Professional Documents
Culture Documents
Onshore Fabrication and Installation of Pipeline Signage For PL358 & PL106 and PL346 & PL232 - Closed Out Report (COR)
Onshore Fabrication and Installation of Pipeline Signage For PL358 & PL106 and PL346 & PL232 - Closed Out Report (COR)
Onshore Fabrication and Installation of Pipeline Signage For PL358 & PL106 and PL346 & PL232 - Closed Out Report (COR)
REF. NO OPM/23/004
PAGE 1 OF 1
CONTRACT TITLE PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICE FOR PETRONAS CARIGALI SDN BHD
SUBJECT Onshore Fabrication and Insulation of Pipeline Signage at Outside Perimeter MCOT
FOR:
APPROVAL / RETURN
INFORMATION FILE
REVIEW / COMMENTS
FURTHER ACTION
AS PER REQUEST
APPROVED
REMARKS
CLOSE-OUT REPORT
PO NO.: 3400264335
REPORT NO.: P610/2023/SKA/004
Prepared By. Reviewed By. Reviewed By. Approved By.
Civil Engineer Project Engineer Project Manager Pipeline Engineer Team Lead (PCSB-
Posi�on
(HCSB) (HCSB) (HCSB) (PCSB-SKA) SKA)
Signature
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
1. Introduction
Haluan Cekap Sdn Bhd had carry out an onshore fabrication and installation of pipeline signage
at PL106 & PL358 High Pressure Oil Pipeline and PL232 & PL346 High Pressure Gas Pipeline at
outside perimeter MCOT. Execution of installation of pipeline signage was smoothly performed
on 23rd February 2023 until 17th March 2023 within the duration of 20 days.
2. Objectives
HCSB to carry out installation of Pipeline Signage and pipeline signage repair at PL106, PL358,
PL232, PL346.
3. Scope of Work
Scope of work for this campaign as per stated below:
1. To Install new Pipeline Signage for PL106 High Pressure Oil Pipeline Marker Type A.
2. To Install new Pipeline Signage for PL106 High Pressure Oil Pipeline Marker Type C.
3. To Install new Pipeline Signage for PL358 High Pressure Oil Pipeline Marker Type A.
4. To Install new Pipeline Signage for PL358 High Pressure Oil Pipeline Marker Type C Near
Beach.
5. To Repair Existing Pipeline Signage for PL358 High Pressure Oil Pipeline Marker Type C
near Outside Perimeter Accessway.
6. To Install new Pipeline Signage for PL232 High Pressure Gas Pipeline Marker Type B.
7. To Install new Pipeline Concrete Marker for PL232 High Pressure Gas Pipeline.
8. To repair existing Pipeline Concrete Marker for PL346 High Pressure Oil Pipeline Marker
Type C
Please refer to photo attachments in Chapter 3.1 – Summary Scope of Work in the next page.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 3
Date: 25/2/23
Remark: No photo attachment for activity due to no permit for photo taking.
Day 5
Date: 28/3/23
Figure 10: Concreting for PL358 Figure 11: Touch up painting Figure 12: Transfer pipeline
pipeline signage market Type A for PL358 concrete marker. signage frame for PL106
concrete stump. pipeline signage marker
Type A to work area.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 6
Date: 1/3/23
Figure 13: PL346 concrete Figure 14: Touch up paint 1st Figure 15: Erect scaffolding
marker touch paint and coat for PL106 pipeline for installation of signage
plastering completed. marker Type C. type A at PL106.
Day 7
Date: 2/3/23
Figure 16: Punch for PL232 Figure 17: Install rebar for Figure 18: Touch up paint
concrete marker reinforcement. PL232 concrete marker coat for PL106 pipeline
footings. marker Type C.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Date 8
Date: 3/3/23
Figure 19: Touch up painting Figure 20: Install pipeline Figure 21: Touch up paint final
for PL232 concrete marker signage PL106 marker Type coat for PL106 pipeline marker
completed. A. Type A.
Day 9
Date: 4/3/23
Figure 22: Install new Figure 23: Fabricate PL232 Figure 24: Transfer 2 units toolbox
signage for PL358 marker marker Type B signage to Bridge No.3 Outside Perimeter
Type A. pole. MCOT.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 10
Date: 6/3/23
Figure 25: Dismantle Figure 26: Dismantle scaffolding Figure 27: Touch up paint 1st
scaffolding at PL358 marker at PL358 marker Type A. coat for signage pole PL232
Type A. marker Type A.
Day 11
Date: 7/3/23
Figure 28: Dismantle Figure 29: Transfer project Figure 30: Transfer pre-
scaffolding at PL106 marker material from HCSB KB Yard to fabricated signage pole to
Type A completed. Outside Perimeter MCOT. PL232 pipeline signage Type
B.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 12
Date: 8/3/23
Figure 31: Removed Figure 32: Backfill for PL358 marker Figure 33: Cutting existing PL232
formwork for PL358 Type A concrete stump. marker Type B signage pole.
marker Type A
concrete stump
completed.
Day 13
Date: 9/3/23
Figure 34: Erect Figure 35: Install formwork for Figure 36: Erect scaffolding at
scaffolding at new concrete stump PL232 marker Type PL232 marker Type B.
PL232 marker Type B. B.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 14
Date: 10/3/23
Figure 37: Concreting for PL232 Figure 38: Mixing Figure 39: Pour concrete mixed
marker Type B concrete stump. concrete manually for into PL232 marker Type B
PL232 marker Type B concrete stump.
concrete stump.
Day 15
Date: 11/3/23
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 16
Date: 13/3/23
Figure 43: Remove Figure 44: Installation of pipeline Figure 45: Installation of
formwork for prefabricated signage PL358 marker Type C and pipeline signage PL 358
pipeline signage PL358 backfilled excavated soil. marker type A and C
marker Type C prior completed.
installation.
Day 17
Date: 14/3/23
Figure 46: Touch up paint Figure 47: Touch up plastering Figure 48: Install pipeline
for PL358 marker Type C. PL358 marker Type A. signage board for PL232
Marker type B
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 18
Date: 15/3/23
Figure 49: Remove PL232 Marker Figure 50: Installation of Figure 51: Touch up
Type B concrete Stump pipeline signage for PL232 plastering to repair concrete
formwork Marker Type B completed. honeycomb at PL232 Marker
Type B Concrete Stump
Day 19
Date: 16/3/23
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
Day 20
Date: 17/3/23
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
4. Organizational Chart
Please refer to next page.
open
18.05.23
CLIENT PETRONAS CARIGALI SDN BHD –SARAWAK ASSETS DATE
0
SUBJECT Closed Out Report for Installation of New Pipeline Signage for PL106 & REV
PL358 and PL232 & PL346 at Outside Perimeter MCOT
HALUAN CEKAP SDN BHD
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
open
HSE DAILY PROGRESS REPORT
DATE : 23.02.2023 DAY 1
LOCATION : MIRI CRUDE OIL TERMINAL AT PL358,PL106,PL232 & PL346
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE AT PL358 & PL106(HIGH PRESSURE OIL PIPELINE AND PL232 & PL346(HIGH PRESSURE GAS PIPELINE )
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 112 1
HSE SUPERVISOR 0 0 23.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 0 0
MECHANIC 1 8 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 23.02.2023 23.02.2023 23.02.2023
HSE DAILY PROGRESS REPORT
DATE : 24.02.2023 DAY 2
LOCATION : MIRI CRUDE OIL TERMINAL AT PL106,PL358,PL232 & PL358
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE AT PL358 & PL106(HIGH PRESSURE OIL PIPELINE AND PL232 & PL346(HIGH PRESSURE GAS PIPELINE )
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 232 2
HSE SUPERVISOR 1 8 24.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 112 1
MECHANIC 1 8 23.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 24.02.2023 24.02.2023 24.02.2023
HSE DAILY PROGRESS REPORT
DATE : 25.02.2023 DAY 3
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS WORKING DAYS
PART 1 MANPOWER REPORT PART 2
CUMULATIVE CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 344 3
HSE SUPERVISOR 1 8 25.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 232 2
MECHANIC 1 8 24.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 25.02.2023 25.02.2023 25.02.2023
HSE DAILY PROGRESS REPORT
DATE : 27.02.2023 DAY 4
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS WORKING DAYS
PART 1 MANPOWER REPORT PART 2
CUMULATIVE CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 464 4
HSE SUPERVISOR 1 8 27.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 344 3
MECHANIC 1 8 25.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 120
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 27.02.2023 27.02.2023 27.02.2023
HSE DAILY PROGRESS REPORT
DATE : 28.02.2023 DAY 5
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 576 5
HSE SUPERVISOR 1 8 28.02.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 456 4
MECHANIC 1 8 27.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 28.02.2023 28.02.2023 28.02.2023
HSE DAILY PROGRESS REPORT
DATE : 01.03.2023 DAY 6
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 688 6
HSE SUPERVISOR 1 8 01.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 576 5
MECHANIC 1 8 28.02.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 01.03.2023 01.03.2023 01.03.2023
HSE DAILY PROGRESS REPORT
DATE : 02.03.2023 DAY 7
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 808 7
HSE SUPERVISOR 1 8 02.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 688 6
MECHANIC 1 8 01.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 02.03.2023 02.03.2023 02.03.2023
HSE DAILY PROGRESS REPORT
DATE : 03.03.2023 DAY 8
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 928 8
HSE SUPERVISOR 1 8 03.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 5 40
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 808 7
MECHANIC 1 8 02.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 15 120
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 03.03.2023 03.03.2023 03.03.2023
HSE DAILY PROGRESS REPORT
DATE : 04.03.2023 DAY 9
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1040 9
HSE SUPERVISOR 1 8 04.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 928 8
MECHANIC 1 8 03.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 04.03.2023 04.03.2023 04.03.2023
HSE DAILY PROGRESS REPORT
DATE : 06.03.2023 DAY 10
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1152 10
HSE SUPERVISOR 1 8 06.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1040 9
MECHANIC 1 8 04.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 06.03.2023 06.03.2023 06.03.2023
HSE DAILY PROGRESS REPORT
DATE : 07.03.2023 DAY 11
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1264 11
HSE SUPERVISOR 1 8 07.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1152 10
MECHANIC 1 8 06.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 14 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 07.03.2023 07.03.2023 07.03.2023
HSE DAILY PROGRESS REPORT
DATE : 08.03.2023 DAY 12
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1360 12
HSE SUPERVISOR 1 8 08.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1264 11
MECHANIC 1 8 07.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 08.03.2023 08.03.2023 08.03.2023
HSE DAILY PROGRESS REPORT
DATE : 09.03.2023 DAY 13
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1480 13
HSE SUPERVISOR 1 8 09.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1368 12
MECHANIC 1 8 08.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 09.03.2023 09.03.2023 09.03.2023
HSE DAILY PROGRESS REPORT
DATE : 10.03.2023 DAY 14
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 1568 14
HSE SUPERVISOR 1 8 10.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 2 16
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1480 13
MECHANIC 1 8 09.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 11 88
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 10.03.2023 10.03.2023 10.03.2023
HSE DAILY PROGRESS REPORT
DATE : 11.03.2023 DAY 15
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 1648 15
HSE SUPERVISOR 1 8 11.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 2 16
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1560 14
MECHANIC 1 8 10.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 11 88
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 11.03.2023 11.03.2023 11.03.2023
HSE DAILY PROGRESS REPORT
DATE : 13.03.2023 DAY 16
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1752 16
HSE SUPERVISOR 1 8 13.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1648 15
MECHANIC 1 8 11.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 112
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 13.03.2023 13.03.2023 13.03.2023
HSE DAILY PROGRESS REPORT
DATE : 14.03.2023 DAY 17
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1856 17
HSE SUPERVISOR 1 8 14.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1752 16
MECHANIC 1 8 13.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 14.03.2023 14.03.2023 14.03.2023
HSE DAILY PROGRESS REPORT
DATE : 15.03.2023 DAY 18
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 1960 18
HSE SUPERVISOR 1 8 15.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1856 17
MECHANIC 1 8 14.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 15.03.2023 15.03.2023 15.03.2023
HSE DAILY PROGRESS REPORT
DATE : 16.03.2023 DAY 19
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 0 0 TODAY: 2064 19
HSE SUPERVISOR 1 8 16.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 4 32
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 1960 18
MECHANIC 1 8 15.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
DESIGNATION HSE SUPERVISOR CIVIL ENGINEER PCSB CSS
DATE 16.03.2023 16.03.2023 16.03.2023
HSE DAILY PROGRESS REPORT
DATE : 17.03.2023 DAY 20
LOCATION : MIRI CRUDE OIL TERMINAL
PROJECT : PROVISION OF ONSHORE PIPELINE MAINTENANCE SERVICES FOR PETRONAS CARIGALI SDN BHD.
(INSTALLATION OF PIPELINE SIGNAGE FOR PL106 & PL358 (HIGH PRESSURE OIL PIPELINE)
AND PL 232 & PL346 (HIGH PRESSURE GAS PIPELINE) AT OUTSIDE PERIMETER MCOT
MANHOURS WORKS
PART 1 MANPOWER REPORT PART 2 WORKING DAYS CUMULATIVE
CUMULATIVE
TOTAL WORKERS TOTAL WORKING
DESCRIPTION
(NORMAL HOURS) HOURS
CIVIL ENGINEER 1 8 TODAY: 2168 20
HSE SUPERVISOR 1 8 17.03.2023 MAN-HOURS
SUPERVISOR 1 8
QAQC 0 0
RIGGER 3 24
CIVIL TEAM LEADER 1 8
SCAFFOLDER LEVEL 2 3 24
SCAFFOLDER LEVEL 3 1 8 YESTERDAY: 2064 19
MECHANIC 1 8 16.03.2023 MAN-HOURS
FIREWATCHER 0 0
CONCRETER 1 8
TOTAL 13 104
PART 8 ACKNOWLEDGEMENT
DESCRIPTION REPORTED BY REVIEWED BY HANDOVER / CC TO:
SIGNATURE
……………………………………………….. ……………………………………………….. ……………………………..
NAME AARON SIGAU LAING SYED MOHD HUSSAINI ROSLEE YUSOF
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
8. Progress S-curve
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
open
INTRODUCTION
HCSB will perform proper disposal of scrap metal from the project. Purpose of this report
is to showing that the scrap from the campaign of installation of new pipeline signage that
had been removed from the existing pipeline signage was properly disposed by the HCSB.
of PL106 & PL358 High Pressure Oil Pipeline and PL232 & PL346 High Pressure Gas
Pipeline.
The scrap metal will be temporarily placed at HCSB LOT 616 Rest Shed. HCSB will
barricade properly the scrap metal at HCSB LOT 616 Rest Shed, to ensure the scrap metal
is safely disposed and to prevent lost of PCSB asset.
Execution of this campaign was from 23rd February 2023 until 17th March 2023.
Attachment
Photo Description
10. Conclusion
Haluan Cekap Sdn Bhd (HCSB) is pleased to affirm the completion of the Provision of Onshore
Pipeline Maintenance – Installation of New Pipeline Signage at PL106 & PL358 (High Pressure
Oil Pipeline) and PL232 & PL346 (High Pressure Gas Pipeline) at outside perimeter MCOT. Refer
to Chapter 11 – Attachment (11.3 Certificate of Completion). The project was able to complete
with the cooperation and understanding given by all parties involved.
With some good practices of HSE has brought zero LTI and zero incident/accident. In
conclusion, this project has been completed with satisfactory to both PETRONAS Carigali Sdn
Bhd and Haluan Cekap Sdn Bhd.
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
11. Attachments
11.1. Project Daily Progress Report (DPR)
Please refer to next page.
open
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 23.2.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 4
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 23.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Note:
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 4
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 23.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
1730hrs - 1800hrs 1.) Housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 1.00% 1.00% IN PROGRESS
2 Prepare and setup equipment at working area 2.5% 1.00% 1.00% IN PROGRESS
B EXECUTION
5 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00%
7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%
17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
C Project Post‐Execution
Photo Attachment -
Dismantle Rest shed at bridge No. 1 to collect Scaffolding Material are ready to be use for erection at
Remove Existing Pipeline Signage for PL358
for Scaffolding Material PL358
Existing Pipeline Signage for PL358 are stored at Existing Pipeline Signage Post for PL358 are stored at
Remove Existing Pipeline signage Post for
temporary storage before declare for Scrap Metal temporary storage before declare for Scrap Metal
PL358
with MCOT. with MCOT.
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (ROSLEE YUSOF)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 24.2.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 24.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Note:
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 24.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 24.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
1300hrs - 1730hrs 1). Continue transfer scaffolding materials from bridge no 1 to PL 358 area.( in progress)
2). Remove signage & support at PL 358.( completed)
3). Manual excavation for new stump at PL 358 signage repair.( in progress).
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB N/a
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% Completed
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% Completed
B EXECUTION
3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.00% 1.00% In Progress
5 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00%
7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%
17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
C Project Post‐Execution
Photo Attachment -
Transfer scaffolding Material from Bridge No Transfer Metal Tool Box From HCSB KB YARD to Formwork for Concrete Stump and Pipeline Concrete
1 to PL358 worksite Outside Perimeter MCOT Marker for PL358 are ready to be install.
Manual Excavation for PL358 Pipeline Manual Excavation for PL358 Pipeline signage Transfer scaffolding Material from Bridge No 1 to
signage concrete stump. concrete stump. PL358 worksite
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 25.2.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 25.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 25.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 25.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0900hrs-1200hrs 1.) Permit approved 0910hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2).Transfer materials from HCSB kuala baram yard to mcot outside perimeter. (in progress)
3). transfer scaffolding materials from bridge no 1 area to PL 358.(in progress)
4). Continue manual excavation at pipeline signage PL 358. (completed)
1300hrs - 1730hrs 1). Continue transfer scaffolding materials from bridge no 1 to PL 358 area.( in progress)
2). Install frame for PL 358. (In Progress)
3). Erect scaffolding at PL 358 prior to frame installation.( in progress)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB N/a
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
B EXECUTION
3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
4 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
5 Installation at site after Fabrication new Pipeline Signage 3.00% 2.00% 2.00% In Progress
6 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00%
7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%
17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
C Project Post‐Execution
Photo Attachment -
Continue Manual digging for concrete stump Manual digging for concrete stump PL358 pipeline
Install Reinforcement for Concrete Stump
PL358 pipeline signage Type A Marker signage Type A Marker completed
Erect Scaffolding at PL358 Pipeline Signage Install PL358 Pipeline Signage Frame
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 27.02.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 27.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 27.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 27.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0900hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2).Alignment and install rebar and formwork for PL 358 new stump.(in progress)
3). install new signage frame and signage footing for PL 358.(in progress)
4) erect scaffolding at prior to install new frame and footing at PL 358.(completed)
1300hrs - 1630hrs 1). Perform concreting for new stump at PL 358.(in progress)
2) Re - alignment concrete support at PL 358( completed)
1630hrs - 1700hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
B EXECUTION
3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
4 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
5 Installation at site after Fabrication new Pipeline Signage 3.00% 2.50% 2.50% In Progress
6 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 1.50% 1.50% In Progress
7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%
17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
C Project Post‐Execution
Photo Attachment -
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 28.02.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 28.2.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 28.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 28.2.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0900hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2)Performed concreting for new stump at PL 358.(completed)
3). Touch up paint on corroded support for PL 358.(completed)
4) Reinstate and Touch-up paint concrete marker PL358
5). Transfer materials from kb yard to outside perimeter area.( completed)
1300hrs - 1730hrs 1). Manual handling and transfer signage frame from bridge no 3 to PL 106 & PL 232.(completed)
2). Remove existing signage at PL 106 & PL232.( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB 1. New Findings on Pipeline Signage Pole for PL232 Badly corroded.
2.New Findings on Pipeline Signage PL358 Marker Type C besides beach area.
ACTIVITIES PLANNED FOR NEXT 24HRS (1.03.2023)
1 Manual transfer scaffolding materials from bridge no 3 to PL 106 signage repair area.
2 Erect scaffolding at PL 106 for signage repair.
3 Remove existing signage type C at PL 106
4 Touch up paint at signage type C at PL 106.
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
B EXECUTION
3 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
4 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
5 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
6 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
7 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.00%
9 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
10 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
27 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
C Project Post‐Execution
Photo Attachment -
Concreting for PL358 Pipeline Signage Concreting for PL358 Pipeline Signage Marker Type A
Touch Up Paint for PL358 Concrete Marker
Marker Type A Concrete Stump Concrete Stump
Transfer Pipeline Signage Frame to PL106 Transfer Existing Pipeline Signage for PL106 at
Pipeline signage Marker Type A working designated storage area before declare for scrap Temporary store at PL106 for existing Marker Type A
Area metal with MCOT AP.
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 01.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 01.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 01.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 01.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0900hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0900hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage repair.
2) perform touch up plastering at PL 346 for concrete maker.( completed)
3) remove damage signboard type C at PL 106.( completed)
4). Transfer scaffolding materials from bridge no 3 to PL 106 pipeline signage repair area.( completed)
1300hrs - 1730hrs 1). manual handling and transfer concrete maker & formwork from bridge no 3 to PL 232 area.(completed)
2). Erect scaffolding at PL 106 for pipeline signage repair.( in progress)
3) touch up paint at concrete maker for PL 346.( completed)
4). apply 1st coat on corroded T-post type C for PL 106. ( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
6 Manual Excavation for concrete stump new pipeline signage 1.50% 1.50% 1.50% 25.02.2023
7 Erect Scaffolding for Installation of New Pipeline Signage 3.00% 3.00% 3.00% 25.02.2023
8 Installation at site after Fabrication new Pipeline Signage 3.00% 3.00% 3.00% 28.02.2023
9 Carry Out Concrete Footings for Pipeline Signage and let Curing for 3 days 3.00% 3.00% 3.00% 28.02.2023
10 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 0.50%
16 Manual Excavation Existing pipeline signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
17 Reinstate Existing Pipeline Signage Concrete Marker 3.75% 3.75% 3.75% 28.02.2023
24 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
26 Manual Excavation Existing pipeline signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
34 Housekeeping and dismantle scaffolding After Installation of New Pipeline Signage 3.75%
C Project Post‐Execution
Photo Attachment -
PL346 Concrete Marker Touch up Paint and PL346 Concrete Marker Touch up Paint and Touch Up Paint 1st Coat for PL106 Pipeline Marker
Plastering Completed Plastering Completed Type C
Erect scaffolding for installation of sinage Erect scaffolding for installation of sinage type A at Erect scaffolding for installation of sinage type A at
type A at PL106 PL106 PL106
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 02.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 02.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 02.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 02.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Install rebar and formwork for concrete marker at PL 232.( completed)
3) Erect scaffolding at PL 106 for pipeline signage Marker type A. ( in progress)
4). Touch up paint at PL 106 for Marker Type C ( completed)
1300hrs - 1730hrs 1) Continue erect scaffolding at PL 106 for pipeline signage type A. (completed)
2) Perform concreting at PL 232 for concrete marker. (completed)
3) Remove existing paint at PL 106 for type A pipeline signage. ( completed)
4) Apply 1st coat touch up paint for PL 106 Marker Type A.
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Punch For PL232 Concrete Marker Touch Up Paint Final Coat for PL106 Pipeline
Install Rebar For PL232 Concrete Marker Footings
Reinforcement Marker Type C
Concrete Marker For PL232 Has Been Touch Up Paint Final Coat for PL106 Pipeline Marker Touch Up Paint Final Coat for PL106 Pipeline
Installed Type C Marker Type C
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 03.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 03.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 03.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 03.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2). Transfer signage board from kb yard to outside perimeter MCOT PL 106.( completed)
3) Apply final coat touch up paint at signage repair for PL 106 type A. ( completed)
1300hrs - 1730hrs 1). Install frame at PL 106 for pipeline signage type A. ( completed)
2). Perform touch up plastering for PL232 Concrete Marker. ( completed)
3). Install new signage board at PL 106 for type A signage. ( completed)
4) Perform rivet for new signboard at PL 106.( in progress)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Touch up Plastering for PL232 Concrete Touch up Plastering for PL232 Concrete Marker
Install Pipeline Signage PL106 Marker Type A
Marker Completed Completed
Install Pipeline Signage PL106 Marker Type Touch Up Paint Final Coat for PL106 Pipeline
Install Pipeline Signage PL106 Marker Type A
A Marker Type A
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 04.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 04.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 04.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 04.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2). Transfer signage board from kb yard to PL 358 location.( completed)
3)Erect scaffolding at signage repair for PL 358 type A. ( completed)
4) fabricate rebar and signage pole for PL 232 at HCSB KB YARD.
5) fabricate PL358 marker type C structure.
1300hrs - 1730hrs 1). Install new signboard at PL 358 for pipeline signage type A. ( completed)
2). Rivet at PL 358 Marker type A ( completed).
3) perform rivet for new signage at PL 106 Marker Type A .( completed)
4)Transfer 2 unit toolbox from PL 358 to bridge no 3.( completed).
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 07.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 07.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 07.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 07.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) All activity suspend due to WOW until afternoon.
3) All crew go to HCSB KB yard to do preparation additional scope for PL 232 & PL 106.( completed)
4) Transfer materials from HCSB KB yard to mcot bridge no 3.( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Dismantle Scaffolding at PL106 Marker Type Dismantle Scaffolding at PL106 Marker Type A
Dismantle Scaffolding at PL106 Marker Type A
A Completed
Transfer Project Material from HCSB Kb Transfer Pre‐fabricated signage pole to PL232 Transfer Project Material from HCSB Kb Yard to
Yard to Outside Perimeter MCOT Pipeline Signage Type B Outside Perimeter MCOT
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 08.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 08.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 08.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 08.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Remove formwork at PL358 Marker Type B concrete stump.( completed)
3) Manual transfer scaffolding materials from PL 106 to PL 232 pipeline signage repair.( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Removed formwork for PL358 Marker Type Cutting existing PL232 Marker Type B Signage
Backfill for PL358 Marker Type A Concrete Stump
A Concrete Stump Completed Pole
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 09.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 09.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 09.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 09.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Install rebar and formwork for new stump at PL 232 pipeline signage marker type B.(completed)
3) Erect scaffolding at PL 232 for pipeline signage marker type B.( in progress)
4). Manual transfer aggregate and sand from bridge no 3 to PL 232 pipeline signage marker type B.( in progress)
5) Install new signboard at PL 106 pipeline signage type C ( completed)
1300hrs - 1730hrs 1). Install new pole and frame type B at PL 232.(completed)
2) Erect scaffolding at PL 232 for pipeline signage repair.( completed)
3). Manual transfer aggregate and sand from bridge no 3 to PL 232 pipeline signage repair area.( in progress)
4). Dismantle rest shed at PL 358 and housekeeping ( completed).
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Erect scaffolding at new PL232 marker type Install formwork for concrete stump PL232
Install new frame for PL232 Marker Type B
B Marker type B
Erect scaffolding at PL232 Marker type B Erect scaffolding at PL232 Marker type B
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 10.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 10.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 10.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 10.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) perform concreting for new stump at PL233 pipeline signage Marker Type B. (in progress)
1300hrs - 1730hrs 1). perform concreting for new stump PL233 pipeline signage Marker Type B. (completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Concreting for PL232 Marker type B Mixing concrete manually for PL232 Marker Type B Pour concrete mixed into PL232 Marker Type B
concrete stump concrete stump. concrete Stump
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 11.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 11.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 11.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 11.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Dismantle formwork at concrete marker for PL232.( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 13.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 13.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 13.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 13.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Dismantle existing footing at PL 358 Marker Type C.(completed)
3) Transfer PL358 Marker type C from outside perimeter accessway to the installation location.(completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 14.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 14.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 14.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 14.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2) Install signboard type B at PL 232.( in progress)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Touch up paint for PL358 Marker Type C Touch up paint for PL358 Marker Type C Touch up plastering PL358 Marker type A
Touch up plastering and housekeeping Install pipeline signage board for PL232 Marker type Install pipeline signage board for PL232 Marker
PL358 Marker type A. B type B
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2)transfer scrap metal from bridge no3 to lot 616( completed)
3) Final inspection from mcot team and HCSB team( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Remove PL232 Marker Type B concrete Remove PL232 Marker Type B concrete Stump Installation of pipeline signage for PL232
Stump formwork formwork Marker Type B completed.
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 16.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 16.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2)transfer scrap metal from bridge no3 to lot 616( completed)
3) Final inspection from mcot team and HCSB team( completed)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
Transfer scrap metal from outside Transfer scrap metal from outside perimeter MCOT to Transfer scrap metal from outside perimeter
perimeter MCOT to Lot 616 Rest Shed Lot 616 Rest Shed MCOT to Lot 616 Rest Shed
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
Document No: : F OPS 01
HALUAN CEKAP SDN BHD Date Issued: : 17.03.2023
(641632-A) Version: 0
Revision: 0
DAILY PROGRESS REPORT Sheet: 1 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 17.03.2023 Wong Mee, Wan Hidayat, Patrick Wang,
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 2 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas To: Petronas Carigali Sdn Bhd (SKA)
Project Title: Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 17.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
Revision: 0
DAILY PROGRESS REPORT Sheet: 3 of 5
Document Type: Supporting Documentation
Provision of Onshore Pipeline Maintenance Services for Petronas
Project Title: To: Petronas Carigali Sdn Bhd (SKA)
Carigali Sdn Bhd.
Job no: P610 Attn: EIC Asyraf Wadjidee/PSS Roslee Yusof
Client: PETRONAS CARIGALI SDN BHD- SKA (QSM-22) CC: Haluan Cekap Sdn Bhd
Date: 17.03.2023 Wong Mee, Wan Hidayat, Patrick Wang
Location: Outside Perimeter MCOT Michael Kedit
Contract no: REP - 000000000116 From: Syed Mohd Hussaini
0830hrs - 0930hrs HCSB proceed with inhouse TBM at Lot 616 MCOT while waiting for permit approval
0930hrs-1200hrs 1.) Permit approved 0930hrs and all manpower proceed to outside MCOT perimeter for PL106/PL232 & PL 358 pipeline signage
2). Perform general housekeeping at all work area PL 358, PL 232 & PL 106 pipeline signage repair.(in progress)
1730hrs - 1800hrs 1.) Performed housekeeping before all manpower left from site MCOT.
2.) Permit daily suspend & handover to operation MCOT
AOB
% OF COMPLETION
No. ACTIVITIES
WEIGHTAGE (%) PLAN(%) ACTUAL(%) COMPLETE DATE
A PRE‐EXECUTION
1 Mobilize tools, equipment and materials to outside MCOT perimeter 2.5% 2.50% 2.50% 24.02.2023
2 Prepare and setup equipment at working area 2.5% 2.50% 2.50% 24.02.2023
3 EXECUTION
4 Pipeline Signage For PL358 Type A
27 Reinstate Existing Pipeline Signage Concrete Marker 1.00% 1.00% 1.00% 01.03.2023
Photo Attachment -
HCSB Equipment had been transferred from HCSB Toolbox had been transferred from outside
outside perimeter MCOT to HCSB KB Yard. perimeter MCOT to HCSB KB Yard.
____________________________________ ____________________________________
(SYED MOHD HUSSAINI) (Roslee Yusof)
CIVIL ENGINEER ENGINEER / PROJECT SITE SUPERVISOR (PSS)
HALUAN CEKAP SDN BHD PETRONAS CARIGALI SDN BHD ‐ SARAWAK ASSET
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
open
CLIENT PETRONAS CARIGALI SDN BHD – SARAWAK ASSETS DATE 18.05.23
Closed Out Report for Installation of New Pipeline
SUBJECT Signage for PL106 & PL358 and PL232 & PL346 at REV 0
HALUAN CEKAP SDN BHD
Outside Perimeter MCOT
open