of Pipeline Signage
For
Pipeline Signage For PL358 & PL106
(High Pressure Oil Pipeline)
&
Pipeline Signage For PL346 & PL232
(High Pressure Gas Pipeline)

CLOSE-OUT REPORT
PO NO.: 3400264335
REPORT NO.: P610/2023/SKA/004
Prepared By. Reviewed By. Reviewed By. Approved By.
Civil Engineer Project Engineer Project Manager Pipeline Engineer Team Lead (PCSB-
Posi�on
(HCSB) (HCSB) (HCSB) (PCSB-SKA) SKA)

Signature

Francis Jalong Wan Mohd


Name Michael Kedit Asyraf Wadjidee Roziana Bt A. Aziz.
Seling Hidayat

Date 18.05.2023 18.05.2023


CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

No. Table of Content  / NA


1. Introduction 
2. Objective 
3. Scope of Work 
3.1. Summary Scope of Work 
4. Organization Chart 
5. HSE Daily Progress Report 
6. Inspection Findings and Recommendation 
7. Project Man-hours / Performance Analysis 
8. Progress S-curve 
9. Material Management – Scrap Metal 
10. Conclusion 
11. Attachments 
11.1. Project Daily Progress Report (DPR) 
11.2. Handover Note 
11.3. Certificate of Completion 

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

1. Introduction
Haluan Cekap Sdn Bhd had carry out an onshore fabrication and installation of pipeline signage
at PL106 & PL358 High Pressure Oil Pipeline and PL232 & PL346 High Pressure Gas Pipeline at
outside perimeter MCOT. Execution of installation of pipeline signage was smoothly performed
on 23rd February 2023 until 17th March 2023 within the duration of 20 days.

2. Objectives
HCSB to carry out installation of Pipeline Signage and pipeline signage repair at PL106, PL358,
PL232, PL346.

3. Scope of Work
Scope of work for this campaign as per stated below:
1. To Install new Pipeline Signage for PL106 High Pressure Oil Pipeline Marker Type A.
2. To Install new Pipeline Signage for PL106 High Pressure Oil Pipeline Marker Type C.
3. To Install new Pipeline Signage for PL358 High Pressure Oil Pipeline Marker Type A.
4. To Install new Pipeline Signage for PL358 High Pressure Oil Pipeline Marker Type C Near
Beach.
5. To Repair Existing Pipeline Signage for PL358 High Pressure Oil Pipeline Marker Type C
near Outside Perimeter Accessway.
6. To Install new Pipeline Signage for PL232 High Pressure Gas Pipeline Marker Type B.
7. To Install new Pipeline Concrete Marker for PL232 High Pressure Gas Pipeline.
8. To repair existing Pipeline Concrete Marker for PL346 High Pressure Oil Pipeline Marker
Type C

Please refer to photo attachments in Chapter 3.1 – Summary Scope of Work in the next page.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

3.1. Summary Scope of Work


Day 1
Date: 23/2/23

Figure 1: Dismantle resting Figure 2: Removing existing Figure 3: Existing pipeline


shed at Bridge No.1 to collect pipeline signage post for signage post for PL358 are
for scaffolding material for PL358. stored at temporary storage
scaffolding erection at PL358. before declare for Scrap
Metal with MCOT.
Day 2
Date: 24/2/23

Figure 4: Transferring Figure 5: Formwork for Figure 6: Manual excavation


scaffolding material from concrete stump and pipeline for PL358 pipeline signage
Bridge No.3 to PL358 concrete marker for PL358 are concrete stump.
worksite. ready to be installed.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 3
Date: 25/2/23

Figure 7: Continue manual Figure 8: Install Figure 9: Erect scaffolding at


excavation for concrete stump reinforcement for concrete PL358 pipeline signage.
PL358 pipeline signage Type A stump.
marker.
Day 4
Date: 27/2/23

Remark: No photo attachment for activity due to no permit for photo taking.

Day 5
Date: 28/3/23

Figure 10: Concreting for PL358 Figure 11: Touch up painting Figure 12: Transfer pipeline
pipeline signage market Type A for PL358 concrete marker. signage frame for PL106
concrete stump. pipeline signage marker
Type A to work area.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 6
Date: 1/3/23

Figure 13: PL346 concrete Figure 14: Touch up paint 1st Figure 15: Erect scaffolding
marker touch paint and coat for PL106 pipeline for installation of signage
plastering completed. marker Type C. type A at PL106.
Day 7
Date: 2/3/23

Figure 16: Punch for PL232 Figure 17: Install rebar for Figure 18: Touch up paint
concrete marker reinforcement. PL232 concrete marker coat for PL106 pipeline
footings. marker Type C.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Date 8
Date: 3/3/23

Figure 19: Touch up painting Figure 20: Install pipeline Figure 21: Touch up paint final
for PL232 concrete marker signage PL106 marker Type coat for PL106 pipeline marker
completed. A. Type A.
Day 9
Date: 4/3/23

Figure 22: Install new Figure 23: Fabricate PL232 Figure 24: Transfer 2 units toolbox
signage for PL358 marker marker Type B signage to Bridge No.3 Outside Perimeter
Type A. pole. MCOT.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 10
Date: 6/3/23

Figure 25: Dismantle Figure 26: Dismantle scaffolding Figure 27: Touch up paint 1st
scaffolding at PL358 marker at PL358 marker Type A. coat for signage pole PL232
Type A. marker Type A.
Day 11
Date: 7/3/23

Figure 28: Dismantle Figure 29: Transfer project Figure 30: Transfer pre-
scaffolding at PL106 marker material from HCSB KB Yard to fabricated signage pole to
Type A completed. Outside Perimeter MCOT. PL232 pipeline signage Type
B.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 12
Date: 8/3/23

Figure 31: Removed Figure 32: Backfill for PL358 marker Figure 33: Cutting existing PL232
formwork for PL358 Type A concrete stump. marker Type B signage pole.
marker Type A
concrete stump
completed.
Day 13
Date: 9/3/23

Figure 34: Erect Figure 35: Install formwork for Figure 36: Erect scaffolding at
scaffolding at new concrete stump PL232 marker Type PL232 marker Type B.
PL232 marker Type B. B.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 14
Date: 10/3/23

Figure 37: Concreting for PL232 Figure 38: Mixing Figure 39: Pour concrete mixed
marker Type B concrete stump. concrete manually for into PL232 marker Type B
PL232 marker Type B concrete stump.
concrete stump.
Day 15
Date: 11/3/23

Figure 42: Transfer scrap material


Figure 40: Remove PL232 concrete Figure 41: Touch up from existing PL232 marker Type
marker formwork. plastering for PL232 B to temporary storage at Bridge
concrete marker No.3 Outside Perimeter MCOT.
footing formwork.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 16
Date: 13/3/23

Figure 43: Remove Figure 44: Installation of pipeline Figure 45: Installation of
formwork for prefabricated signage PL358 marker Type C and pipeline signage PL 358
pipeline signage PL358 backfilled excavated soil. marker type A and C
marker Type C prior completed.
installation.
Day 17
Date: 14/3/23

Figure 46: Touch up paint Figure 47: Touch up plastering Figure 48: Install pipeline
for PL358 marker Type C. PL358 marker Type A. signage board for PL232
Marker type B

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 18
Date: 15/3/23

Figure 49: Remove PL232 Marker Figure 50: Installation of Figure 51: Touch up
Type B concrete Stump pipeline signage for PL232 plastering to repair concrete
formwork Marker Type B completed. honeycomb at PL232 Marker
Type B Concrete Stump
Day 19
Date: 16/3/23

Figure 52: Transfer scrap metal


from Outside Perimeter MCOT to Figure 53: Final inspection Figure 54: Final inspection
Lot 616 Rest Shed. with MCOT Operation after with MCOT Operation after
completion before completion before handover
handover to MCOT to MCOT Operation.
Operation.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

Day 20
Date: 17/3/23

Figure 56: HCSB Toolbox had


Figure 55: HCSB Equipment had been transferred from outside
been transferred from outside perimeter MCOT to HCSB KB
perimeter MCOT to HCSB KB Yard.
Yard.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

4. Organizational Chart
Please refer to next page.

open
18.05.23
CLIENT PETRONAS CARIGALI SDN BHD –SARAWAK ASSETS DATE
0
SUBJECT Closed Out Report for Installation of New Pipeline Signage for PL106 & REV
PL358 and PL232 & PL346 at Outside Perimeter MCOT
HALUAN CEKAP SDN BHD

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

5. HSE Daily Report


Please refer to next page.

open
HSE DAILY PROGRESS REPORT
DATE : 23.02.2023 DAY 1
LOCATION : MIRI CRUDE OIL TERMINAL AT PL358,PL106,PL232 & PL346
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE AT PL358 & PL106(HIGH PRESSURE OIL PIPELINE AND PL232 & PL346(HIGH PRESSURE GAS PIPELINE )

MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 112 1
HSE SUPERVISOR 0 0 23.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 0 0
MECHANIC 1 8 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 MEGA TOOLBOX MEETING WITH MCOT OPERATIONS AND CONTRACTORS 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF LOADING MATERIAL INTO
1 1 AARON CLOSED
THE WORKSITE AREA OF PIPELINE SIGNAGE.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 25.02.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.
TO PERFORM SCAFFOLDING ERECTION AND
2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006483 SUA RANGAL 25.02.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006477 SUA RANGAL 25.02.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006614 SUA RANGAL 25.02.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006437 SEMAN BUNTAL 25.02.2023
PROJECT MATERIALS.

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 0 0 0
CUMULATIVE 5 0 0
TODAY TOTAL 5
PREVIOUS TOTAL 0
GRAND TOTAL 5

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 23.02.2023 23.02.2023 23.02.2023
HSE DAILY PROGRESS REPORT
DATE : 24.02.2023 DAY 2
LOCATION : MIRI CRUDE OIL TERMINAL AT PL106,PL358,PL232 & PL358
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE AT PL358 & PL106(HIGH PRESSURE OIL PIPELINE AND PL232 & PL346(HIGH PRESSURE GAS PIPELINE )

MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 232 2
HSE SUPERVISOR 1 8 24.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 112 1
MECHANIC 1 8 23.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 15
2

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF LOADING MATERIAL INTO THE
1 1 AARON CLOSED
WORKSITE AREA OF PIPELINE SIGNAGE.
SUPERVISE ACTIVITY OF MANUAL EXCAVATION FOR
2 1 AARON CLOSED
NEW STUMP AT PL358 SIGNAGE REPAIR.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 25.02.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.
TO PERFORM SCAFFOLDING ERECTION AND
2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006483 SUA RANGAL 25.02.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006477 SUA RANGAL 25.02.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006614 SUA RANGAL 25.02.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006437 SEMAN BUNTAL 25.02.2023
PROJECT MATERIALS.

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 5 0 0
CUMULATIVE 10 0 0
TODAY TOTAL 5
PREVIOUS TOTAL 5
GRAND TOTAL 10

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 24.02.2023 24.02.2023 24.02.2023
HSE DAILY PROGRESS REPORT
DATE : 25.02.2023 DAY 3
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS WORKING DAYS
PART 1 MANPOWER REPORT PART 2
CUMULATIVE CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 344 3
HSE SUPERVISOR 1 8 25.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 232 2
MECHANIC 1 8 24.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 ZETO RULES SHARING BY TEAM 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF LOADING MATERIAL INTO
1 1 AARON CLOSED
THE WORKSITE AREA OF PIPELINE SIGNAGE.
SUPERVISE ACTIVITY OF ERECTION OF SCAFFOLD AT
2 1 AARON CLOSED
PL358 SIGNAGE REPAIR.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 25.02.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.
TO PERFORM SCAFFOLDING ERECTION AND
2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 CW0006483 SUA RANGAL 25.02.2023
& PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006477 SUA RANGAL 25.02.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006614 SUA RANGAL 25.02.2023
SIGNAGE FOOTING REPAIR.

TO PERFORM MANUAL TRANSFER AND HANDLING OF


5 CW0006437 SEMAN BUNTAL 25.02.2023
PROJECT MATERIALS.

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 10 0 0
CUMULATIVE 15 0 0
TODAY TOTAL 5
PREVIOUS TOTAL 10
GRAND TOTAL 15

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 25.02.2023 25.02.2023 25.02.2023
HSE DAILY PROGRESS REPORT
DATE : 27.02.2023 DAY 4
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS WORKING DAYS
PART 1 MANPOWER REPORT PART 2
CUMULATIVE CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 464 4
HSE SUPERVISOR 1 8 27.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 344 3
MECHANIC 1 8 25.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 120

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 ZETO RULES SHARING 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF LOADING MATERIAL INTO
1 1 AARON CLOSED
THE WORKSITE AREA OF PIPELINE SIGNAGE.
SUPERVISE ACTIVITY OF ERECTION OF SCAFFOLD AT
2 1 AARON CLOSED
PL358 SIGNAGE REPAIR.

SUPERVISE ACTIVITY OF CONCRETING SIGNAGE BASE


3 1 AARON CLOSED
SUPPORT AT PL358 SIGNAGE INSTALLATION.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON ON HOLD. SUBMITTED ON
1 HW0006607 DOMINIC UGAK
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR. 27.02.2023

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 CW0006710 SUA RANGAL 04.03.2023
& PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006711 SUA RANGAL 04.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006709 SUA RANGAL 04.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006712 SEMAN BUNTAL 04.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006721 DOMINIC UGAK 04.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006714 SEMAN BUNTAL 04.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 15 0 0
CUMULATIVE 20 0 0
TODAY TOTAL 5
PREVIOUS TOTAL 15
GRAND TOTAL 20

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 27.02.2023 27.02.2023 27.02.2023
HSE DAILY PROGRESS REPORT
DATE : 28.02.2023 DAY 5
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 576 5
HSE SUPERVISOR 1 8 28.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 456 4
MECHANIC 1 8 27.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 15
2 ZETO RULES SHARING 1 15

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF LOADING MATERIAL INTO THE
1 1 AARON CLOSED
WORKSITE AREA OF PIPELINE SIGNAGE.
SUPERVISE ACTIVITY OF CONCRETING SIGNAGE BASE
2 1 AARON CLOSED
SUPPORT AT PL358 SIGNAGE INSTALLATION.

SUPERVISE ACTIVITY OF MANUAL TRANSFER SIGNAGE


3 1 AARON CLOSED
MATERIAL FROM BRIDGE 3 TO BEACH AREA OF PL106.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 04.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006710 SUA RANGAL 04.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006711 SUA RANGAL 04.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006709 SUA RANGAL 04.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006712 SEMAN BUNTAL 04.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006721 DOMINIC UGAK 04.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006714 SEMAN BUNTAL 04.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 20 0 0
CUMULATIVE 25 0 0
TODAY TOTAL 5
PREVIOUS TOTAL 20
GRAND TOTAL 25

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 28.02.2023 28.02.2023 28.02.2023
HSE DAILY PROGRESS REPORT
DATE : 01.03.2023 DAY 6
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 688 6
HSE SUPERVISOR 1 8 01.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 576 5
MECHANIC 1 8 28.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 ZETO RULES SHARING 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF LOADING MATERIAL TO
1 1 AARON CLOSED
BRIDGE 3 PL106.
SUPERVISE ACTIVITY OF SCAFFOLD INSTALLATION FOR
2 1 AARON CLOSED
SIGNAGE INSTALLATION AT PL106 BEACH AREA.

SUPERVISE ACTIVITY OF MANUAL TRANSFER SIGNAGE


3 1 AARON CLOSED
MATERIAL FROM BRIDGE 3 TO BEACH AREA OF PL106.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 04.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006710 SUA RANGAL 04.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006711 SUA RANGAL 04.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006709 SUA RANGAL 04.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006712 SEMAN BUNTAL 04.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006721 DOMINIC UGAK 04.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006714 SEMAN BUNTAL 04.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
4 0 1
PREVIOUS 25 0 0
CUMULATIVE 29 0 1
TODAY TOTAL 5
PREVIOUS TOTAL 25
GRAND TOTAL 30

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 01.03.2023 01.03.2023 01.03.2023
HSE DAILY PROGRESS REPORT
DATE : 02.03.2023 DAY 7
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 808 7
HSE SUPERVISOR 1 8 02.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 688 6
MECHANIC 1 8 01.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 15
2 ZETO RULES SHARING 1 15

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF CONCRETING SIGNAGE PL232
1 1 AARON CLOSED
AT BEACH AREA.
SUPERVISE ACTIVITY OF SCAFFOLD INSTALLATION FOR
2 1 AARON CLOSED
SIGNAGE INSTALLATION AT PL106 BEACH AREA.

SUPERVISE ACTIVITY OF MANUAL TRANSFER SIGNAGE


3 1 AARON CLOSED
MATERIAL FROM BRIDGE 3 TO BEACH AREA OF PL106.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 04.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006710 SUA RANGAL 04.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006711 SUA RANGAL 04.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006709 SUA RANGAL 04.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006712 SEMAN BUNTAL 04.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006721 DOMINIC UGAK 04.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006714 SEMAN BUNTAL 04.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 29 0 0
CUMULATIVE 34 0 1
TODAY TOTAL 5
PREVIOUS TOTAL 30
GRAND TOTAL 35

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 02.03.2023 02.03.2023 02.03.2023
HSE DAILY PROGRESS REPORT
DATE : 03.03.2023 DAY 8
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 928 8
HSE SUPERVISOR 1 8 03.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 808 7
MECHANIC 1 8 02.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 15
2 ZETO RULES SHARING 1 15

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF SIGNAGE INSTALLATION FOR
1 1 AARON CLOSED
PL106 AT BEACH AREA.
SUPERVISE ACTIVITY OF TOUCH UP PAINTING
2 1 AARON CLOSED
SIGNAGE SUPPORT FOR PL106 BEACH AREA.

SUPERVISE ACTIVITY OF MANUAL TRANSFER SIGNAGE


3 MATERIAL FROM BRIDGE 3 TO BEACH AREA OF PL106 1 AARON CLOSED
AND PL232.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 04.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006710 SUA RANGAL 04.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006711 SUA RANGAL 04.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006709 SUA RANGAL 04.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006712 SEMAN BUNTAL 04.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006721 DOMINIC UGAK 04.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006714 SEMAN BUNTAL 04.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 34 0 0
CUMULATIVE 39 0 1
TODAY TOTAL 5
PREVIOUS TOTAL 35
GRAND TOTAL 40

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 03.03.2023 03.03.2023 03.03.2023
HSE DAILY PROGRESS REPORT
DATE : 04.03.2023 DAY 9
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1040 9
HSE SUPERVISOR 1 8 04.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 928 8
MECHANIC 1 8 03.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 ZETO RULES SHARING 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF SIGNAGE INSTALLATION FOR
1 1 AARON CLOSED
PL106 AT BEACH AREA.
SUPERVISE ACTIVITY OF SIGNAGE INSTALLATION FOR
2 1 AARON CLOSED
PL358 AT BEACH AREA.

SUPERVISE ACTIVITY OF TRANSFER 2 UNIT CONTAINER


3 1 AARON CLOSED
FROM PL358 TO BRIDGE 3 PL106 AREA.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006607 DOMINIC UGAK 04.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006710 SUA RANGAL 04.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006711 SUA RANGAL 04.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006709 SUA RANGAL 04.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006712 SEMAN BUNTAL 04.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006721 DOMINIC UGAK 04.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006714 SEMAN BUNTAL 04.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 39 0 0
CUMULATIVE 44 0 1
TODAY TOTAL 5
PREVIOUS TOTAL 40
GRAND TOTAL 45

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 04.03.2023 04.03.2023 04.03.2023
HSE DAILY PROGRESS REPORT
DATE : 06.03.2023 DAY 10
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1152 10
HSE SUPERVISOR 1 8 06.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1040 9
MECHANIC 1 8 04.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 ZETO RULES SHARING 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF SIGNAGE INSTALLATION FOR
1 1 AARON CLOSED
PL358 AT BEACH AREA.
SUPERVISE ACTIVITY OF TOUCH UP PANTING PL358
2 1 AARON CLOSED
SIGNAGE AT BEACH AREA.

3 DISMANTLING OF SCAFFOLDING AT PL358 SIGNAGE. 1 AARON CLOSED

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006818 DOMINIC UGAK 11.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006807 SUA RANGAL 11.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006806 SUA RANGAL 11.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006805 SUA RANGAL 11.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006826 STENCEER MATIN 11.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006820 DOMINIC UGAK 11.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006827 STENCEER MATIN 11.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
4 1 0
PREVIOUS 44 0 0
CUMULATIVE 48 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 45
GRAND TOTAL 50

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 06.03.2023 06.03.2023 06.03.2023
HSE DAILY PROGRESS REPORT
DATE : 07.03.2023 DAY 11
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1264 11
HSE SUPERVISOR 1 8 07.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1152 10
MECHANIC 1 8 06.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 HSE CAMPAIGN HAND AND FINGER INJURY PREVENTION 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF MANUAL TRANSFER
1 1 AARON CLOSED
MATERIAL AT PL232 BEACH AREA.
SUPERVISE ACTIVITY OF DISMANTLING SCAFFOLD AT
2 1 AARON CLOSED
SIGNAGE PL106 AT BEACH AREA.

3 DISMANTLING OF SCAFFOLDING AT PL106 SIGNAGE. 1 AARON CLOSED

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006818 DOMINIC UGAK 11.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006807 SUA RANGAL 11.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006806 SUA RANGAL 11.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006805 SUA RANGAL 11.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006826 STENCEER MATIN 11.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006820 DOMINIC UGAK 11.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006827 STENCEER MATIN 11.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 48 1 0
CUMULATIVE 53 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 50
GRAND TOTAL 55

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 07.03.2023 07.03.2023 07.03.2023
HSE DAILY PROGRESS REPORT
DATE : 08.03.2023 DAY 12
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1360 12
HSE SUPERVISOR 1 8 08.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1264 11
MECHANIC 1 8 07.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 13
2 HSE CAMPAIGN HAND AND FINGER INJURY PREVENTION 1 13

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF MANUAL TRANSFER
1 1 AARON CLOSED
MATERIAL AT PL232 BEACH AREA.
SUPERVISE ACTIVITY OF TRANSFER MATERIAL FROM
2 1 AARON CLOSED
PL106 TO PL232 AT BEACH AREA.

SUPERVISE FORMWORK INSTALLATION AT PL232


3 1 AARON CLOSED
SIGNAGE.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)


NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS
TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006818 DOMINIC UGAK 11.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.

TO PERFORM SCAFFOLDING ERECTION AND


2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006807 SUA RANGAL 11.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006806 SUA RANGAL 11.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006805 SUA RANGAL 11.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
5 CW0006826 STENCEER MATIN 11.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006820 DOMINIC UGAK 11.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006827 STENCEER MATIN 11.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 53 0 0
CUMULATIVE 58 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 55
GRAND TOTAL 60

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 08.03.2023 08.03.2023 08.03.2023
HSE DAILY PROGRESS REPORT
DATE : 09.03.2023 DAY 13
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1480 13
HSE SUPERVISOR 1 8 09.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1368 12
MECHANIC 1 8 08.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 13
2 ZETO RULES SHARING BY CREW 1 13

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF MANUAL TRANSFER
1 1 AARON CLOSED
MATERIAL AT PL232 BEACH AREA.
SUPERVISE ACTIVITY OF TRANSFER MATERIAL FROM
2 1 AARON CLOSED
PL106 TO PL232 AT BEACH AREA.

SUPERVISE FORMWORK INSTALLATION AT PL232


3 1 AARON CLOSED
SIGNAGE.

SUPERVISE SCAFFOLDING INSTALLATION FOR SIGNAGE


4 1 AARON CLOSED
AT PL232 BEACH AREA.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS


TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006818 DOMINIC UGAK 11.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.
TO PERFORM SCAFFOLDING ERECTION AND
2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006807 SUA RANGAL 11.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006806 SUA RANGAL 11.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006805 SUA RANGAL 11.03.2023
SIGNAGE FOOTING REPAIR.

TO PERFORM MANUAL TRANSFER AND HANDLING OF


5 CW0006826 STENCEER MATIN 11.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006820 DOMINIC UGAK 11.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006827 STENCEER MATIN 11.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 58 0 0
CUMULATIVE 63 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 60
GRAND TOTAL 65

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 09.03.2023 09.03.2023 09.03.2023
HSE DAILY PROGRESS REPORT
DATE : 10.03.2023 DAY 14
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 1568 14
HSE SUPERVISOR 1 8 10.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 2 16
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1480 13
MECHANIC 1 8 09.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 11 88

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 11
2 ZETO RULES SHARING BY CREW 1 11

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF MANUAL TRANSFER
1 1 AARON CLOSED
MATERIAL AT PL232 BEACH AREA.
SUPERVISE ACTIVITY OF CONCRETING SIGNAGE FOR
2 1 AARON CLOSED
PL232 AT BEACH AREA.

SUPERVISE FORMWORK INSTALLATION AT PL232


3 1 AARON CLOSED
SIGNAGE.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS


TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006818 DOMINIC UGAK 11.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.
TO PERFORM SCAFFOLDING ERECTION AND
2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006807 SUA RANGAL 11.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006806 SUA RANGAL 11.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006805 SUA RANGAL 11.03.2023
SIGNAGE FOOTING REPAIR.

TO PERFORM MANUAL TRANSFER AND HANDLING OF


5 CW0006826 STENCEER MATIN 11.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006820 DOMINIC UGAK 11.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006827 STENCEER MATIN 11.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 58 0 0
CUMULATIVE 63 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 60
GRAND TOTAL 65

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 10.03.2023 10.03.2023 10.03.2023
HSE DAILY PROGRESS REPORT
DATE : 11.03.2023 DAY 15
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 1648 15
HSE SUPERVISOR 1 8 11.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 2 16
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1560 14
MECHANIC 1 8 10.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 11 88

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 11
2 ZETO RULES SHARING BY CREW 1 11

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF MANUAL TRANSFER
1 1 AARON CLOSED
MATERIAL AT PL232 BEACH AREA.
SUPERVISE ACTIVITY OF TOUCH UP CONCRETING
2 1 AARON CLOSED
SIGNAGE FOR PL232 AT BEACH AREA.

SUPERVISE FORMWORK REMOVAL AT PL232 PIPELINE


3 1 AARON CLOSED
CONCRETE MARKER.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS


TO CARRY OUT PHOTO TAKING WITHOUT FLASH ON
1 HW0006818 DOMINIC UGAK 11.03.2023
PL106, PL232, PL358 & PL346 FOR SIGNAGE REPAIR.
TO PERFORM SCAFFOLDING ERECTION AND
2 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006807 SUA RANGAL 11.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
3 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006806 SUA RANGAL 11.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
4 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006805 SUA RANGAL 11.03.2023
SIGNAGE FOOTING REPAIR.

TO PERFORM MANUAL TRANSFER AND HANDLING OF


5 CW0006826 STENCEER MATIN 11.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


6 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT CW0006820 DOMINIC UGAK 11.03.2023
PERIMETER

7 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006827 STENCEER MATIN 11.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 68 0 0
CUMULATIVE 73 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 70
GRAND TOTAL 75

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 11.03.2023 11.03.2023 11.03.2023
HSE DAILY PROGRESS REPORT
DATE : 13.03.2023 DAY 16
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1752 16
HSE SUPERVISOR 1 8 13.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1648 15
MECHANIC 1 8 11.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 112

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 13
2 ZETO RULES SHARING BY CREW 1 13

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF TOUCH UP PAINTING AT
1 1 AARON CLOSED
PL232 SIGNAGE BEACH AREA.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS

TO PERFORM SCAFFOLDING ERECTION AND


1 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 CW0006940 SUA RANGAL 18.03.2023
& PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
2 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006939 SUA RANGAL 18.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
3 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006938 SUA RANGAL 18.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
4 CW0006937 SUA RANGAL 18.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


5 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT HW0006959 DOMINIC UGAK 18.03.2023
PERIMETER & PHOTOTAKING

6 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006936 SUA RANGAL 18.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 73 0 0
CUMULATIVE 78 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 75
GRAND TOTAL 80

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 13.03.2023 13.03.2023 13.03.2023
HSE DAILY PROGRESS REPORT
DATE : 14.03.2023 DAY 17
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1856 17
HSE SUPERVISOR 1 8 14.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1752 16
MECHANIC 1 8 13.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 14
2 ZETO RULES SHARING BY CREW 1 14

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF INSTALLATION SIGNBOARD
1 1 AARON CLOSED
TYPE B AT PL232 SIGNAGE BEACH AREA.

2 TOUCH UP PAINT AT PL232 CONCRETE MARKER. 1 AARON CLOSED

3 TOUCH UP PAINT AT PIPELINE SIGNAGE FOR PL358. 1 AARON CLOSED

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS

TO PERFORM SCAFFOLDING ERECTION AND


1 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006940 SUA RANGAL 18.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
2 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006939 SUA RANGAL 18.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
3 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006938 SUA RANGAL 18.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
4 CW0006937 SUA RANGAL 18.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


5 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT HW0006959 DOMINIC UGAK 18.03.2023
PERIMETER & PHOTOTAKING

6 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006936 SUA RANGAL 18.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 78 0 0
CUMULATIVE 83 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 80
GRAND TOTAL 85

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 14.03.2023 14.03.2023 14.03.2023
HSE DAILY PROGRESS REPORT
DATE : 15.03.2023 DAY 18
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1960 18
HSE SUPERVISOR 1 8 15.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1856 17
MECHANIC 1 8 14.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 13
2 ZETO RULES SHARING BY CREW 1 13

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF DISMANTLING OF SCAFFOLD
1 1 AARON CLOSED
AT PL232 SIGNAGE

TRANSFER OF SCAFFOLD MATERIAL FROM PL232


2 1 AARON CLOSED
BEACH AREA TO BRIDGE 3 PL106.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS

TO PERFORM SCAFFOLDING ERECTION AND


1 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006940 SUA RANGAL 18.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
2 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006939 SUA RANGAL 18.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
3 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006938 SUA RANGAL 18.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
4 CW0006937 SUA RANGAL 18.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


5 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT HW0006959 DOMINIC UGAK 18.03.2023
PERIMETER & PHOTOTAKING

6 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006936 SUA RANGAL 18.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 83 0 0
CUMULATIVE 88 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 85
GRAND TOTAL 90

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 15.03.2023 15.03.2023 15.03.2023
HSE DAILY PROGRESS REPORT
DATE : 16.03.2023 DAY 19
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 2064 19
HSE SUPERVISOR 1 8 16.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1960 18
MECHANIC 1 8 15.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 13
2 ZETO RULES SHARING BY CREW 1 13

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF TRANSFER OF MATERIALS
1 1 AARON CLOSED
FROM PL232 SIGNAGE TO PL106 CONTAINER.

DISMANTLE FORMWORK & PLASTERING OF NEW


2 1 AARON CLOSED
STUMP AT PL232 BEACH AREA.

TRANSFER OF SCRAP METAL FROM BRIDGE 3 TO LOT


3 1 AARON CLOSED
616.

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS

TO PERFORM SCAFFOLDING ERECTION AND


JOB COMPLETED - PERMIT
1 DISMANTLE SCAFFOLDING FOR PL106, PL232, PL358 & CW0006940 SUA RANGAL
HANDBACK ON 16.03.2023
PL346 FOR SIGNAGE SUPPORT REPAIR.
TO PERFORM CONCRETING AND PLASTERING WORK
JOB COMPLETED - PERMIT
2 AT PIPELINE SIGNAGE FOOTONG REPAIR FOR PL358, CW0006939 SUA RANGAL
HANDBACK ON 16.03.2023
PL232 & PL106.
TO CARRY OUT FORMWORK INSTALLATION &
JOB COMPLETED - PERMIT
3 DISMANTLING FOR PL106, PL232, & PL358 AT CW0006938 SUA RANGAL
HANDBACK ON 16.03.2023
SIGNAGE FOOTING REPAIR.
TO PERFORM MANUAL TRANSFER AND HANDLING OF
4 CW0006937 SUA RANGAL 18.03.2023
PROJECT MATERIALS.

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


5 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT HW0006959 DOMINIC UGAK 18.03.2023
PERIMETER & PHOTOTAKING

JOB COMPLETED - PERMIT


6 TO CARRY OUT TOUCH UP PAINTING ON SIGNAGE. CW0006936 SUA RANGAL
HANDBACK ON 16.03.2023

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 88 0 0
CUMULATIVE 93 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 90
GRAND TOTAL 95

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 16.03.2023 16.03.2023 16.03.2023
HSE DAILY PROGRESS REPORT
DATE : 17.03.2023 DAY 20
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 2168 20
HSE SUPERVISOR 1 8 17.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 2064 19
MECHANIC 1 8 16.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104

PART 3 OH&S PROGRAMS


NO DESCRIPTION FREQUENCIES ATTENDANCE
1 DAILY TOOLBOX MEETING AT LOT 616 1 13
2 ZETO RULES SHARING BY CREW 1 13

PART 4 HSE INSPECTION


NO TYPE OF INSPECTION FREQUENCIES CONDUCTED BY VALIDITY / STATUS
SUPERVISE ACTIVITY OF TRANSFER OF MATERIALS
1 1 AARON CLOSED
FROM PL232 SIGNAGE TO PL106 CONTAINER.
SUPERVISE LIFTING ACTIVITY OF CONTAINER FROM
2 BRIDGE 3 LOAD ONTO LORRY TO DEMOB CONTAINER 1 AARON CLOSED
BACK TO KB YARD

PART 5 TOTAL PERMIT TO WORK APPLY (IF APPLICABLE)

NO DESCRIPTION OF TASK TYPE & NO OF PTW RA / WL VALIDITY / STATUS

TO PERFORM MANUAL TRANSFER AND HANDLING OF JOB COMPLETED - PERMIT


1 CW0006937 SUA RANGAL
PROJECT MATERIALS. HANDBACK ON 17.03.2023

TO CARRY OUT SITE CLEARING ACTIVITY (GRASS


JOB COMPLETED - PERMIT
2 CUTTING AND BRANCH TRIMMING) OUTSIDE MCOT HW0006959 DOMINIC UGAK
HANDBACK ON 17.03.2023
PERIMETER & PHOTOTAKING

PART 6 UNSAFE ACT UNSAFE CONDITION FINDINGS


GOOD PRACTICE UNSAFE ACT UNSAFE CONDITION
TODAY
5 0 0
PREVIOUS 93 0 0
CUMULATIVE 98 1 1
TODAY TOTAL 5
PREVIOUS TOTAL 95
GRAND TOTAL 100

PART 7 HSE ACCIDENT / INCIDENT STATISTICS


NO TYPE OF INJURY NO. OF CASE NO. OF INJURY STATUS
1 NIL 0 0 NIL
2 NIL 0 0 NIL

PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:

SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF

DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS

DATE 17.03.2023 17.03.2023 17.03.2023


CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

6. Inspection, Findings and Recommendation


During the execution, HCSB found out PL358 Marker Type C badly corroded and damaged. The
scope to install new pipeline signage for the findings had been included in this campaign.

7. Project Man-hours / Performance Analysis

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

8. Progress S-curve

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

9. Material Management – Scrap Metal


Please refer to next page.

open
 

INTRODUCTION
HCSB will perform proper disposal of scrap metal from the project. Purpose of this report
is to showing that the scrap from the campaign of installation of new pipeline signage that
had been removed from the existing pipeline signage was properly disposed by the HCSB.
of PL106 & PL358 High Pressure Oil Pipeline and PL232 & PL346 High Pressure Gas
Pipeline.

The scrap metal will be temporarily placed at HCSB LOT 616 Rest Shed. HCSB will
barricade properly the scrap metal at HCSB LOT 616 Rest Shed, to ensure the scrap metal
is safely disposed and to prevent lost of PCSB asset.

Execution of this campaign was from 23rd February 2023 until 17th March 2023.
 
Attachment

Photo Description

Signage board from MARKER TYPE A


PL358 & PL106 & MARKER TYPE B
PL232 had been removed from existing
signage.

Signage board from MARKER TYPE A


PL358 & PL106 & MARKER TYPE B
PL232 had been removed from existing
signage.

Signage Pole from PL232 Pipeline


signage Marker Type B
 

The Scrap Metal was placed at HCSB Lot 616 MCOT.


CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

10. Conclusion
Haluan Cekap Sdn Bhd (HCSB) is pleased to affirm the completion of the Provision of Onshore
Pipeline Maintenance – Installation of New Pipeline Signage at PL106 & PL358 (High Pressure
Oil Pipeline) and PL232 & PL346 (High Pressure Gas Pipeline) at outside perimeter MCOT. Refer
to Chapter 11 – Attachment (11.3 Certificate of Completion). The project was able to complete
with the cooperation and understanding given by all parties involved.

With some good practices of HSE has brought zero LTI and zero incident/accident. In
conclusion, this project has been completed with satisfactory to both PETRONAS Carigali Sdn
Bhd and Haluan Cekap Sdn Bhd.

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

11. Attachments
11.1. Project Daily Progress Report (DPR)
Please refer to next page.

open
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 23.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 4
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 23.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0845hrs-0910hrs Raining
1145hrs-1200hrs Raining

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Sua Rangal Supervisor MCOT 8 2
3 Seman Buntal Rigger MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 2
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2

Note:

TOTAL POB 14 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 1 112
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 1 5 5
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 23.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 4
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 23.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


23.2.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join Mega Toolbox With MCOT Management/Operation

0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0900hrs-1200hrs 1)Permit approved & all manpower enter to MCOT


2) Worksite Preparation and verification at PL358

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1)Dismantle rest shed at bridge no 1 area. (In Progress)


2) Remove Signage & Suppor at PL358(In Progress)

1730hrs - 1800hrs 1.) Housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB 1 ) MCOT FIRE DRILL 1100hrs-1130hrs

ACTIVITIES PLANNED FOR NEXT 24HRS (24.02.2023


1 Dismantle rest shed at bridge no 1 area.
2 Remove Signage & Suppor at PL358
3 Transfer Equipment from HCSB KB Yard to outside Perimeter MCOT

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE

A PRE‐EXECUTION

1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 1.00% 1.00% IN PROGRESS

2 Prepare and setup equipment at working area 2.5% 1.00% 1.00% IN PROGRESS

B EXECUTION

1 Pipeline Signage For PL358

2 Dismantle Existing Pipeline Signage 1.50% 1.00% 1.00% IN PROGRESS

3 Manual Excavation for concrete stump new pipeline signage 1.50%

4 Erect Scaffolding for Installation of New Pipeline Signage 3.00%

5 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00%

6 Installation at site after Fabrication new Pipeline Signage 3.00%

7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%

8 Pipeline Signage Concrete Marker For PL358

9 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

10 Reinstate Existing Pipeline Signage Concrete Marker 3.75%


11 Touch-up Paint For Concrete Marker 3.75%

12 Perform Proper Housekeeping 3.75%

13 Pipeline Signage For PL232

14 Manual Excavation for concrete stump new pipeline signage 3.75%

15 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

16 Installation at site after Fabrication new Pipeline Signage 3.75%

17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

18 Pipeline Signage Concrete Marker For PL346

19 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

20 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

21 Touch-up Paint For Concrete Marker 3.75%

22 Perform Proper Housekeeping 3.75%

23 Pipeline Signage For PL106

24 Manual Excavation for concrete stump new pipeline signage 3.75%

25 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

26 Installation at site after Fabrication new Pipeline Signage 3.75%

27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

28 Pipeline Signage Concrete Marker For PL106

29 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

30 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

31 Touch-up Paint For Concrete Marker 3.75%

32 Perform Proper Housekeeping 3.75%

C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%

2 Demobilize tools, equipment and materials 1.25%

3 Final housekeeping 1.25%

4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%

Overall Percentage % (Days 1) 100.00% 3.00% 3.00%


Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 23.2.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Dismantle Rest shed at bridge No. 1 to collect Scaffolding Material are ready to be use for erection at
Remove Existing Pipeline Signage for PL358
for Scaffolding Material PL358

N/A N/A N/A

Existing Pipeline Signage for PL358 are stored at Existing Pipeline Signage Post for PL358 are stored at
Remove Existing Pipeline signage Post for
temporary storage before declare for Scrap Metal temporary storage before declare for Scrap Metal
PL358
with MCOT. with MCOT.

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (ROSLEE YUSOF)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 24.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 24.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Sua Rangal Supervisor MCOT 8 2
3 Seman Buntal Rigger MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 2
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2

Note:

TOTAL POB 14 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 2 224
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 2 5 10
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 24.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 24.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si F dP
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 24.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 24.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


24.2.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join Mega Toolbox With MCOT Management/Operation

0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0900hrs-1200hrs 1)Permit approved & all manpower enter to MCOT


2).Transfer materials from HCSB kuala baram yard to mcot outsite perimeter.
3). transfer scaffolding materials from bridge no 1 area to PL 358.

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Continue transfer scaffolding materials from bridge no 1 to PL 358 area.( in progress)
2). Remove signage & support at PL 358.( completed)
3). Manual excavation for new stump at PL 358 signage repair.( in progress).

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB N/a

ACTIVITIES PLANNED FOR NEXT 24HRS (25.2.2023)


1 Continue transfer scaffolding materials from bridge no 1 to PL 358 area.
2 Manual excavation for new stump at PL 358 signage repair.
3 Install rebar and formwork for new stump at PL 358 signage repair.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE

A PRE‐EXECUTION

1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% Completed

2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% Completed

B EXECUTION

1 Pipeline Signage For PL358

2 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% Completed

3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.00% 1.00% In Progress

4 Erect Scaffolding for Installation of New Pipeline Signage 3.00%

5 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00%

6 Installation at site after Fabrication new Pipeline Signage 3.00%

7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%

8 Pipeline Signage Concrete Marker For PL358

9 Manual Excavation Existing pipeline signage Concrete Marker 3.75%


10 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

11 Touch-up Paint For Concrete Marker 3.75%

12 Perform Proper Housekeeping 3.75%

13 Pipeline Signage For PL232

14 Manual Excavation for concrete stump new pipeline signage 3.75%

15 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

16 Installation at site after Fabrication new Pipeline Signage 3.75%

17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

18 Pipeline Signage Concrete Marker For PL346

19 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

20 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

21 Touch-up Paint For Concrete Marker 3.75%

22 Perform Proper Housekeeping 3.75%

23 Pipeline Signage For PL106

24 Manual Excavation for concrete stump new pipeline signage 3.75%

25 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

26 Installation at site after Fabrication new Pipeline Signage 3.75%

27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

28 Pipeline Signage Concrete Marker For PL106

29 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

30 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

31 Touch-up Paint For Concrete Marker 3.75%

32 Perform Proper Housekeeping 3.75%

C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%

2 Demobilize tools, equipment and materials 1.25%

3 Final housekeeping 1.25%

4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%

Overall Percentage % (Days 2) 100.00% 7.50% 7.50%


Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 24.2.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Transfer scaffolding Material from Bridge No Transfer Metal Tool Box From HCSB KB YARD to Formwork for Concrete Stump and Pipeline Concrete
1 to PL358 worksite Outside Perimeter MCOT Marker for PL358 are ready to be install.

N/A N/A N/A

Manual Excavation for PL358 Pipeline Manual Excavation for PL358 Pipeline signage Transfer scaffolding Material from Bridge No 1 to
signage concrete stump. concrete stump. PL358 worksite

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 25.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 25.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Sua Rangal Supervisor MCOT 8 2
2 Seman Buntal Rigger MCOT 8 2
3 Steward Maoh Scaffolder Inspector MCOT 8 2
4 Farihan Harris Rigger MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Febian Philemon anak Devis Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 3 328
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 3 5 15
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 25.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 25.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter MCOT
2 Sand 0.5 tonne MCOT 25.02.2023
to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 25.2.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 25.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


25.2.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join Mega Toolbox With MCOT Management/Operation

0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0900hrs-1200hrs 1.) Permit approved 0910hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2).Transfer materials from HCSB kuala baram yard to mcot outside perimeter. (in progress)
3). transfer scaffolding materials from bridge no 1 area to PL 358.(in progress)
4). Continue manual excavation at pipeline signage PL 358. (completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Continue transfer scaffolding materials from bridge no 1 to PL 358 area.( in progress)
2). Install frame for PL 358. (In Progress)
3). Erect scaffolding at PL 358 prior to frame installation.( in progress)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB N/a

ACTIVITIES PLANNED FOR NEXT 24HRS (27.2.2023)


1 Continue transfer scaffolding materials from bridge no 1 to PL 358 area.
2 Transfer materials from HCSB kuala baram yard to mcot outsite perimeter.
3 Continue Installation frame for PL 358.
4 Perform concreting at PL 358 for new stump

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE

A PRE‐EXECUTION

1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023

2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023

B EXECUTION

1 Pipeline Signage For PL358

2 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023

3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023

4 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023

5 Installation at site after Fabrication new Pipeline Signage 3.00% 2.00% 2.00% In Progress

6 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00%

7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%

8 Pipeline Signage Concrete Marker For PL358

9 Manual Excavation Existing pipeline signage Concrete Marker 3.75%


10 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

11 Touch-up Paint For Concrete Marker 3.75%

12 Perform Proper Housekeeping 3.75%

13 Pipeline Signage For PL232

14 Manual Excavation for concrete stump new pipeline signage 3.75%

15 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

16 Installation at site after Fabrication new Pipeline Signage 3.75%

17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

18 Pipeline Signage Concrete Marker For PL346

19 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

20 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

21 Touch-up Paint For Concrete Marker 3.75%

22 Perform Proper Housekeeping 3.75%

23 Pipeline Signage For PL106

24 Manual Excavation for concrete stump new pipeline signage 3.75%

25 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

26 Installation at site after Fabrication new Pipeline Signage 3.75%

27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

28 Pipeline Signage Concrete Marker For PL106

29 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

30 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

31 Touch-up Paint For Concrete Marker 3.75%

32 Perform Proper Housekeeping 3.75%

C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%

2 Demobilize tools, equipment and materials 1.25%

3 Final housekeeping 1.25%

4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%

Overall Percentage % (Days 3) 100.00% 13.00% 13.00%


Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 25.2.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Continue Manual digging for concrete stump Manual digging for concrete stump PL358 pipeline
Install Reinforcement for Concrete Stump
PL358 pipeline signage Type A Marker signage Type A Marker completed

N/A N/A N/A

Erect Scaffolding at PL358 Pipeline Signage Install PL358 Pipeline Signage Frame

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 27.02.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 27.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 1
2 Aaron Sigau Laing HSE Supervisor MCOT 8 1
3 Sua Rangal Supervisor MCOT 8 1
4 Seman Buntal Rigger MCOT 8 1
5 Steward Maoh Scaffolder Inspector MCOT 8 1
6 Farihan Harris Rigger MCOT 8 1
7 Noel Enchi Rigger MCOT 8 1
8 Malang Embap Scaffolder L2 MCOT 8 1
9 Stenceer Matin Scaffolder L2 MCOT 8 1
10 Cho Vui Hua Exp. Concreter MCOT 8 1
11 Mulin Kibong Scaffolder L2 MCOT 8 1
12 Dominic Ugak Rigger MCOT 8 1
13 Leban Dagang Team Leader MCOT 8 1
14 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 1
15 Febian Philemon anak Devis Rigger MCOT 8 1

TOTAL POB 15 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 4 464
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 4 5 20
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 27.02.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 27.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter MCOT
2 Sand 0.5 tonne MCOT 25.02.2023
to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 27.02.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 27.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


27.2.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join Mega Toolbox With MCOT Management/Operation

0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0900hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2).Alignment and install rebar and formwork for PL 358 new stump.(in progress)
3). install new signage frame and signage footing for PL 358.(in progress)
4) erect scaffolding at prior to install new frame and footing at PL 358.(completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1630hrs 1). Perform concreting for new stump at PL 358.(in progress)
2) Re - alignment concrete support at PL 358( completed)

1630hrs - 1700hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB 1. Unable to take photo for activity due to permit On Hold.

ACTIVITIES PLANNED FOR NEXT 24HRS (28.2.2023)


1 Continue transfer scaffolding materials from bridge no 1 to PL 358 area.
2 Transfer materials from HCSB kuala baram yard to mcot outside perimeter.
3 Perform concreting for new stump at PL 358.
4 Touch up paint at correded support for PL 358.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE

A PRE‐EXECUTION

1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023

2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023

B EXECUTION

1 Pipeline Signage For PL358

2 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023

3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023

4 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023

5 Installation at site after Fabrication new Pipeline Signage 3.00% 2.50% 2.50% In Progress

6 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 1.50% 1.50% In Progress

7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%

8 Pipeline Signage Concrete Marker For PL358

9 Manual Excavation Existing pipeline signage Concrete Marker 3.75%


10 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

11 Touch-up Paint For Concrete Marker 3.75%

12 Perform Proper Housekeeping 3.75%

13 Pipeline Signage For PL232

14 Manual Excavation for concrete stump new pipeline signage 3.75%

15 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

16 Installation at site after Fabrication new Pipeline Signage 3.75%

17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

18 Pipeline Signage Concrete Marker For PL346

19 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

20 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

21 Touch-up Paint For Concrete Marker 3.75%

22 Perform Proper Housekeeping 3.75%

23 Pipeline Signage For PL106

24 Manual Excavation for concrete stump new pipeline signage 3.75%

25 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

26 Installation at site after Fabrication new Pipeline Signage 3.75%

27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

28 Pipeline Signage Concrete Marker For PL106

29 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

30 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

31 Touch-up Paint For Concrete Marker 3.75%

32 Perform Proper Housekeeping 3.75%

C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%

2 Demobilize tools, equipment and materials 1.25%

3 Final housekeeping 1.25%

4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%

Overall Percentage % (Days 4) 100.00% 15.00% 15.00%


Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 27.02.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

N/A N/A N/A

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 28.02.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 28.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Seman Buntal Rigger MCOT 8 2
5 Steward Maoh Scaffolder Inspector MCOT 8 2
6 Farihan Harris Rigger MCOT 8 2
7 Noel Enchi Rigger MCOT 8 2
8 Malang Embap Scaffolder L2 MCOT 8 2
9 Stenceer Matin Scaffolder L2 MCOT 8 2
10 Cho Vui Hua Exp. Concreter MCOT 8 2
11 Mulin Kibong Scaffolder L2 MCOT 8 2
12 Dominic Ugak Rigger MCOT 8 2
13 Leban Dagang Team Leader MCOT 8 2
14 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
15 Febian Philemon anak Devis Rigger MCOT 8 2

TOTAL POB 15 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 5 576
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 5 5 25
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 28.02.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 28.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter MCOT
2 Sand 0.5 tonne MCOT 25.02.2023
to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 28.02.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 28.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


28.2.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0900hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2)Performed concreting for new stump at PL 358.(completed)
3). Touch up paint on corroded support for PL 358.(completed)
4) Reinstate and Touch-up paint concrete marker PL358
5). Transfer materials from kb yard to outside perimeter area.( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Manual handling and transfer signage frame from bridge no 3 to PL 106 & PL 232.(completed)
2). Remove existing signage at PL 106 & PL232.( completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB 1. New Findings on Pipeline Signage Pole for PL232 Badly corroded.
2.New Findings on Pipeline Signage PL358 Marker Type C besides beach area.
ACTIVITIES PLANNED FOR NEXT 24HRS (1.03.2023)
1 Manual transfer scaffolding materials from bridge no 3 to PL 106 signage repair area.
2 Erect scaffolding at PL 106 for signage repair.
3 Remove existing signage type C at PL 106
4 Touch up paint at signage type C at PL 106.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE

A PRE‐EXECUTION

1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023

2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023

B EXECUTION

1 Pipeline Signage For PL358

2 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023

3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023

4 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023

5 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023

6 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023

7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%

8 Pipeline Signage Concrete Marker For PL358

9 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
10 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023

11 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023

12 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023

13 Pipeline Signage For PL232

14 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

15 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023

16 Installation at site after Fabrication new Pipeline Signage 3.75%

17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

18 Pipeline Signage Concrete Marker For PL346

19 Manual Excavation Existing pipeline signage Concrete Marker 3.75%

20 Reinstate Existing Pipeline Signage Concrete Marker 3.75%

21 Touch-up Paint For Concrete Marker 3.75%

22 Perform Proper Housekeeping 3.75%

23 Pipeline Signage For PL106

24 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

25 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023

26 Installation at site after Fabrication new Pipeline Signage 3.75%

27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

28 Pipeline Signage Concrete Marker For PL106

29 Install formwork for concrete marker footings 3.75%

30 Concreting for Concrete Marker footings 3.75%

31 Remove formwork concrete marker footings 3.75%

32 Perform Proper Housekeeping 3.75%

C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%

2 Demobilize tools, equipment and materials 1.25%

3 Final housekeeping 1.25%

4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%

Overall Percentage % (Days 5) 100.00% 39.50% 39.50%


Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 28.02.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Concreting for PL358 Pipeline Signage Concreting for PL358 Pipeline Signage Marker Type A
Touch Up Paint for PL358 Concrete Marker
Marker Type A Concrete Stump Concrete Stump

N/A N/A N/A

Transfer Pipeline Signage Frame to PL106 Transfer Existing Pipeline Signage for PL106 at
Pipeline signage Marker Type A working designated storage area before declare for scrap Temporary store at PL106 for existing Marker Type A
Area metal with MCOT AP.

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 01.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 01.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 2
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2

TOTAL POB 14 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 6 688
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 6 5 30
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 01.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 01.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp 100 Pcs Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 MCOT 24.02.2023
Metal Deck 30 Pcs Perimeter MCOT to PL358 worksite area.
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358Harness
Body Si F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter MCOT
2 Sand 0.5 tonne MCOT 25.02.2023
to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 01.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 01.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


01.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0900hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2) perform touch up plastering at PL 346 for concrete maker.( completed)
3) remove damage signboard type C at PL 106.( completed)
4). Transfer scaffolding materials from bridge no 3 to PL 106 pipeline signage repair area.( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). manual handling and transfer concrete maker & formwork from bridge no 3 to PL 232 area.(completed)
2). Erect scaffolding at PL 106 for pipeline signage repair.( in progress)
3) touch up paint at concrete maker for PL 346.( completed)
4). apply 1st coat on corroded T-post type C for PL 106. ( completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (02.03.2023)


1 Transfer 2 unit toolbox from PL 358 to bridge no 3.
2 Erect scaffolding at PL 106 for signage repair.
3 Touch up paint at signage type C at PL 106.
4 Install formwork, rebar and concrete maker at PL 232
5 Perform concreting work prior to concrete maker installation at PL 232.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE

A PRE‐EXECUTION

1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023

2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023

3 EXECUTION

4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023

6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023

7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023

8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023

9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023

10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50%

11 Pipeline Signage Concrete Marker For PL358 Type C

12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023

13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

14 Perform Proper Housekeeping 0.50%


15 Pipeline Signage Concrete Marker For PL358

16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023

17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023

18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023

19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023

20 Pipeline Signage For PL232 Marker Type B

21 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023

23 Installation at site after Fabrication new Pipeline Signage 3.75%

24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

25 Pipeline Signage Concrete Marker For PL346

26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A

31 Erect Scaffolding for Installation of New Pipeline Signage 3.75%

32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023

33 Installation at site after Fabrication new Pipeline Signage 3.75%

34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%

35 Pipeline Signage For PL106 Marker Type C

36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023

37 Mechanical cleaning at existing Pipeline signage 2.50%

38 Touch-up Paint For Concrete Marker 2.50%

39 Install new Pipeline signage 2.50%

40 Perform Proper Housekeeping 1.00%

41 Pipeline Signage Concrete Marker For PL106

42 Install formwork for concrete marker footings 3.75%

43 Concreting for Concrete Marker footings 3.75%

44 Remove formwork concrete marker footings 3.75%

45 Perform Proper Housekeeping 3.75%

C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%

2 Demobilize tools, equipment and materials 1.25%

3 Final housekeeping 1.25%

4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%

Overall Percentage % (Days 6) 100.00% 48.00% 48.00%


Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 01.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

PL346 Concrete Marker Touch up Paint and PL346 Concrete Marker Touch up Paint and Touch Up Paint 1st Coat for PL106 Pipeline Marker
Plastering Completed Plastering Completed Type C

N/A N/A N/A

Erect scaffolding for installation of sinage Erect scaffolding for installation of sinage type A at Erect scaffolding for installation of sinage type A at
type A at PL106 PL106 PL106

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 02.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 02.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 2
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2
15 Seman Buntal Rigger MCOT 8 2

TOTAL POB 15 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 7 808
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 7 5 35
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 02.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 02.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 02.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 02.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


02.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Install rebar and formwork for concrete marker at PL 232.( completed)
3) Erect scaffolding at PL 106 for pipeline signage Marker type A. ( in progress)
4). Touch up paint at PL 106 for Marker Type C ( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1) Continue erect scaffolding at PL 106 for pipeline signage type A. (completed)
2) Perform concreting at PL 232 for concrete marker. (completed)
3) Remove existing paint at PL 106 for type A pipeline signage. ( completed)
4) Apply 1st coat touch up paint for PL 106 Marker Type A.

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (03.03.2023)


1 Transfer 2 unit toolbox from PL 358 to bridge no 3.
2 Apply final coat touch up paint at signage type A at PL 106.
3 Install frame at pipeline signage type A for PL 106.
4 Transfer signage board from KB yard to PL 358 for signage Marker type A.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50%
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50%
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75%
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 3.75%
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75%
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75%
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50%
38 Touch-up Paint For Concrete Marker 2.50%
39 Install new Pipeline signage 2.50%
40 Perform Proper Housekeeping 1.00%
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 2.25% 2.25% In Progress
44 Remove formwork concrete marker footings 3.75%
45 Perform Proper Housekeeping 3.75%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 7) 100.00% 54.00% 54.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 02.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Punch For PL232 Concrete Marker Touch Up Paint Final Coat for PL106 Pipeline
Install Rebar For PL232 Concrete Marker Footings
Reinforcement Marker Type C

N/A N/A N/A

Concrete Marker For PL232 Has Been Touch Up Paint Final Coat for PL106 Pipeline Marker Touch Up Paint Final Coat for PL106 Pipeline
Installed Type C Marker Type C

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 03.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 03.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 1
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2
15 Seman Buntal Rigger MCOT 8 2

TOTAL POB 15 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 8 928
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 8 5 40
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 03.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 03.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 03.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 03.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


03.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2). Transfer signage board from kb yard to outside perimeter MCOT PL 106.( completed)
3) Apply final coat touch up paint at signage repair for PL 106 type A. ( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Install frame at PL 106 for pipeline signage type A. ( completed)
2). Perform touch up plastering for PL232 Concrete Marker. ( completed)
3). Install new signage board at PL 106 for type A signage. ( completed)
4) Perform rivet for new signboard at PL 106.( in progress)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (03.03.2023)


1 Transfer 2 unit toolbox from PL 358 to bridge no 3.
2 Continue rivet for new signboard at PL 106.
3 Erect and perform scaffolding modification at PL 358 prior install new signboard.
4 Transfer new signboard from hcsb kb yard to outside perimeter MCOT for PL 358.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50%
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50%
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75%
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 3.75%
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 2.00% 2.00% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint For Concrete Marker 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50%
40 Perform Proper Housekeeping 1.00%
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75%
45 Perform Proper Housekeeping 3.75%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 8) 100.00% 66.25% 66.25%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 03.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Touch up Plastering for PL232 Concrete Touch up Plastering for PL232 Concrete Marker
Install Pipeline Signage PL106 Marker Type A
Marker Completed Completed

N/A N/A N/A

Install Pipeline Signage PL106 Marker Type Touch Up Paint Final Coat for PL106 Pipeline
Install Pipeline Signage PL106 Marker Type A
A Marker Type A

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 04.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 04.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 2
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2

TOTAL POB 14 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 9 1040
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 9 5 45
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 04.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 04.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 04.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 04.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


04.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2). Transfer signage board from kb yard to PL 358 location.( completed)
3)Erect scaffolding at signage repair for PL 358 type A. ( completed)
4) fabricate rebar and signage pole for PL 232 at HCSB KB YARD.
5) fabricate PL358 marker type C structure.

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Install new signboard at PL 358 for pipeline signage type A. ( completed)
2). Rivet at PL 358 Marker type A ( completed).
3) perform rivet for new signage at PL 106 Marker Type A .( completed)
4)Transfer 2 unit toolbox from PL 358 to bridge no 3.( completed).

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (06.03.2023)


1 continue fabrication work at kb yard for PL232 Signage Pole and PL358 Marker Type C( additional scope)
2 Dismantle formwork at PL 358.
3 touch up paint at PL 358 Marker Type A.
4 Dismantle Scaffolding at PL358 Marker Type A.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50%
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 2.00% 2.00% In Progress
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 3.75%
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 2.00% 2.00% In Progress
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 1.00% 1.00% In Progress
40 Perform Proper Housekeeping 1.00%
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 1.50% 1.50% In Progress
45 Perform Proper Housekeeping 3.75%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 9) 100.00% 75.00% 75.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 04.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Install new Signage For PL358 Marker Type


Install new Signage For PL358 Marker Type A Install new Signage For PL358 Marker Type A
A

N/A N/A N/A

Transfer 2 Unit Tool Box to Bridge No. 3 Outside


Fabricate PL232 Marker Type B Signage Pole PL232 Marker Type B Signage Pole after cutting
Perimeter MCOT.

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 07.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 07.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0900hrs-1200hrs Raining

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Farihan Harris Rigger MCOT 8 2
6 Noel Enchi Rigger MCOT 8 2
7 Malang Embap Scaffolder L2 MCOT 8 2
8 Stenceer Matin Scaffolder L2 MCOT 8 2
9 Cho Vui Hua Exp. Concreter MCOT 8 2
10 Mulin Kibong Scaffolder L2 MCOT 8 2
11 Dominic Ugak Rigger MCOT 8 2
12 Leban Dagang Team Leader MCOT 8 2
13 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
14 Febian Philemon anak Devis Rigger MCOT 8 2

TOTAL POB 14 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 11 1264
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 11 5 55
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 07.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 07.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 07.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 07.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


07.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) All activity suspend due to WOW until afternoon.
3) All crew go to HCSB KB yard to do preparation additional scope for PL 232 & PL 106.( completed)
4) Transfer materials from HCSB KB yard to mcot bridge no 3.( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Loading materials at bridge no 3.( completed )


2). dismantle scaffolding at PL 106 pipeline signage.( completed)
3) manual handling scaffolding materials from PL 106 to PL 232 area.( in progress)
4) Manual transfer scrap metal PL 106 to temporary storage area.( Completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (08.03.2023)


1 Dismantle formwork at PL 358.
2 Backfill at new stump PL 358.
3 Manual transfer scaffolding materials from PL 106 to PL 232 pipeline signage repair area.
4 Install new signboard at PL 106 pipeline signage type C.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 2.50% 2.50% In Progress
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00%
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 2.00% 2.00% In Progress
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.00% 2.00% In Progress
40 Perform Proper Housekeeping 0.50%
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.00% 3.00% In Progress
45 Perform Proper Housekeeping 3.75%
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 1.00%
37 Fabricate New Pipeline Signage 2.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.00%
40 Perform Proper Housekeeping 1.00%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 11) 100.00% 80.00% 80.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 07.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Dismantle Scaffolding at PL106 Marker Type Dismantle Scaffolding at PL106 Marker Type A
Dismantle Scaffolding at PL106 Marker Type A
A Completed

N/A N/A N/A

Transfer Project Material from HCSB Kb Transfer Pre‐fabricated signage pole to PL232 Transfer Project Material from HCSB Kb Yard to
Yard to Outside Perimeter MCOT Pipeline Signage Type B Outside Perimeter MCOT

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 08.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 08.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 12 1360
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 12 5 60
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 08.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 08.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 08.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 08.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


08.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Remove formwork at PL358 Marker Type B concrete stump.( completed)
3) Manual transfer scaffolding materials from PL 106 to PL 232 pipeline signage repair.( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Backfill at PL 358 pipeline signage repair.( completed )


2). Transfer 2 unit formwork from PL358 to PL232 pipeline signage repair location.( completed)
3)Remove existing signage pole for PL232 Marker type B.(Completed)
4) Manual excavation for new stump at PL232 Marker type B.( completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (09.03.2023)


1 Install rebar and formwork for new stump at PL 232 pipeline signage repair type B.
2 Install new pole and frame type B at PL 232.
3 Erect scaffolding at PL 232 for pipeline signage repair.
4 Manual transfer aggregate and sand from bridge no 3 to PL 232 pipeline signage repair area.
5 Install new signboard at PL 106 pipeline signage type C.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.00% 3.00% In Progress
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 0.50% 0.50% In Progress
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 2.00% 2.00% In Progress
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50%
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.00% 3.00% In Progress
45 Perform Proper Housekeeping 3.75%
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 1.00% 0.50% 0.50% In Progress
37 Fabricate New Pipeline Signage 2.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.00%
40 Perform Proper Housekeeping 1.00%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 12) 100.00% 82.00% 82.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 08.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Removed formwork for PL358 Marker Type Cutting existing PL232 Marker Type B Signage
Backfill for PL358 Marker Type A Concrete Stump
A Concrete Stump Completed Pole

N/A N/A N/A

Manual excavation for PL232 Marker Type B


Concrete Stump.

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 09.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 09.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Seman Buntal Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 13 1480
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 13 5 65
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 09.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 09.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 09.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 09.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


09.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Install rebar and formwork for new stump at PL 232 pipeline signage marker type B.(completed)
3) Erect scaffolding at PL 232 for pipeline signage marker type B.( in progress)
4). Manual transfer aggregate and sand from bridge no 3 to PL 232 pipeline signage marker type B.( in progress)
5) Install new signboard at PL 106 pipeline signage type C ( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). Install new pole and frame type B at PL 232.(completed)
2) Erect scaffolding at PL 232 for pipeline signage repair.( completed)
3). Manual transfer aggregate and sand from bridge no 3 to PL 232 pipeline signage repair area.( in progress)
4). Dismantle rest shed at PL 358 and housekeeping ( completed).

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (10.03.2023)


1 manual transfer aggregate and sand from bridge no 3 to PL 232 Marker type B.
2 perform concreting for new stump at PL 232 pipeline signage Marker Type B.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.00% 3.00% In Progress
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 0.50% 0.50% In Progress
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.25% 3.25% In Progress
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50%
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75%
45 Perform Proper Housekeeping 3.75%
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 1.00% 0.50% 0.50% In Progress
37 Fabricate New Pipeline Signage 2.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.00%
40 Perform Proper Housekeeping 1.00%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 13) 100.00% 84.00% 84.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 09.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Erect scaffolding at new PL232 marker type Install formwork for concrete stump PL232
Install new frame for PL232 Marker Type B
B Marker type B

N/A N/A N/A

Erect scaffolding at PL232 Marker type B Erect scaffolding at PL232 Marker type B

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 10.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 10.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Aaron Sigau Laing HSE Supervisor MCOT 8 2
2 Sua Rangal Supervisor MCOT 8 2
3 Steward Maoh Scaffolder Inspector MCOT 8 2
4 Noel Enchi Rigger MCOT 8 2
5 Malang Embap Scaffolder L2 MCOT 8 2
6 Stenceer Matin Scaffolder L2 MCOT 8 2
7 Cho Vui Hua Exp. Concreter MCOT 8 2
8 Mulin Kibong Scaffolder L2 MCOT 8 2
9 Dominic Ugak Rigger MCOT 8 2
10 Leban Dagang Team Leader MCOT 8 2
11 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2

TOTAL POB 11 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 14 1568
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 14 5 70
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 10.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 10.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 10.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 10.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


10.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) perform concreting for new stump at PL233 pipeline signage Marker Type B. (in progress)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). perform concreting for new stump PL233 pipeline signage Marker Type B. (completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (11.03.2023)


1 Dismantle formwork at concrete marker for PL232.
2 Plastering activity at concrete marker for PL232.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 1.50% 1.50% In Progress
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.25% 3.25% In Progress
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.25% 0.25% In Progress
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 3.75%
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 1.00% 0.50% 0.50% In Progress
37 Fabricate New Pipeline Signage 2.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.00%
40 Perform Proper Housekeeping 1.00%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 14) 100.00% 86.00% 86.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 10.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Concreting for PL232 Marker type B Mixing concrete manually for PL232 Marker Type B Pour concrete mixed into PL232 Marker Type B
concrete stump concrete stump. concrete Stump

N/A N/A N/A

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 11.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 11.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Aaron Sigau Laing HSE Supervisor MCOT 8 2
2 Sua Rangal Supervisor MCOT 8 2
3 Steward Maoh Scaffolder Inspector MCOT 8 2
4 Noel Enchi Rigger MCOT 8 2
5 Malang Embap Scaffolder L2 MCOT 8 2
6 Stenceer Matin Scaffolder L2 MCOT 8 2
7 Cho Vui Hua Exp. Concreter MCOT 8 2
8 Mulin Kibong Scaffolder L2 MCOT 8 2
9 Dominic Ugak Rigger MCOT 8 2
10 Leban Dagang Team Leader MCOT 8 2
11 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2

TOTAL POB 11 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 15 1648
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 15 5 75
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 11.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 11.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 11.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 11.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


11.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Dismantle formwork at concrete marker for PL232.( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1). perform plastering at concrete Marker at PL232.( completed)


2) housekeeping scrap metal from PL 232 type B Pipeline signage repair to bridge no 3( completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (13.03.2023)


1 Install signage type C at PL 358.
2 touch up paint at PL 232 frame and pole.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 2.00% 2.00% 11.03.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00%
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.75% 3.75% 11.03.2023
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.50% 0.50% 11.03.2023
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 3.75% 0.25% 0.25% In Progress
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 1.00% 1.00% 1.00% In Progress
37 Fabricate New Pipeline Signage 2.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.00%
40 Perform Proper Housekeeping 1.00%
C Project Post‐Execution

1 Final inspection by PCSB representative 1.25%


2 Demobilize tools, equipment and materials 1.25%
3 Final housekeeping 1.25%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 1.25%
Overall Percentage % (Days 15) 100.00% 88.00% 88.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 11.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Transfer scrap material from existing PL232


Touch up plastering for PL232 Concrete marker
Remove PL232 Concrete Marker formwork marker type B to temporary storage at bridge
footings formwork
no. 3 outside perimeter MCOT

N/A N/A N/A

Transfer scrap material from existing PL232


marker type B to temporary storage at
bridge no. 3 outside perimeter MCOT

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 13.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 13.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Seman Buntal Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 16 1752
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 16 5 80
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 13.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 13.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 13.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 13.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


13.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Dismantle existing footing at PL 358 Marker Type C.(completed)
3) Transfer PL358 Marker type C from outside perimeter accessway to the installation location.(completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1) Install pipeline signage PL358 marker type C .( completed)


2) Install signboard at PL 358( completed)
3) touch up paint at PL 232 for frame and pole marker type B. ( completed)
4) Measure scrap metal dimension.( completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (14.03.2023)


1 Install signboard for PL 232 Marker type B.
2 Touch up paint for PL232 concrete maker.
3 Touch up paint for PL358 pipeline signage.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 2.00% 2.00% 11.03.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00% 1.00% 1.00%

25 Pipeline Signage Concrete Marker For PL346


26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.75% 3.75% 11.03.2023
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.50% 0.50% 11.03.2023
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 4.00% 1.25% 1.25% In Progress
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 2.00% 1.00% 1.00% In Progress
37 Fabricate New Pipeline Signage 3.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.50%
40 Perform Proper Housekeeping 1.25%
C Project Post‐Execution

1 Final inspection by PCSB representative 0.50%


2 Demobilize tools, equipment and materials 0.50%
3 Final housekeeping 0.50%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 0.50%
Overall Percentage % (Days 16) 100.00% 90.00% 90.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 13.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Remove formwork for prefabricated


Manual excavation prior installation of pipeline
pipeline signage PL358 marker type C prior Measure scrap metal dimension
signage PL358 marker type C
installation

N/A N/A N/A

Installation of pipeline signage PL 358 Installation of pipeline signage PL 358 Marker


Installation of pipeline signage PL 358 Marker type C
Marker type C and backfilled excavated soil. type A and C Completed.

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 14.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 14.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Seman Buntal Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 17 1856
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 17 5 85
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 14.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 14.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 14.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 14.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


14.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Install signboard type B at PL 232.( in progress)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1) Install signboard Marker type B at PL 232.( completed)


2)touch up paint at PL232 concrete maker.( completed)
3) touch up paint at pipeline signage for PL 358( completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (15.03.2023)


1 Dismantle scaffolding at PL 232.
2 Manual transfer scaffolding materials from PL232 to bridge no 3.
3 Transfer scrap metal from bridge no 3 to LOT 616 MCOT.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 2.00% 2.00% 11.03.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00% 1.00% 1.00% 13.03.2023
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.75% 3.75% 11.03.2023
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.50% 0.50% 11.03.2023
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 4.00% 2.25% 2.25% In Progress
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 2.00% 2.00% 2.00% 13.03.2023
37 Fabricate New Pipeline Signage 3.00% 1.50% 1.50% In Progress
39 Install new Pipeline signage 1.50%
40 Perform Proper Housekeeping 1.25%
C Project Post‐Execution

1 Final inspection by PCSB representative 0.50%


2 Demobilize tools, equipment and materials 0.50%
3 Final housekeeping 0.50%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 0.50%
Overall Percentage % (Days 17) 100.00% 92.00% 92.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 14.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Touch up paint for PL358 Marker Type C Touch up paint for PL358 Marker Type C Touch up plastering PL358 Marker type A

N/A N/A N/A

Touch up plastering and housekeeping Install pipeline signage board for PL232 Marker type Install pipeline signage board for PL232 Marker
PL358 Marker type A. B type B

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Seman Buntal Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 18 2064
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 19 5 95
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


16.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2)transfer scrap metal from bridge no3 to lot 616( completed)
3) Final inspection from mcot team and HCSB team( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1) Dismantle formwork at new stump at PL 232.


2) plastering at new stump at PL 232.
3) General housekeeping at all work area.

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (16.03.2023)


1 Transfer 2 unit toolboxs ftom bridge no 3 to HCSB KB YARD.
2 General housekeeping at all work area.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 2.00% 2.00% 11.03.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00% 1.00% 1.00% 13.03.2023
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.75% 3.75% 11.03.2023
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.50% 0.50% 11.03.2023
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 4.00% 4.00% 4.00% 16.03.2023
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 2.00% 2.00% 2.00% 13.03.2023
37 Fabricate New Pipeline Signage 3.00% 3.00% 3.00% 15.03.2023
39 Install new Pipeline signage 1.50% 1.50% 1.50% 15.03.2023
40 Perform Proper Housekeeping 1.25% 1.00% 1.00% 15.03.2023
C Project Post‐Execution

1 Final inspection by PCSB representative 0.50% 0.50% 0.50% 16.03.2023


2 Demobilize tools, equipment and materials 0.50% 0.50% 0.50% 16.03.2023
3 Final housekeeping 0.50%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 0.50%
Overall Percentage % (Days 19) 100.00% 98.75% 98.75%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Remove PL232 Marker Type B concrete Remove PL232 Marker Type B concrete Stump Installation of pipeline signage for PL232
Stump formwork formwork Marker Type B completed.

N/A N/A N/A

Touch up plastering to repair concrete


Installation of pipeline signage for PL232 Touch up plastering to repair concrete honeycomb at
honeycomb at PL232 Marker Type B concrete
Marker Type B completed. PL232 Marker Type B concrete Stump
Stump

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Seman Buntal Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 18 1960
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 19 5 95
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


16.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2)transfer scrap metal from bridge no3 to lot 616( completed)
3) Final inspection from mcot team and HCSB team( completed)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1) Dismantle formwork at new stump at PL 232.


2) plastering at new stump at PL 232.
3) General housekeeping at all work area.

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (17.03.2023)


1 Transfer 2 unit toolboxs ftom bridge no 3 to HCSB KB YARD.
2 General housekeeping at all work area.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 2.00% 2.00% 11.03.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00% 1.00% 1.00% 13.03.2023
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.75% 3.75% 11.03.2023
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.50% 0.50% 11.03.2023
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 4.00% 4.00% 4.00% 16.03.2023
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 2.00% 2.00% 2.00% 13.03.2023
37 Fabricate New Pipeline Signage 3.00% 3.00% 3.00% 15.03.2023
39 Install new Pipeline signage 1.50% 1.50% 1.50% 15.03.2023
40 Perform Proper Housekeeping 1.25% 1.00% 1.00% 15.03.2023
C Project Post‐Execution

1 Final inspection by PCSB representative 0.50% 0.50% 0.50% 16.03.2023


2 Demobilize tools, equipment and materials 0.50%
3 Final housekeeping 0.50%
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 0.50%
Overall Percentage % (Days 19) 100.00% 98.25% 98.25%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

Transfer scrap metal from outside Transfer scrap metal from outside perimeter MCOT to Transfer scrap metal from outside perimeter
perimeter MCOT to Lot 616 Rest Shed Lot 616 Rest Shed MCOT to Lot 616 Rest Shed

N/A N/A N/A

Final Inspection with MCOT Operation after


Final Inspection with MCOT Operation after Final Inspection with MCOT Operation after
completion before handover to MCOT
completion before handover to MCOT Operation completion before handover to MCOT Operation
Operation

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 17.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 17.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No PCSB PERSONNEL POSITION LOCATION STATUS Weather Conditon


1 Roslee Yusof PSS MCOT Plant Mob 0800hrs-1800hrs Good

No. HCSB PERSONNEL POSITION LOCATION STATUS WH (HRS) OT (HRS)


1 Syed Mohd Hussaini Civil Engineer MCOT 8 2
2 Aaron Sigau Laing HSE Supervisor MCOT 8 2
3 Sua Rangal Supervisor MCOT 8 2
4 Steward Maoh Scaffolder Inspector MCOT 8 2
5 Noel Enchi Rigger MCOT 8 2
6 Malang Embap Scaffolder L2 MCOT 8 2
7 Stenceer Matin Scaffolder L2 MCOT 8 2
8 Cho Vui Hua Exp. Concreter MCOT 8 2
9 Mulin Kibong Scaffolder L2 MCOT 8 2
10 Dominic Ugak Rigger MCOT 8 2
11 Leban Dagang Team Leader MCOT 8 2
12 Nelson Nuga anak Christopher Jaarop Rigger MCOT 8 2
13 Seman Buntal Rigger MCOT 8 2

TOTAL POB 13 Pax

No. SAFETY / MANHOURS REPORT TODAY ACCUMULATIVE (Hrs.)


1 MANHOURS WORKED FROM 20 2168
2 NUMBER OF LOST WORKDAYS (FOR LTIs) 0
3 NUMBER OF RESTRICTIVE WORK CASES (RWCs) 0
4 NUMBER OF MEDICAL TREATMENT CASES (MTCs) 0
5 NUMBER OF FIRST AID TREATMENT CASES (FTCs) 0
6 NUMBER OF FIRE INCIDENTS (ON JOB SITE) 0
7 NUMBER OF PROPERTY DAMAGED INCIDENTS (ON JOB SITE) 0
8 NUMBER OF EQUIPMENT FAILURE INCIDENTS (ON JOB SITE) 0
9 NUMBER OF NEAR MISSES (ON JOB SITE) 0
10 MEDICAL EVACUATION (MEDIVAC) 0

No CONSUMABLE QTY UAUC SUMMARY


1 Ear Plug 2 Box Submission UAUC Accumulative 
2 Impact Resistance Hand Glove 8 sets 20 5 100
3 Hand Gloves 2 Pair
4 Latex Glove 2 Pair
5 High cut steel Teo Cap Rubber Boots 10 Sets No CONSUMABLE QTY
6 Coverall 15 Pcs 9 Chopper Hammer 1LB 2 Pcs.
7 Safety boots 15 Sets 10 Canves (Blue/Orange) 2 Rolls
8 Faceshield, grinding faceshield 5 Sets 11 Adjust Spanner 2 units
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 17.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 17.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

No. EQUIPMENT QTY LOCATION Moblize Demob Remarks


Scaffolding Tube - 2M 20 Pcs
Scaffolding Tube - 4M 20 Pcs
Scaffolding Tube - 6M 20 Pcs
Scaffolding Clamp Transfer using lorry Crane from HCSB KB YARD & Bridge No 1 Outside
1 100 Pcs MCOT 24.02.2023
Metal Deck Perimeter MCOT to PL358 worksite area.
30 Pcs
Wooden Plank 20 Pcs
Metal Tool Box 2 Unit
PL358 Si
Body Harness F dP 4 Pcs
50KG Portland Cement 5 Bag
Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
2 Sand 0.5 tonne MCOT 25.02.2023
MCOT to PL358 worksite area.
3/4" Aggregate 0.5 tonne
1000L IBC Tank 1 Unit
50KG Portland Cement 5 Bag
Sand 1 Jumbo Bag Transfer using lorry Crane from HCSB KB YARD to Outside Perimeter
3 3/4" Aggregate 1 Jumbo Bag MCOT 07.03.2023
MCOT to PL232 worksite area.
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 17.03.2023
(641632-A) Version: 0

Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 17.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini

TIME / DATE ACTIVITIES


17.03.2023
0700hrs-0730hrs Arrived at LOT 616 MCOT
0730hrs-0830hrs Join TBM with MCOT Operation.

0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval

0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2). Perform general housekeeping at all work area PL 358, PL 232 & PL 106 pipeline signage repair.(in progress)

1200hrs - 1300hrs Lunch Time

1300hrs - 1730hrs 1) General housekeeping at all work area.(completed)


2) Transfer 2 unit toolboxs and 3 unit wheel barrow from bridge no 3 to HCSB kb yard.(completed)

1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT

AOB

ACTIVITIES PLANNED FOR NEXT 24HRS (18.03.2023)


1 Nil.

% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A

5 Dismantle Existing Pipeline Signage 1.50% 1.50% 1.50% 24.02.2023


6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50% 0.50% 0.50% 06.03.2023
11 Pipeline Signage Concrete Marker For PL358 Type C
12 Mechanical cleaning at existing Pipeline signage 1.00% 1.00% 1.00% 01.03.2023
13 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
14 Perform Proper Housekeeping 0.50% 0.50% 0.50% 02.03.2023
15 Pipeline Signage Concrete Marker For PL358
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
18 Touch-up Paint For Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
19 Perform Proper Housekeeping 3.75% 3.75% 3.75% 28.02.2023
20 Pipeline Signage For PL232 Marker Type B
21 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 10.03.2023
22 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
23 Installation at site after Fabrication new Pipeline Signage 2.00% 2.00% 2.00% 11.03.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 1.00% 1.00% 1.00% 13.03.2023
25 Pipeline Signage Concrete Marker For PL346
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

28 Touch-up Paint For Concrete Marker 1.00% 1.00% 1.00% 01.03.2023

29 Perform Proper Housekeeping 1.00% 1.00% 1.00% 01.03.2023

30 Pipeline Signage For PL106 Marker Type A


31 Erect Scaffolding for Installation of New Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
32 Remove Existing Pipeline Signage 3.75% 3.75% 3.75% 28.02.2023
33 Installation at site after Fabrication new Pipeline Signage 3.75% 3.75% 3.75% 03.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75% 3.75% 3.75% 11.03.2023
35 Pipeline Signage For PL106 Marker Type C
36 Remove Existing Pipeline Signage 2.50% 2.50% 2.50% 01.03.2023
37 Mechanical cleaning at existing Pipeline signage 2.50% 2.50% 2.50% 03.03.2023
38 Touch-up Paint 2.50% 2.50% 2.50% 03.03.2023
39 Install new Pipeline signage 2.50% 2.50% 2.50% 08.03.2023
40 Perform Proper Housekeeping 0.50% 0.50% 0.50% 11.03.2023
41 Pipeline Signage Concrete Marker For PL232
42 Install formwork for concrete marker footings 3.75% 3.75% 3.75% 02.03.2023
43 Concreting for Concrete Marker footings 3.75% 3.75% 3.75% 03.03.2023
44 Remove formwork concrete marker footings 3.75% 3.75% 3.75% 10.03.2023
45 Perform Proper Housekeeping 4.00% 4.00% 4.00% 16.03.2023
35 Pipeline Signage For PL358 Marker Type C
36 Remove Existing Pipeline Signage 2.00% 2.00% 2.00% 13.03.2023
37 Fabricate New Pipeline Signage 3.00% 3.00% 3.00% 15.03.2023
39 Install new Pipeline signage 1.50% 1.50% 1.50% 15.03.2023
40 Perform Proper Housekeeping 1.25% 1.25% 1.25% 15.03.2023
C Project Post‐Execution

1 Final inspection by PCSB representative 0.50% 0.50% 0.50% 16.03.2023


2 Demobilize tools, equipment and materials 0.50% 0.50% 0.50% 16.03.2023
3 Final housekeeping 0.50% 0.50% 0.50% 17.03.2023
4 Handover pipeline PL106,PL358,PL232 & PL346 to MCOT 0.50% 0.50% 0.50% 17.03.2023
Overall Percentage % (Days 20) 100.00% 100.00% 100.00%
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 17.03.2023
(641632-A) Version: 0

Photo Attachment  -

N/A N/A N/A

HCSB Equipment had been transferred from HCSB Toolbox had been transferred from outside
outside perimeter MCOT to HCSB KB Yard. perimeter MCOT to HCSB KB Yard.

N/A N/A N/A

Prepared by: Acknowledged by:

____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

11.2. Handover Note

open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT

11.3. Certificate of Completion