Professional Documents
Culture Documents
Government Contracts With Independent Power Producers MS Report No. 2005 09
Government Contracts With Independent Power Producers MS Report No. 2005 09
Government Contracts With Independent Power Producers MS Report No. 2005 09
Government Contracts
with
Independent Power Producers
Republic of the Philippines
Commission on Audit
MANAGEMENT SERVICES
Commonwealth Avenue, Quezon City, Philippines
Telephone Nos. 931-9235, 931-7455
Sir:
The audit was conducted to assess the propriety of IPP contracting and
effectiveness of contract management in ensuring the provision of
uninterrupted power supply at reasonable cost taking into consideration the
contracted capacity, contract arrangements and fuel management.
SUSAN P. GARCIA
Director IV
Contents Page
Part I Executive Summary 1
Introduction 2
Audit Objective 2
Audit Scope & Methodology 3
Audit Conclusion 4
Introduction 10
The Electric Power System
Before RA 9136 13
Electric Power Industry Reform Act 13
Implementing/Participating Agencies
and Linkages 13
Introduction 18
IPP Contracts 18
Project Status 20
IPP Contract Review 21
Introduction 25
Observation 26
Management Comments and Team’s
Rejoinder 43
Introduction 49
Observations 49, 54, 56, 58, 59, 62,
63,66
Management Comments and Team’s
Rejoinder 51, 55, 57, 61, 62, 66, 69
Contents Page
Introduction 75
Observation 75, 81, 86, 89, 90
Management Comments and Team’s
Rejoinder 79, 85, 88, 90, 92
Part IV Recommendations 95
Part I
Executive Summary
1
EXECUTIVE SUMMARY
INTRODUCTION
The issuance of Executive Order No. 215 on July 10, 1987 opened to the
private sector an opportunity to participate in the electricity generation sector.
It was believed that the generation of electricity by the private sector can
provide a means of increasing power capacity to meet the projected increase in
power demand in the future without in anyway requiring financial assistance or
guarantee from the government. This paved the way for the entry of
Independent Power Producers (IPPs).
The participation of the private sector was enhanced under RA 6957 issued on
July 9, 1990 authorizing the financing, construction, operation and maintenance
of infrastructure projects by the private sector. All government infrastructure
agencies including government-owned and controlled corporations and local
government units were then authorized to enter into contract with any duly pre-
qualified contractor for the financing, construction, operation and maintenance
of any viable infrastructure facilities through the build-operate-and-transfer
(BOT) scheme or any of its variants.
At the height of the power crisis in 1993, RA 7648 was issued granting the
President of the Philippines authority to enter into negotiated contracts for the
construction, repair, rehabilitation, improvement and maintenance of power
plants, projects and facilities subject to certain requirements.
Pursuant to these laws, the National Power Corporation (NPC) entered into 42
IPP contracts under different contractual arrangements. Under these contracts,
NPC is under obligation to pay the IPPs, capital recovery fees among others, to
recover the IPPs’ capital investment with corresponding return on investment.
The total capacity fees payable to IPPs for the duration of the co-operation
period where ownership of the plant will be transferred to NPC at the end of co-
operation period are recognized outright in the books of the NPC as Electric
Plant under Capital Lease Plant. As of December 2005, there were 13 IPP
contracts recorded in the NPC books with an aggregate balance of P596 billion.
AUDIT OBJECTIVE
The audit was conducted to assess the propriety of IPP contracting and
effectiveness of contract management in ensuring the provision of uninterrupted
power supply at reasonable cost taking into consideration the
2
EXECUTIVE SUMMARY
following factors:
Contracted capacity
Contract arrangements
Fuel management
The audit covered the evaluation of IPP contracts and their implementation in
line with existing laws, rules, regulations and policies adopted by the following
agencies:
The team considered the following key criteria for assessing the propriety of
IPP contracting and effectiveness of contract management:
To achieve the audit objective, the team adopted the following audit techniques:
Confirmed data gathered from the concerned agencies with the data
3
EXECUTIVE SUMMARY
The audit was conducted from July 27, 2005 to May 13, 2006 pursuant to COA
MS/TS Office Order Nos. 2005-036 and 2005-036A dated July 6 and
November 11, 2005, respectively.
AUDIT CONCLUSION
The audit concluded that IPP contracting may not be considered properly
undertaken and contracts were not effectively managed. Thus, while power
supply was uninterrupted, the corresponding cost may not be considered
reasonable adversely affecting public interest. This is manifested in excessive
contracted generation capacities, unfavorable contract arrangements and lapses
in fuel management which contributed to NPC’s substantial losses as illustrated
below:
4
EXECUTIVE SUMMARY
The IPPs were allowed under the contract not to operate for a defined
period to undertake pre-arranged or planned outage, normal inspection,
maintenance or repair. In several cases, the defined period was not
consumed during the year and the unutilized balances were allowed to be
carried forward to the following year. This policy of forwarding unutilized
balances to succeeding year may affect the ability of NPC to meet energy
requirements on the affected year as IPPs were then allowed not to operate
for a longer period than necessary without being penalized.
Costs for the conduct of performance, efficiency and other tests are
chargeable to the account of the NPC when it is the IPPs’ responsibility to
demonstrate the plant capability to produce the contracted/guaranteed
capacity and net heat rates. Thus, in a number of cases, NPC did not
strictly require or even waived the conduct of testing to avoid the cost to
be incurred. This may not be considered appropriate as payments of IPP
fees were supposed to have been based on the results of tests. There was
therefore no assurance that the contracted plants are capable of delivering
the guaranteed electricity which are being paid for by the NPC.
The annual contracted quantities of natural gas for CYs 2002 to 2005 were
excessive being 141% to 195% of the forecasted need and 122% to 191%
of the total consumption. The unconsumed natural gas as of December 31,
2005 was recognized in the NPC’s books as stored fuel – Ilijan valued at
P31.280 billion. This amount, which was charged to the net government
share from Malampaya and deferred payment facilities, was unlikely to be
recovered and would eventually form part of NPC’s losses.
The minimum fuel inventory levels set for seven (7) IPPs were way
5
EXECUTIVE SUMMARY
Other fuel contracts with oil companies amounting to P2.113 billion were
likewise not based on forecasted fuel requirements resulting in excessive
fuel inventories which amounted to P2.654 billion as of December 31,
2005.
Seven (7) IPP contracts have no prescribed fuel limitations for activities
without energy generation such as start up, shutdown, and the like while
five others with different rated capacities and heat rates have the same
prescribed fuel limitations. For CY 2004 alone, fuel utilization of these
IPPs for this purpose ranged from P.280 to P20.620 million.
While NPC was prohibited under the EPIRA law to enter into new contracts for
the purchase of power, the management of existing IPP contracts still remains
with NPC. Hence, the team’s recommended measures under Part V of the report
were addressed to the NPC.
MANAGEMENT’S REACTION
The team forwarded the draft audit report to NPC, PSALM, DOE, and
TRANSCO on January 4, 2007 for comments. The DOE Secretary in turn,
forwarded a copy of the draft report to the Secretaries of Finance and Justice
and the Director-General of the National Economic Development
Administration for their comments, as members of the committee that reviewed
the IPP contracts.
NPC acknowledged the audit observations as true and correct with some
reservations. Detailed comments were incorporated in the report, where
appropriate. The NPC’s salient explanations were shared, in one way or
another, by TRANSCO and PSALM. They claimed that:
the additional contracts were entered into because of the looming power
shortage in Mindanao and to sustain the forecasted high power demand and
6
EXECUTIVE SUMMARY
reduce the country’s dependence on imported and costly fuel oil as well as
those hydro projects that have no power benefits. They, however,
acknowledged that the high economic targets were not attained and the actual
demands were below the forecasted peak demand targets. Thus, some IPPs
were underutilized during the period as dispatch was constrained. They
explained that the generating capacity would have been just sufficient to meet
the required reserve levels had the forecasted demand growth been realized.
they require the conduct of capacity and efficiency tests and inventory of
spare parts six months prior to end of contract
they based the contracted fuel quantity on generation and fuel consumption
forecasts and that the shortfall in the take-or-pay quantity for natural gas is
attributed largely to the Biňan-Dasmariňas line constraints which were
corrected only in February 2005. The minimum inventory level considers
procurement lead time and suppliers lead time for production of petroleum
products and restrictions in the logistics of fuel deliveries.
The comment of the DOJ that recommendations were in order was, however,
not shared by the DOE. The DOE considers the recommendation to negotiate
with the IPPs to lower the fees as non-doable as the Inter-agency Review
Committee had already submitted its recommendation to Malacaňang on July 2,
2002. It, however, concurs with the team that it is necessary to require the IPPs
to conduct performance tests prior to turn-over of the power plant to NPC.
TEAM’S REJOINDER
It is true that the team used the installed capacity as of December 1994 due to
the absence of any information on dependable capacity as of that date. The
Power Economics was able to provide data on dependable capacity only for
year 1997 and onwards. However, even in 1997, the reported installed and
dependable capacities were almost the same. This only shows that in 1994,
these plants were even more dependable.
The claim that additional contracts were entered into due to looming power
shortage in Mindanao was also unfounded. The five (5) additional plants
located in Mindanao were contracted during 1996 to 1998 when the two (2)
previously contracted IPP plants, NMPC 1 and 2, were claimed by NPC to be
on extended economic shutdown. This only manifests that installed capacities
already exceeded the requirements.
7
EXECUTIVE SUMMARY
It was also noted that the objective of reducing the country’s dependence on
imported and costly fuel oil was not served as two (2) of the additional
contracted plants were likewise run by diesel.
Moreover, NPC was already aware as early as 1997 that the forecasted demands
in 1994 were not being sustained and that a number of IPP plants were already
underutilized. Yet, seven (7) IPP contracts were still entered into between May
1997 and November 1998 and two (2) others renewed in 1999.
On the other hand, the benefits from requiring the conduct of capacity and
efficiency tests prior to the expiration of the contract may be negated by the
contract provision excluding warranties as to fitness and absence of defects of
the power station at the time of transfer.
Records would also prove wrong the claim that contracted fuel quantities were
based on fuel consumption forecasts as nine (9) IPPs without forecasted fuel
requirements were just the same included in the contract for the supply of fuel.
8
Part II
9
THE ELECTRIC GENERATION SECTOR
INTRODUCTION
NPC was created under Commonwealth Act No. 120 dated November 3, 1936
which nationalized the hydroelectric industry and reserved for the use of NPC,
all streams, lakes and springs in the Philippines where power may be
developed.
On September 9, 1971, by virtue of Republic Act No. 6395, the NPC charter
was revised and its activities and functions decentralized to be carried out by
three (3) regional offices to be established in Luzon, Visayas and Mindanao.
The scope of energy sources for power generation was also expanded under this
Act to include nuclear, geothermal, and other sources and mandated NPC to
undertake the establishment and operation of power transmission nationwide.
Thus, under Presidential Decree No. 40 dated November 11, 1972, NPC was
held responsible in setting up transmission line grids and construction of
associated generation facilities in Luzon, Visayas and Mindanao and major
islands of the country.
Under this Decree, the private sector participation in the electric industry was
limited to:
areas not embraced by the NPC grid, where the state may permit cooperatives
and private utilities to own and operate isolated grids and generation facilities;
such existing privately-owned generating facilities which the NPC may allow
to remain in operation; and
the distribution of electric power which may be undertaken by cooperatives,
local government units, and private utilities over their respective franchise.
In line with the NPC’s policy to centralize all generating capacities in Luzon
under its operation as part of the unification of the so called Luzon grid, the
government purchased the thermal plants of Meralco consisting of Malaya 1 in
Pililia, Rizal; Gardners1 and II, and Synders I and II in Sucat, Paranaque; and
fuel storage facilities in San Pascual, Batangas.
In 1987, by virtue of Executive Order No. 215 issued on July 10, 1987, the
construction and operation of the following types of electric generating plants
were opened to private corporations, cooperatives or similar associations
subject to existing rules and regulations:
10
THE ELECTRIC GENERATION SECTOR
To consider the private sector as the prime mover for economic growth. In this
regard, private initiative is to be encouraged, with deregulation and self-
regulation of business activities to be generally adopted where dictated by
urgent social concerns.
To play a supportive role, rather than competitive one, providing the
framework, the climate and the incentives within which business activity is to
take place.
Scheme/
Features
Variant
Build - Operate The project proponent is responsible for the following:
and Transfer
(BOT) • To undertake construction, including financing, of a given
infrastructure facility, and the operation maintenance thereof.
• To operate the facility over the fixed term during which it is allowed
to charge facility users appropriate tolls, fees, rentals, and charges
not exceeding those proposed in its bid or as negotiated and
incorporated in the contract to enable the project proponent to
recover its investment, and operating and maintenance expenses in
the project.
• To transfer the facility to the government agency or local
government unit concerned at the end of the fixed term which shall
not exceed fifty (50) years.
Build and The project proponent undertakes the financing and construction of a
Transfer (BT) given infrastructure or development facility and after its completion
turns it over to the government agency/local government unit
concerned which shall pay the proponent on an agreed schedule its total
investments expended on the project, plus reasonable rate of return
thereon. This arrangement may be employed in the construction of any
infrastructure or development project, including critical facilities which
for security or strategic reasons, must be operated directly by the
government.
11
THE ELECTRIC GENERATION SECTOR
Scheme/
Features
Variant
Build - Own and Project proponent is authorized to finance, construct, own, operate and
Operate (BOO) maintain an infrastructure or development facility from which the
proponent is allowed to recover its total investment, operating and
maintenance costs plus a reasonable return thereon by collecting tolls,
fees, rentals or other charges from facility users; Provided, that all such
projects, upon recommendation of the Investment Coordination
Committee (ICC) of the National Economic and Development
Authority (NEDA), shall be approved by the President of the
Philippines. Under this project, the proponent which owns the assets of
the facility may assign its operation and maintenance to a facility
operator.
Build - Lease and The project proponent is authorized to finance and construct an
Transfer (BLT) infrastructure or development facility and upon its completion turns it
over to the government agency or local government unit concerned on
a lease arrangement for a fixed period after which ownership of the
facility is automatically transferred to the government agency or local
government unit concerned.
Build - Transfer The public sector contracts out the building of an infrastructure facility
and Operate to a private entity such that the contractor builds the facility on a turn-
(BTO) key basis, assuming cost overrun, delay and specified performance
risks. Once the facility is commissioned satisfactorily, title is
transferred to the implementing agency. The private entity, however,
operates the facility on behalf of the implementing agency under an
agreement.
Contract - Add and The project proponent adds to an existing infrastructure facility which
Operate (CAO) it is renting from the government. It operates the expanded project
over an agreed franchise period. There may, or may not be a transfer
arrangement in regard to the facility.
Develop - Operate A contractual arrangement whereby favorable conditions external to a
and Transfer new infrastructure project which is to be built by a private project
(DOT) proponent are integrated into the arrangement by giving that entity the
right to develop adjoining property, and thus, enjoy some of the
benefits the investment creates such as property or rent values.
Rehabilitate - A contractual arrangement whereby an existing facility is turned over
Operate and to the private sector to refurbish, operate and maintain for a franchise
Transfer (ROT) period at the expiry of which the legal title to the facility is turned over
to the government. The term is also used to describe the purchase of an
existing facility from abroad, importing, refurbishing, erecting and
consuming it within the host country.
Rehabilitate - Own A contractual arrangement whereby an existing facility is turned over
and Operate to the private sector to refurbish, operate with no time limitation
(ROO) imposed on ownership. As long as the operator is not in violation of its
franchise, it can continue to operate the facility in perpetuity.
The BOT Program has been expanded under the streamlined Private Sector
Participation (PSP) Program, to cover not only the above BOT variants but also
other modalities such as joint venture agreements, Rehabilitate-Operate-
Maintain and Manage (ROMM), Build-Rehabilitate–Operate and Transfer
(BROT), among others.
12
THE ELECTRIC GENERATION SECTOR
Prior to the passage of Republic Act 9136, the generation of energy was
monopolized by NPC which is responsible for the transmission of electricity to
the distributor (like MERALCO) and large industrial users through its high
voltage wire comprising the transmission grid highway interconnecting the
main islands nationwide.
The Electric Power Industry Reform Act (EPIRA) of 2001 or Republic Act No.
9136 was signed into law on June 8, 2001 and became effective on June 26,
2001. It was designed to improve the delivery of power to end-users by
encouraging greater competition and efficiency in the electric industry and to
bring down electricity rates.
Among the major reforms embodied in RA 9136 are the restructuring of the
electric power industry and the privatization of the NPC. The restructuring of
the electric industry covers the separation of the different components of the
power sector into generation, transmission, distribution and supply sectors. On
the other hand, the privatization of the NPC would involve the sale of its
generation assets to private investors and award of the operation and
maintenance of the transmission assets to a concessionaire. Under this set-up,
the generation of energy shall be competitive and open to all qualified
generation companies and shall no longer be regulated. The transmission and
distribution shall be regulated and subject to the ratemaking power of Energy
Regulatory Commission.
13
THE ELECTRIC GENERATION SECTOR
Office Mandate/Functions/Responsibilities
14
THE ELECTRIC GENERATION SECTOR
Office Mandate/Functions/Responsibilities
Law/Date Responsibility
RA 6395/ To undertake the development of hydroelectric generation
9/10/71 power and production of electricity from nuclear,
geothermal and other sources, as well as transmission of
electric power on a nationwide basis.
PD 40/ To set up transmission line grids and construct associated
11/7/72 generation facilities in Luzon, Mindanao and major islands
of the country including the Visayas.
EO 215/ For the strategic and rational development of the country’s
7/10/87 power grids including construction of generating facilities
and setting up of transmission grids in Luzon, Visayas,
and Mindanao.
RA 9136/ NPC is responsible, among others, for the following:
6/8/01
• To perform the missionary electrification function through
the Small Power Utilities Group (SPUG) and provide
power generation and associated power delivery system in
areas not connected to the transmission system;
15
THE ELECTRIC GENERATION SECTOR
Office Mandate/Functions/Responsibilities
16
Part III
17
CONTRACTS WITH INDEPENDENT POWER PRODUCERS
INTRODUCTION
In the light of the looming power crisis and in adherence to the liberalization,
deregulation and privatization policies, the government entered into the first
phase of privatization in the energy sector.
These contracts take the forms of Power Purchase Agreement (PPA) where
NPC commits to purchase power generated by IPP, Energy Conversion
Agreement (ECA) where NPC provides fuel to IPP and purchased the generated
power and variants of Operation and Maintenance (O and M) agreements.
IPP CONTRACTS
18
CONTRACTS WITH INDEPENDENT POWER PRODUCERS
19
CONTRACTS WITH INDEPENDENT POWER PRODUCERS
PROJECT STATUS
As of March 31, 2006, the IPP power plants are in various status. One (1) was
under construction, one (1) pre-terminated, twenty two (22) were under
concession while co-operation period of 18 others were already terminated:
N Capacity
o. Project Name Proponent (MW) Status
Under Construction
1 Mindanao Coal-fired Thermal Power Harbin/State Investment 200 Target operation is October 2006
Plant Project I (China)/STEAG State Power, Inc. for Unit 1 and December 2006 for
Unit 2 and Power Plant.
Sub-Total 200
Pre-terminated
2 San Pascual Cogen Power Plant San Pascual Cogen, USA 304 Project did not materialize.
Contract pre-terminated.
Sub-Total 304
Under Concession
3 Benguet Province Mini Hydro : Operational
Ampohaw Mini Grid Hydro Electric Dev’t. Corp., Phil. 18.35
Bakun Mini Grid Northern Mini Hydro Corp. 11.90
4 Limay Bataan Combined Cycle ABB/Marubeni/Kawasaki, Swiss/ 310 Operational but under preservation
GasTurbine Power Plant Block B Japan status due to high cost of fuel and
5 Subic, Zambales Diesel Power Plant II Enron Power Corp., USA 116 low dispatch
6 Mindanao Diesel Power Barges Mitsui/BWES, Japan/Denmark 200 Operational
(PB117 and PB118)
7 Limay Bataan Combined Cycle ABB/Marubeni/Kawasaki, Swiss/ 310 Operational but under
GasTurbine Power Plant Block A Japan preservation status due to high cost
of fuel and low dispatch.
8 Naga Thermal Plant Comple SALCON, Philippines 202.10 Operational
9 Bauang, La Union Diesel Power First Private Power Corp., Phil. 235.2 Operational but under preservation
Plant status due to high cost of fuel and
10 Malaya Thermal Power Plant (Unit 1 KEPCO, South Korea 650 low dispatch.
and 2)
11 Pagbilao Coal-Fired Power Plant MIRANT, Philippines 728 Operational
20
CONTRACTS WITH INDEPENDENT POWER PRODUCERS
N Capacity
o. Project Name Proponent (MW) Status
12 Mindanao I Geothermal Plant Oxbow/Marubeni, USA/Japan 54.24 Operational
13 Leyte-Cebu A Geothermal Power PNOC-EDC 200
Plant
14 Leyte-Cebu B Geothermal Power 400
Plant
15 Zamboanga Diesel Power Plant ALSONs/Tomen, Philippines/Japan 113
16 General Santos Diesel Power Plant ALSONs/Tomen, Philippines/Japan 59
17 Mindanao II Geothermal Plant Oxbow/Marubeni, USA/Japan 54.24
18 Sual Coal-Fired Thermal Power MIRANT, Philippines 1,294
Plant
19 Bakun AC Hydro Power Plant Luzon Hydro Corp., Philippines 70
20 Casecnan Hydro Electric Plant NIA, Philippines 165
21 Ilijan Natural Gas Combined Cycle KEPCO, South Korea 1,271
Power Plant
22 CBK Complex IMPSA, Argentina 755.5
23 San Roque Multi-purpose Project Marubeni/Kansai Electric Power 345
Inc./Sithe Energies, Inc., Japan/USA
Sub – Total 7,562.53
Completed/Terminated
24 Subic, Zambales Diesel Power Plant I Enron Power Corp., USA 28 Contract concluded January 1998
25 Gas Turbine Power Barges Hopewell Tileman Ltd., Hongkong 270 Pre-terminated 1999
26 Clark Air Base Diesel Plant Electrobus, Philippines 50 Contract concluded January 1998
27 Binga Hydro Power Plant Chiang Jiang Energy Corp., China 100 Pre-terminated. NPC issued Notice
of Termination dated August 28,
2000
28 Calaca, Batangas Diesel Power Barges Far East Levingston, Singapore 90 Contract concluded September 1998
29 North Harbor Diesel Power Barges Far East Levingston, Singapore 90 Contracts concluded May 1999
30 Navotas Diesel Power Barges 1 East Asia Power Corp., Singapore 60
31 Navotas Diesel Power Barges 2 East Asia Power Corp., Singapore 60
32 Engineering Island Power Barge Sabah Shipyard SDN BHD, Malaysia 100
33 Ambuklao Hydro Power Plant MIESCOR, Philippines 75 Pre-terminated July 5, 2000. Plant
under asset preservation.
34 Navotas Gas Turbine 1-3 Hopewell Holdings Ltd., Hongkong 210 Contract concluded March 2003
and plants placed under
preservation status since then.
35 Toledo Cebu Coal Thermal Plant Atlas Cons. Mining & Devt. Corp., 55 Contract concluded February 25,
Philippines 2003
36 Pinamucan, Batangas Diesel Power Enron Power Corp., USA 105 Contract concluded July 2003
Plant Transferred to NPC July 22, 2003
37 Iligan City Diesel Plant I ALSON/Tomen, Philippines/Japan 58 Contract concluded July 2003 and
plant placed under asset
preservation since then. Resumed
operation on February 2004.
38 Bataan EPZA Diesel Plant Edison Global, Hongkong 58 Contract concluded June 21, 2004
39 Makban Binary Geothermal Plant Ormat, Inc., USA 15.73 Contract concluded June 2004
Turned-over to NPC June 30, 2004
40 Navotas Gas Turbine 4 Hopewell Energy Int’l. Ltd., 100 Contract concluded August 2005
Hongkong Transferred to NPC August 1, 2005
41 Cavite EPZA Diesel Plant Magellan Cogen Utilities, Philippines 43 Contract concluded December 5,
2005
42 Iligan City Diesel Plant II ALSON/Tomen, Phil./Japan 42 Plant not operational at the time of
inspection and reportedly placed
under Asset Preservation since its
turn-over on February 9, 2006.
Sub-Total 1,609.73
TOTAL 9,676.26
21
CONTRACTS WITH INDEPENDENT POWER PRODUCERS
No. of IPP
Results
contract
No finding of legal and financial issues. 6
Had some remedial financial issues that need to be addressed to assure that 11
the government and the public are not being financially prejudiced.
Found to have legal or financial issues that need to be referred for 16
appropriate study
Had only remedial policy issues 2
Total 35
22
Part IV
Audit Observations
23
Chapter 1
24
ADEQUATE CONTRACTED CAPACITY
INTRODUCTION
To achieve the above objective, the DOE was required under the Rules and
Regulations implementing Executive Order No. 215 to provide policy
directions for the formulation of power system expansion plans and programs
consistent with the approved national economic plan and policies on
environmental protection, conservation and maintenance of ecological balance.
On the other hand, NPC is responsible for the formulation and implementation
of such programs as are necessary to ensure the reliability of electricity and
power grids, consistent with the general and specific policies adopted by the
DOE. NPC may undertake generation and transmission projects through private
sector participation. For this purpose, NPC is required to submit development
program to DOE reflecting an efficient portfolio of generation and demand-side
resources, for the DOE’s review and approval.
The audit disclosed that while the reported installed generating capacity as of
December 1994 was already adequate to meet the NPC’s forecasted peak
demand for the period 1995 to 2000, NPC still entered into 12 additional IPP
contracts from 1995 to 1999. This resulted in underutilized generation
capacities and high generation cost of NPC contributing to NPC’s substantial
losses.
25
ADEQUATE CONTRACTED CAPACITY
OBSERVATION
Twelve (12) additional IPP contracts were entered into by NPC from
1995 to 1999 with total capacity of 3,758.25 MW despite adequate
generation capacity as of December 1994 to meet the system-wide
forecasted peak demand including the required reserves for the years
1995 to 2000. This manifests lapses in assessment of needs before
contracting. Thus, a number of IPPs were underutilized of which five
(5) were already placed under preservation status as of March 2006
due to low dispatch. As a result, NPC incurred substantial losses in
generation costs per kwh of P1.5564 and P1.9164 in CYs 2004 and
2005, respectively, representing IPP fees and fuel costs alone.
The NPC, under Presidential Decree No. 40 dated November 7, 1972, was
authorized to own and operate, as a single integrated system, all generating
facilities supplying electric power to the entire area embraced by any of its grid.
By virtue of Executive Order No. 215, issued in 1987, the government allowed
private investors to participate in electric power generation. Private sector
participation was further encouraged under the Omnibus Investment Code of
1987 and expanded upon issuance of RA 6957 issued on July 9, 1990 as
amended by RA 7718 issued on May 5, 1994.
Date of Coop.
Capacity Contract Commercial Period
Project Name Proponent (MW) Execution Operation (years)
1. Navotas Gas Turbine 1-3 Power Hopewell Project Mgmt. Co. Ltd., 210 11/16/ 88 1/91 12
Station Hongkong (H.K.)
2. Pagbilao Coal-Fired Power Plant Hopewell Holdings Ltd., H.K. 2 x 350 11/9/91 3/96 – 6/96 29
3. Mindanao Diesel Power Barges Proj. Mitsui/BWES, Japan/Denmark 2 X 100 2/13/ 92 3/94 – 8/94 15
4. Mak-Ban Binary Geothermal Plant ORMAT Inc., USA 15.73 2/21/92 3/94 10
5. Bataan Gas Turbine Combined Cycle ABB/Marubeni/Kawasaki SC 90 2/27/92 4/94- 10/94 15
GTPP “Block A” Consortium, Swiss/Japan CC 300
6. Navotas Gas Turbine Power Station Hopewell Holdings Ltd., H.K. 100 6/29/92 3/93 12
Unit 4
7. Pinamucan Diesel Power Plant Enron Power Corp., USA 105 6/29/92 7/93 10
8. Iligan City Diesel Plant I ALSONS/TOMEN, Phil/Japan 58 6/29/92 7/93 12
9. Bataan Gas Turbine Combined Cycle ABB/Marubeni/Kawasaki SC 90 6/29/92 11/93–12/94 15
GTPP “ Block B” Consortium, Swiss/Japan CC 300
10. Nine (9) Gas Turbine Power Hopewell Tileman Ltd., 270 4/92 1/93 10
Barges/Navotas Hongkong
11. Clark Air Base Diesel Plant/ Electrobus Consolidated, Phil. 50 7/31/92 7/92 7
Pampanga
12. Ambuklao Hydro Electric Power MIESCOR, Philippines 75 9/14/92 10/95 5
Plant/Mt. Province
26
ADEQUATE CONTRACTED CAPACITY
Date of Coop.
Capacity Contract Commercial Period
Project Name Proponent (MW) Execution Operation (years)
13. Iligan City Diesel Power Plant II ALSONS/TOMEN, Phil./Japan 40 11/19/92 12/93 12
14. Subic Diesel Power Plant II Enron Power Corp., USA 108 1/7/93 2/94 15
15. Subic Diesel Power Plant I 28 1/8/93 1/03 5
16. Bauang Diesel Power Plant First Private Power Corp., Phil. 215 1/11/93 7/95 15
17. Calaca Diesel Power Barge Far East Levingston, Sing./Polar 3 x 30 1/18/93 9/93 5
18. Benguet Province Mini-Hydro Hydro Electric Dev. Corp. 18.25 10/14/99 1/93 25
12.70 1/23/93
19. Toledo Coal-Fired Thermal Power Plant Atlas Com. Mining and Dev’t Corp. 55 2/25/93 2/93 10
20. Binga Hydro Power Plant Chiang Jiang Energy Corp., China 100 7/5/93 8/93 15
21. Cavite EPZA Diesel Power Plant Magellan Cogeneration Utilities, 43 9/23/93 12/95 10
Philippines
22. Engineering Island Power Barge Sabah Shipyard, SDN, BHD, 100 9/8/93 10/94 5
Malaysia
23. Bataan EPZA Diesel Power Plant Edison Global, Hongkong 58 10/15/93 6/94 10
24. Navotas Diesel Power Barge I East Asia Power Corp., Singapore 60 11/93 9/94 5
25. Navotas Diesel Power Barge 2 60 11/93 9/94 5
26. North Harbor Diesel Barges (FELS Far East Levingston, Singapore 2 x 45 12/27/93 7/94 5
2)/Navotas
27. Leyte A Geothermal Power Plant PNOC-EDC, Philippines 200 3/4/94 7/96 15
28. Naga Thermal Plant Complex SALCON Power Corp., Phil. 185.8 3/25/94 11/94 – 6/97 15
29. Leyte B Geothermal Power Plant PNOC-EDC, Philippines 440 5/6/94 7/97 25
30. Sual Coal-Fired Thermal Power Plant Hopewell, Tileman Ltd., H.K. 1,000 5/20/94 10/99 25
31. Casecnan Hydro Electric Plant National Irrigation Admin. 140 6./30/94 4/5/02 20
TOTAL 5,427.48
As may be noted, ten (10) of these IPPs with total capacity of 3,026.80 MW
were operated commercially after 1994. This capacity was apparently not yet
included in the NPC’s report of installed generation capacity of 9,061 MW as of
December 1994 as reflected in the Power Development Program (PDP). This
brought to 12,087.60 MW the total capacity that would be available after 1994
as follows:
Installed
Location Capacity (MW)
Luzon 6,641.00
Visayas 888.00
Mindanao 1,532.00
Sub-Total 9,061.00
Commercially operated after 1994 3,026.80
Total 12,087.80
It was also disclosed in the 1995 PDP that the forecasted system-wide peak
demand for the years 1995 to 2000 would ranged from 5,277 to 9,681 MW
excluding the required reserves to ensure uninterrupted energy supply which
was computed as follows:
27
ADEQUATE CONTRACTED CAPACITY
(In MW)
Year
Forecasted 23.40% Total
Peak Demand Reserves Requirements
1995 5,277 1,234.82 6,511.82
1996 5,855 1,370.07 7,225.07
1997 6,613 1,547.44 8,160.44
1998 7,588 1,775.59 9,363.59
1999 8,621 2,017.31 10,638.31
2000 9,681 2,265.35 11,946.35
Despite sufficient existing plant capacity, NPC still entered into 12 IPP
contracts with total capacities of 3,758.25 MW and renewed two terminated
contracts from 1995 to 1999:
No. of
Months
Date of Const’n. before
Capacity Contract Comm’l period Comm’l.
Project Name/Location Proponent (MW) Exec’n. Oper’n. (years) Oper’n.
1 Zamboanga Diesel Power Plant Alsons/TOMEN, Phil/Japan 100 3/28/96 12/97 21
2 Gen. Santos Diesel Power Plant 50 10/26/96 4/98 18
3 Bakun A, B and C Hydro HEDCOR/AEV, Philippines 70 11/24/96 10/00– 4 48
Electric Plant/Mt. Province 2/01
4 Paragua Power/Palawan Paragua Power Company, Phils. 16 5/27/97 12/17/99 2.5 31
5 San Pascual Cogeneration San Pascual Cogeneration Corp., 304 9/10/97 Pre-
Power Production Facility/ USA terminated
Batangas
6 San Roque Multi-Purpose Marubeni/Ital-hai/Sithe, Japan 345 10/11/97 5/03 5.5 67
Hydro-Electric Power Project/
Pangasinan
7 Ilijan Natural Gas Power Plant/ Korean Electric Power Corp 1,200 11/5/97 6/02 4.5 55
Batangas (KEPCO), South Korea
8 Mindanao II Geothermal Plant/ PNOC-EDC, Philippines 48.25 6/1/98 6/99 12
Mt. Apo
9 Mindanao Coal Fired Thermal State/Harbin, Philippines/China 200 6/29/98 On-going - 100*
Power Plant Project I/Misamis
Oriental
10 Caliraya – Botocan - Kalayaan IMPSA, Argentina 728 11/6/98 2/02 – 3.25 39
Hydro Electric Plants/Laguna 7/04 .68
11 Mindanao I Geothermal PNOC-EDC, Philippines 47 5/12/95 2/97 1.75 21
Plant/Mt. Apo
12 Malaya Thermal Power Plant/ Korean Electric Power Corp 650 5/17/95 9/95 0.33 4
Rizal (KEPCO), South Korea
Sub-total 3,758.25
13 Benguet Province Mini- HEDCOR, Philippines 22 10/14/99 Renewal
Hydro/Benguet
14 Paragua Power/Palawan Paragua Power Company, 16 12/17/99 Renewal
Philippines
TOTAL 3,796.25
* As of October 2006
It may be noted that while the contract provides that these plants were needed to
support rapid economic growth, these were commercially operated only after 4
to 68 months with one (1) contracted in 1998 still on-going as of October 2006
and another one (1) already pre-terminated.
28
ADEQUATE CONTRACTED CAPACITY
It would appear then that the basis for contracting was not established. Even
the extent of utilization of existing NPC-IPPs and NPC-Owned Power Plants
was apparently not considered prior to subsequent contracting. Records show
that during 1994 to 1996, some of the IPPs and NPC-Owned Power Plants were
only 1 to 60% utilized as illustrated below:
IPPs
Clark 48.80 367,688,160 132,576,282 36 367,688,160 134,878,152 37 367,688,160 50,570,488 14
Limay Bataan
620 1,744,000,000 2,397,716,348 137 3,904,000,000 2,758,308,000 71 3,904,000,000 2,479,194,000 63
CCPP
MB-Ormat 18.5 90,403,200 29,058,290 32 90,403,200 33,118,680 37 90,650,880 43,903,440 48
BPPC 235.5 1,540,000,000 158,274,900 10 1,540,000,000 1,342,013,800 87 1,540,000,000 1,046,000,800 68
Magellan 63 241,860,000 20,964,695 9 348,340,000 92,735,180 27 343,390,000 167,681,380 49
CTPP/Salcon 109.3 1,068,000,000 341,165,000 49 999,000,000 381,470,000 38 1,051,000,000 382,080,000 60
NMPC 1 62.7 466,000,000 113,545,800 24 466,000,000 172,641,200 37 466,000,000 2,885,400 1
PB 117 100 800,000,000 114,457,900 14 800,000,000 208,508,000 26 800,000,000 90,759,800 13
PB 118 100 800,000,000 124,702,600 15 800,000,000 313,463,600 39 800,000,000 393,391,500 49
NPC-Owned
Bacman GPP 150 624,600,000 554,097,740 89 624,600,000 715,175,140 115 624,600,000 643,529,655 103
Makban GPP 410 2,043,600,000 2,265,244,600 111 2,043,600,000 1,895,160,279 93 2,043,600,000 2,431,418,557 119
Tiwi GPP 275 1,127,100,000 2,013,598,630 179 1,127,100,000 1,722,831,945 153 1,127,100,000 1,526,211,985 135
Calaca CFTPP 600 2,488,200,000 1,050,246,000 42 2,488,200,000 1,783,665,000 72 2,488,200,000 2,040,634,000 82
Palimpinon 192.5 1,267,200,000 864,315,930 68 1,267,200,000 1,091,773,940 86 1,267,200,000 1,177,197,000 93
Panay (PDPP I) 36.5 57,390,000 72,743,900 127 57,390,000 40,873,120 71 57,390,000 48,444,000 84
Note: For NPC owned power plants, the data used in arriving at the total expected/guaranteed generation for each plant are the highest daily generation based on the daily
operation report for the period August 25 to September 25, 2006, except for Tiwi and Makban plants where the daily generation were based on the daily operation report for
the period January 25 to February 25, 2006, and multiplied by the number of days in a year net of 65 days provision for outages.
Further evaluation disclosed that the forecasted peak demand in 1995 for CYs
1995-2000 were consistently being adjusted to a lower level year after year as
illustrated below:
* The PDP in 1995 was adopted in 1996 since there was no revision in the government’s economic targets.
29
ADEQUATE CONTRACTED CAPACITY
Limay CCPP 620 3,904,000,000 1,520,643,960 39 3,904,000,000 1,801,221,000 46 3,904,000,000 747,905,000 20 3,904,000,000 438,755,000 11 3,904,000,00 738,437,100 19
Pinamucan 105 825,016,800 271,867,000 33 825,016,800 346,166,000 42 825,016,800 235,196,000 29 825,016,800 140,017,000 17 - - -
MB-Ormat 185 90,650,880 48,233,520 53 90,403,200 40,302,720 45 90,403,200 37,517,370 49 90,403,200 21,806,640 24 90,650,880 4,057,200 4
Malaya-KEPCO 650 4,611,600,000 1,213,895,200 26 4,611,600,000 1,743,556,600 38 4,611,600,000 665,620,000 15 4,611,600,000 838,267,800 18 4,611,000,000 1,153,999,800 25
BPPC 235.2 1,540,000,000 289,581,800 19 1,540,000,000 390,092,600 25 1,540,000,000 218,205,000 15 1,540,000,000 247,202,500 16 1,540,000,000 235,985,600 15
Sual CFTPP 1294 9,627,360,000 5,533,566,000 58 9,627,360,000 5,941,021,000 62 9,627,360,000 5,341,662,000 56 9,627,360,000 4,667,365,630 49 9,627,360,000 5,443,130,000 57
CTPP/Salcon 109.3 1,177,000,000 225,187,000 19 1,201,000,000 360,216,000 30 1,177,000,000 399,969,000 34 1,201,000,000 474,955,000 40 1,177,000,000 454,746,000 39
NMPC II 40 321,600,000 9,830,700 3 321,600,000 4,692,350 1 321,600,000 41,716,020 13 321,600,000 83,896,380 26 321,600,000 105,671,320 33
PB 117 100 800,000,000 115,931,300 14 746,600,000 175,643,580 23 746,600,000 305,887,794 41 746,600,000 492,580,400 66 746,600,000 573,909,900 77
PB 118 100 800,000,000 245,469,800 31 746,600,000 289,408,930 39 746,600,000 402,412,960 54 746,600,000 583,711,200 78 746,600,000 578,596,430 77
WMPC 113 744,600,000 11,230,800 2 744,600,000 16,407,100 2 744,600,000 51,037,600 7 744,600,000 163,589,800 22 744,600,000 311,581,200 42
SPPC 59 372,300,000 97,752,000 26 372,300,000 151,952,500 41 372,300,000 170,069,030 46 372,300,000 232,673,390 63 372,300,000 240,765,374 65
30
ADEQUATE CONTRACTED CAPACITY
Considering that the NPC is obligated under the IPP contracts to pay fixed
capital/capacity recovery fees irrespective of generation, this then resulted in
NPC’s substantial losses in generation costs. The generation cost per kwh is
affected by the volume of generation. The unit cost decreases as the volume of
generation increases. For CYs 2004 and 2005, it costs NPC an average of P4.98
and P5.34 per kwh, respectively. These generation costs include only the IPP
fees and fuel costs. The costs of plant sites lease, salaries of NPC employees
and other operating costs incurred in the management of IPP contracts were not
yet taken into consideration.
On the other hand, the ERC’s approved generation rate per kwh for the period
was only P3.4236. In effect, NPC incurred losses of at least P1.5564 and
P1.9164 per kwh in 2004 and 2005, respectively, for IPP fees and fuel costs
alone.
The IPP plants operated in CYs 2004 and 2005 with generation costs ranging
from P1.02 to P2,718.39 per kwh is illustrated below:
Actual Energy
Delivered Per Total Power Total Generation Unit Cost/
IPPs *MOR (in KWh) Billing Total Fuel Cost Cost KWh
2004
1 Ilijan Natural Gas 3,957,706,226.00 P 6,721,409,873.78 P 6,866,743,382.10 P 13,588,153,255.88 P 3.43
2 Pagbilao Coal-Fired TPP 1,979,760,600.00 12,329,389,926.26 2,515,330,047.00 14,844,719,973.26 7.50
Navotas Gas Turbine 4
3 (Tileman) 117,450.00 317,500,611.56 1,774,680.00 319,275,291.56 2,718.39
Northern Mindanao Power
4 Corp. II 94,782,740.00 436,123,194.33 269,181,241.00 705,304,435.33 7.44
5 Bauang La Union DPP 470,623,000.00 2,952,683,317.33 587,495,420.00 3,540,178,737.33 7.52
6 Luzon Hydro 1 & 2 59,613,663.00 2,205,164,927.33 0.00 2,205,164,927.33 36.99
7 Sual Coal Fired TPP 1 & 2 4,537,405,050.00 14,264,308,227.53 6,913,969,961.00 21,178,278,188.53 4.67
8 Subic Zambales Diesel Plant II 231,561,900.00 1,801,028,648.76 630,527,368.00 2,431,556,016.76 10.50
9 San Roque Power Corp. 778,575,051.00 7,263,174,275.94 0.00 7,263,174,275.94 9.33
10 Leyte Geothermal PP 4,052,316,715.00 13,356,727,979.56 0.00 13,356,727,979.56 3.30
11 Cavite EPZA DPP (MCI) 8,701,000.00 9,643,647.99 26,658,387.00 36,302,034.99 4.17
12 Western Mindanao Power Corp. 312,847,694.00 1,374,342,095.01 807,281,781.00 2,181,623,876.01 6.97
Bataan EPZA Diesel Plant
13 (Edison) 17,389,700.00 215,590,537.87 69,048,336.00 284,638,873.87 16.37
14 Southern Phil. Power Corp. 237,945,598.00 734,757,777.20 651,258,086.00 1,386,015,863.20 5.82
Mindanao Geothermal I -Mt.
15 Apo I 437,880,640.00 1,352,566,430.94 0.00 1,352,566,430.94 3.09
Mindanao Geothermal II - Mt.
16 Apo II 422,297,170.00 1,227,257,653.77 0.00 1,227,257,653.77 2.91
17 Northern Mini Hydro 46,038,160.00 161,795,005.35 0.00 161,795,005.35 3.51
Bakun A, B, & C
18 HEP/HEDCOR 213,682,870.00 218,930,814.33 0.00 218,930,814.33 1.02
19 NIA Casecnan 402,219,600.00 2,114,351,791.56 0.00 2,114,351,791.56 5.26
20 Naga Thermal Plant 547,940,399.00 902,171,906.92 1,983,723,381.00 2,885,895,287.92 5.27
21 Malaya Thermal PP 1,119,932,602.00 3,454,429,420.68 3,977,365,482.00 7,431,794,902.68 6.64
22 CBK Caliraya 83,192,257.00 194,866,073.10 0.00 194,866,073.10 2.34
23 CBK Kalayaan 889,943,992.00 5,787,400,718.90 0.00 5,787,400,718.90 6.50
24 CBK Botocan 33,069,188.00 170,312,957.17 0.00 170,312,957.17 5.15
25 Makban Binary Geot. Plant 3,445,691.00 52,497,353.77 52,497,353.77 15.24
26 Limay, Bataan (Block A) 259,114,500.00 1,147,212,986.34 2,311,722,126.00 4,705,099,770.89 6.83
27 Limay, Bataan (Block B) 429,779,000.00 1,246,164,658.55
28 Power Barge – PB 117 546,376,600.00 558,587,707.54 1,181,497,484.00 1,740,085,191.54 3.18
29 Power Barge – PB 118 545,470,200.00 538,975,877.35 1,266,130,299.00 1,805,106,176.35 3.31
Total 22,719,729,256.00 83,109,366,396.72 30,059,707,461.10 113,169,073,857.82 4.98
2005
1 Ilijan Natural Gas 6,422,855,397.00 6,962,613,346.96 12,604,311,248.00 19,566,924,594.96 3.05
2 Pagbilao Coal-Fired TPP 2,441,262,900.00 12,574,776,194.64 3,475,013,602.00 16,049,789,796.64 6.57
3 Navotas Gas Turbine 4
(Tileman) 1,427,850.00 188,397,584.11 5,109,974.00 193,507,558.11 135.52
4 Northern Mindanao Power
Corp. II 120,798,813.00 606,301,941.46 461,499,001.00 1,067,800,942.46 8.84
31
ADEQUATE CONTRACTED CAPACITY
Actual Energy
Delivered Per Total Power Total Generation Unit Cost/
IPPs *MOR (in KWh) Billing Total Fuel Cost Cost KWh
The computed costs exclude unconsumed natural gas intended for Ilijan Natural
Gas Power Plant amounting to P9.129 billion billed by Shell/Oxy. These were
charged against the share of the government from the net proceeds on Quarterly
Assigned Petroleum Amount from Malampaya in the amount of P1.659 billion
and Deferred Payment Facility of P7.470 billion for CYs 2004 and 2005. As of
December 31, 2005, unconsumed natural gas recognized in the NPC books
already amounted to P 31.280 billion.
Analysis of IPPs’ generation data, fees charged to NPC and other records,
interviews and results of ocular inspection conducted by the team on selected
IPP and NPC-owned plants disclosed the following information:
32
ADEQUATE CONTRACTED CAPACITY
33
ADEQUATE CONTRACTED CAPACITY
7. Bataan Combined Cycle Power Plant Each block guaranteed electrical energy
(Block A & B) consisting of 8 units production of 872 GWh for the first six (6)
Limay, Bataan months and 1,952 GWh thereafter.
Actual generation in CYs 2000 to 2004
ranged from 11% to 46% of the
guaranteed generation.
Generation cost per kwh was P6.83 and
P35.93 in 2004 and 2005, respectively.
The plant, composed of 7 units, is
currently under economic shutdown since
July 2005. Another unit (ST KIA) under
plant outage is about to be commissioned
on inspection date.
8. Subic Bunker-fired Diesel Power
Plant II Subic, Zambales A base load plant with contracted capacity
of 108 MW expected to operate 24 hours
daily except during scheduled
maintenance.
34
ADEQUATE CONTRACTED CAPACITY
10. Mindanao Geothermal Power Plant 1 During actual plant visit on March 9, 2006,
& 2 (2 @ 52.3 MW gross capacity) the two (2) power plants are operating on
Mt. Apo, Kidapawan, North Cotabato full capacity, as follows:
In MW
Time Particulars Mt. Apo 1 Mt. Apo 2
0930 HRS Gross 52.50
Station Use 2.661
Net* 49.849
0840 HRS Gross 53.00
Station Use 2.455
Net* 50.545
11. Power Barges 117/118 (2@50 MW Generation of PB 117 and 118 during the
rated capacity each Power Barge) period 2000 to 2004 ranged from 14 to 77%
Nasipit, Agusan Norte/Maco, and 31 to 78%, respectively, of the expected
Compostela Valley generation.
35
ADEQUATE CONTRACTED CAPACITY
36
ADEQUATE CONTRACTED CAPACITY
37
ADEQUATE CONTRACTED CAPACITY
NPC Owned
38
ADEQUATE CONTRACTED CAPACITY
5. Aplaya Diesel Power Plant Another NPC-owned plant with Units 1 and
Bo. Aplaya, Jasaan, Misamis Oriental 2 of Plant No. 1 already dismantled. The
with an installed capacity of 125 MW. team was informed that in October 1983,
one unit was dismantled and transferred to
NPC diesel power plant located in Bohol
and some parts were deployed to General
Santos while sometime in 1996, another
unit (Unit #1) was dismantled and
transferred to Mindoro and Palawan.
39
ADEQUATE CONTRACTED CAPACITY
7. Agus V Hydro Electric Power Plant The plant is one of the six (6) hydroelectric
Ditucalan, Iligan City generating plants harnessing raw water
power potential along the Agus river. It has
two (2) units run-of-the-river type with a
combined capacity of 55 MW and is
situated between the tailwater of Agus IV
and the headwater of Agus VI.
8. Agus VI Hydro Electric Power Plant, Originally known as the Maria Cristina
Fuentes, Iligan City Falls HEP, it has five (5) generating units.
Of the seven (7) hydro sites along the Agus
River, Agus VI was the first to be
developed and completed as the site is the
most feasible, simple, and economical to
construct due to proximity to its expected
power consumers. It is operating as a base
load plant.
40
ADEQUATE CONTRACTED CAPACITY
10. Pulangi IV Hydro Electric Power This is the first ever HEP in the Philippines
Plant, Maramag, Bukidnon to be ISO 9002 Certified in 1997 and the 3rd
recipient of this prestigious citation in NPC.
On November 15, 2005, Pulangi IV was
confirmed ISO 9001:2000 (for Quality), ISO
14001-2004 (for Environment) and OHSAS
18001:1999 (for Occupational Health and
Safety) by the TUV Management Service.
41
ADEQUATE CONTRACTED CAPACITY
12. Binga Hydroelectric Power Plant (100 NPC entered into Rehabilitate Operate and
MW), Tinongdan, Itogon, Benguet Leaseback (ROL) - Power Purchase
Agreement (PPA) with China Chang Jiang
Energy Corporation Group (CCJECG) on
July 5, 1993 with co-operation period of
fifteen (15) years reckoned from August 12,
1993. The rights and obligations of the
CCJECG was assigned to Binga
Hydroelectric Plant, Inc. (BHEPI) on
January 14, 1997.
Under the contract, NPC will purchase and
pay for all power generated by the plant
while the contractor shall pay NPC a
monthly rental fee of US$210,000 per
month. On August 28, 2000, NPC’s
contract with BHEPI was pre-terminated
and NPC entered into contract with Itogon
Power Generation Corporation for the
operation and maintenance of the plant on
April 15, 2001.
The reported generation of the plant in kwh
from 1994 to 2004 ranged from
244,338,156 to 402,597,563.
13. San Pascual Cogeneration Company NPC entered into Power Purchase
International, B.V. (SPCC), San Agreement (PPA) on September 10, 1997
Pascual, Batangas for the construction and operation of a
cogeneration power production facility with
Pre-terminated on November 12, 2003 commercial operation of forty-four (44)
calendar months from the date of signing on
May 10, 2001. The commercial operation
date was eventually moved to January 1,
2004.
The extended date of commencial operation
was not met and the PPA was recommended
for termination by the Inter-Agency
Committee. Instead of terminating the PPA,
PSALM decided to utilize the PPA as a
component of the Generation Project by
requiring SPCC to directly assign all its
title, rights, interests, obligations, and
liabilities to or in the PPA to the winning
bidder of the Generation Project and
PSALM to pay SPCC Philippines a transfer
price of US$6,000,000 or P338,142,000
under the Framework Agreement dated
November 12, 2003.
In addition to the transfer price, PSALM
also paid US$1,917,050 or P105,652,459.60
to N.M. Rothschild and Sons (HK) Ltd., for
financial advisory services needed in
relation to SPCC’s IPP contract.
42
ADEQUATE CONTRACTED CAPACITY
43
ADEQUATE CONTRACTED CAPACITY
Actual generation as
Power Plant % of guaranteed
generation
BPPC 10.278
CTPP/Salcon(c) 49.216
NMPC I 24.366
PB 117 14.307
PB 118 15.588
Further, when the power crisis was finally The team is not questioning the optimistic
eradicated in 1993, the Government was view of the government at that time and
very optimistic and upbeat about the setting of high projections in power
prospects of the country as the next demand but the fact that despite available
“tiger” economy in Asia. As a result, the capacity to meet the higher projected
Government set high economic targets power demand, NPC still entered into 12
which resulted in higher projections in new IPP contracts. Moreover, the
power demand as indicated in the 1993 objective of reducing dependence on
Power Development Program. To sustain costly fuel oil was not evident as out of
the forecasted high power demand, the 12 the 12 additional contracts, two (2) were
additional IPP contracts were entered into still run by diesel fuel oil while out of the
between 1995 and 1999. However, total 42 IPP plants, 23 were run by diesel
emphasis should also be given to power fuel oil.
projects that were undertaken by the
Government to reduce the country’s It would also appear that Casecnan, which
dependence on imported and costly fuel was contracted by NPC in 1994 to be
oil as well as those hydro projects that operational by year 2002, was already
have non-power benefits such as considered in 1995 as one of the hydro
Casecnan and San Roque. projects with non-power benefits.
44
ADEQUATE CONTRACTED CAPACITY
The high economic targets were not Apparently, NPC was already aware as
sustained since the actual demands during early as 1997 that the demands forecasted
the period 1994 to 2000 were below the in 1994 were not being sustained and that
forecasted peak demand targets, a number of existing IPPs were already
aggravated largely by the Asian financial underutilized. Yet, seven (7) IPP
crisis in 1997. As a result, dispatch of contracts were still entered into between
some of these IPPs were constrained and May 1997 to November 1998 and
underutilized during the period. contracts for the other two (2) still
renewed in 1999.
NPC has already negotiated with IPPs for The team recognizes NPC’s efforts in
reduced NCC and MEOT as mandated by negotiating with the IPPs to reduce the
the EPIRA/IPP Contracts Review NCC and MEOT. However, it is
Committee. Some of the IPPs have agreed recommended that further negotiation be
to lower their MEOT and NCC but not made on account of the deficiencies noted
their fee rates. These IPP concessions by the team.
resulted in the extension of the
cooperation period provided in their
respective contracts.
Provided by TRANSCO
It likewise did not consider the economics As illustrated earlier, this alleged
of using the “excess” but cheap capacity objective of replacing expensive plants
to replace the very expensive existing with cheaper plants was not manifested in
plants at that time whose role was then the IPP plants subsequently contracted by
relegated to being reserve plants. In fact, the NPC. Of the 12 IPPs contracted from
as COA implies, System Operations 1995 to 1998, two (2) were run by diesel
45
ADEQUATE CONTRACTED CAPACITY
We would like to point out also that oil- Records show that these plants were
fired thermal power plants, which were being used until CY 2000 and 2001for
used as base-load generation up to the Sucat Oil Thermal. Malaya Oil Thermal
early 1990’s, were either retired (Bataan, was even rehabilitated and was
Manila and Sucat) or mothballed operational as of audit date but was under
(Malaya) because of their high operating economic shutdown.
costs. Additional generating capacity was
put up to replace these expensive plants. As discussed earlier, of the 12 new plants
Further, some of the IPP generating contracted, two were also oil based. In
capacity was contracted before the Asian effect then, the plants claimed to be
financial crisis hit the country and expensive to operate were replaced by
dampened the expected load growth. Had equally expensive ones. Likewise, while
the forecast demand growth been it is true that some plants were contracted
realized, the generating capacity would before the Asian financial crisis, seven (7)
have been just sufficient to meet the load were still contracted after the financial
and the required reserve levels. crisis and two (2) other contracts were
still renewed.
Provided by DOE
The recommended action might not be Considering the results of the audit, there
doable as EPIRA already provided for an is a need to negotiate further with the
Interagency Review Committee and IPPs to lower the fees.
submitted its recommendation to
Malacanang on July 2, 2002. The DOE,
46
ADEQUATE CONTRACTED CAPACITY
Provided by PSALM
1. Five (5) plants are located in The alleged looming power shortage in
Mindanao to augment the looming Mindanao was unfounded. These
power shortage. Power supply in contracts were entered into during 1996
Mindanao in 1994 came mostly from to 1998 when the two (2) previously
hydroelectric plants that brownouts contracted IPPs located in Mindanao,
occur in times of low rainfall. NMPC 1 and 2, were reportedly under
extended economic shutdown. This
already manifests excessive available
capacities.
2. Malaya and CBK are existing plants While it is true that CBK is an existing
and should not be considered as plant, its capacity under the contract
additional capacities. increased from 199 MW to 577.10 MW.
4. Five (5) of the IPP Plants, namely Records show that these plants were
Malaya, Subic, Bauang, Limay CC utilized until 2005 and were under
and Cebu GT, were put under preservation since there were already
preservation because they are costly to excess capacities. While under
operate and there is already an excess preservation, NPC continuously pays for
capacity in as much as the projected the IPPs fixed fees.
GDP growth was not attained.
47
Chapter 2
48
REASONABLE CONTRACT ARRANGEMENTS
INTRODUCTION
Under the BOT scheme, the IPPs undertake the construction, operation and
maintenance of the power station, deliver energy to the NPC for a fee over a
fixed term not exceeding 50 years and transfer the ownership of the power
station to NPC upon termination of co-operation period.
Among the fees paid by NPC are capacity fees intended to recover the IPP’s
capital investment. Since the ownership of the power station will be transferred
to NPC at the end of the co-operation period, the total capacity fees for the
duration of the co-operation period are recognized outright in the books of NPC
by a debit to Electric Plant under Capital Lease account and a corresponding
credit to Lease Obligation.
OBSERVATIONS
49
REASONABLE CONTRACT ARRANGEMENTS
On the other hand, while the ownership of the plant will be transferred to
the NPC at the end of co-operation period, there is no warranty that the
plant to be turned over will be in good running condition and could be
operated as intended. While it was provided in two (2) contracts that the
IPPs shall arrange a maintenance schedule which should include a
scheduled overhaul of its power station to be conducted within 12 months
of the transfer date, there was no sanction in the event that this requirement
was not complied with.
As noted, the contract even provides that the power station will be
transferred on an “as is” basis and excludes warranties implied by statute or
otherwise including without limitation, warranties as to title of the property,
fitness for the purpose, the absence of patent or inherent defects, description
or otherwise of whatsoever nature and after the Transfer Date,
CONTRACTOR shall be under no liability whatsoever to NPC in respect of
the operation or otherwise of the Power Station. This provision in effect
negates earlier provision requiring IPPs to transfer to NPC, free from any
lien or encumbrance all rights and title to the plant including all
improvements thereon. In such case, there is no assurance that the power
station to be transferred to NPC would be free from encumbrance and lien
and perform at its guaranteed capacity.
As mentioned earlier, under the BOT scheme, the power stations are in
effect purchased from the IPPs as ownership is transferred to NPC at the
end of the co-operation period and investments of these IPPs were recouped
in the form of fees paid by the NPC.
50
REASONABLE CONTRACT ARRANGEMENTS
It was interesting to note that in the contract with Ilijan Natural Gas Power
Plant, the warranty as to title was not excluded.
The operational capability of the IPPs turned over to NPC between March
2003 and March 2006 could not be tested as these were never used by the
NPC with the following reported status:
Rated Date of
IPP/Power Capacity Turn-
Station (MW) over Status as of March 2006
Navotas I GT 210 3-24-03 No rehabilitation is needed but the plant
Units 1, 2, 3 needs repairs and maintenance at a cost
of P15 million.
The unit is on a “ready to operate”
preservation which means that
commercial operation can be attained
within a month after the conduct of
functional testing, and subject to
availability of operations personnel and
sufficient fuel.
No test was conducted prior to turnover.
The plant was placed under preservation
status since June 26, 2003.
Ormat BGPP 1 4.5 6-30-04 Needs P17.7 million for plants 1 & 2 for
&2 maintenance and repair works.
NMPC 2 40 02-09-06 The plant is on a ready-to-operate status
but will require about P65 million for
the conduct of 16,000 running hours
preventive maintenance covering the 7
units.
51
REASONABLE CONTRACT ARRANGEMENTS
52
REASONABLE CONTRACT ARRANGEMENTS
It is a standard procedure that all IPP While the conduct of tests was
plants under BOT contracts are being considered a standard procedure, the
subjected to Performance Guarantee contract provision excluding the
Tests prior to turn-over to NPC. warranty as to fitness and absence of
Performance tests, technical and defects of the power station would
environmental due diligence were weaken the NPC’s position in case of
conducted on the following IPP plants dispute.
on dates indicated:
53
REASONABLE CONTRACT ARRANGEMENTS
Review of eleven (11) contracts revealed that in seven (7) contracts, the
IPPs were required to transfer to NPC, free from any lien or encumbrance
created by the IPPs and without payment of any compensation, all its rights,
title and interest in and to the fixtures, fittings, plant and equipment
(including test equipment and special tools) and all improvements
comprising the Power Station. It was not clearly provided that spare parts
will likewise be transferred to NPC.
In three (3) other contracts, the transfer of spare parts was clearly provided.
However, these spare parts were not included in the inventories agreed
upon to be transferred to NPC and the IPPs were nonetheless relieved from
liability for any discrepancies between the inventories and the actual
fixtures, fittings, plant and equipment transferred.
The failure to include spare parts among the items to be turned over to NPC
may adversely affect its future operation. This is clearly manifested in the
case of NMPC 1 turned over to NPC on July 31, 2003. The plant was
placed under asset preservation from the time of turn over until January 31,
2004 and resumed operation in February 2004. After the turn-over, only
ten, out of the eleven generating units, were operated as parts of unit 11
were used to operate ten other units due to the absence of spare parts.
54
REASONABLE CONTRACT ARRANGEMENTS
55
REASONABLE CONTRACT ARRANGEMENTS
Downtime Definition
Forced outage - The number of days, hours or kilowatt hours
per unit per year that Contractor is unable to
operate or synchronize the unit to the system
or grid when requested by NPC due to fault
of Contractor. Forced Outage shall not
include any failure to generate due to fault,
negligence, or failure of NPC, fault or a
condition in the transmission line or the grid,
dispatch instructions, insufficient water level
or other force majeure.
56
REASONABLE CONTRACT ARRANGEMENTS
This provision is fair and equitable to If the IPPs were able to deliver more
both parties considering that the reason energy due to savings in maintenance
for the carry over is due to savings in downtime, they were correspondingly
Maintenance Downtime because of the compensated for deliveries in excess of
early completion of the Maintenance the contracted generation. This gives
Schedule, thereby enabling them to more reason not to carry over any
deliver more energy in that particular unutilized downtimes. On the other
period. Utilizing this unused downtime hand, the carried over downtimes may
when the need arises will not put NPC eventually affect the NPC’s operations
on the losing end but will only and still NPC is obligated to pay the
compensate for the savings in the IPPs in full as this now formed part of
preceding year. authorized downtimes.
In addition to this, the use of the This maybe true in the case of
unutilized outage balances cannot be maintenance outage but not in the case
availed of without the approval of NPC of forced outages which could occur
to ensure reliable and adequate supply anytime. In such case, it may affect the
of electricity. NPC’s operation.
57
REASONABLE CONTRACT ARRANGEMENTS
Provided by PSALM
Under the IPP contracts, the plant is either to be constructed on the site
provided by the NPC, IPP or on a leased property with the lease term
coinciding with the co-operation period as in these cases:
Lease Contract
Project/ Plant Project Site Owner/Lessor Entered into by
1. 200 MW (Unit Nos. 1-3) and Phil. Fisheries Development NPC
100 MW, Unit No. 4 Navotas Authority
Gas Turbine Power Station
2. 105 Pinamucan Bunker-fired CHEMPHIL – LMG Inc. IPP
Power Station
3. Subic Bunker-fired Diesel Subic Bay Metropolitan Authority NPC
Power Plant/ENRON II
4. 200 MW Mindanao Coal-fired PHIVIDEC Industrial Authority NPC
Thermal Power Plant
5. 58 and 40 MW (Iligan I & II) IPP – No lease agreement submitted
Diesel Power Station to the team
The audit, however, disclosed that constructing power plants on sites not
owned by the NPC resulted in substantial expenses during and after the
58
REASONABLE CONTRACT ARRANGEMENTS
expiration of co-operation period and negates the benefits under the BOT
scheme as lease contracts provide that any improvements on the leased
property would redound to the landowner. Details follow:
As the contract requires ENRON to provide the site, BPC entered into a
Ground Lease Agreement on September 7, 1992 with Chemphil-LMG
Incorporated for a term of ten (10) years commencing from the
completion of the power station. The annual rental of $260,000 was
payable in advance on the completion date of the power station and is
subject to annual increase of not more than 15% of the annual rent for
the immediately preceding year.
The lease contract entered into by BPC expired on July 21, 2003 and
the NPC entered into extended Ground Lease Agreement on July 25,
2003 with LMG-Chemphil to complete its dismantling, removal and
transfer activities.
59
REASONABLE CONTRACT ARRANGEMENTS
Replacement Appraised
Assets Cost Value
Guardhouse, 8.16m2 P 57,120 P 29,000
Guardhouse, 9.00m2 63,000 32,100
Guardhouse7.50m2 52,500 27,000
Guard Quarters, 30.0m3 210,000 107,100
Perimeter fence 2,198,811 1,121,400
Admin. Building 8,632,000 3,892,300
Car Shed 305,085 155,600
Canteen 1,378,160 702,900
Water Tank T-3001 9,618,180 5,193,800
HFO Tank T-1001A 14,966,380 8,081,800
HFO Tank T-1001B 14,966,380 8,081,000
Impounding Basin 1,000,000 540,000
HFO Unloading Arm 2,000,000 1,080,000
Total P 55,447,616 P 29,044,000
For the dismantling and demolition of the structures in the plant site
and transfer and installation of eight (8) sets of generating units in its
new location in Dingle, Iloilo, NPC entered into contract with Dingle II
Consortium for P629,503,111. As of December 31, 2005, a total of
P629,006,494.52 was already paid to the contractor.
Records show that in its new location, 6 units were operational during
the period April 2005 to February 2006 while two (2) other units were
still unoperational as of October 2006. These units were operated for
only 2.3 to 361 hours a month as illustrated in the next page.
60
REASONABLE CONTRACT ARRANGEMENTS
No. of Hours
Operated
Unit Operation Period From To
1 February to June 2006 12.6 200.6
2 Not yet operational
3 January to June 2006 9.30 282.10
4 January to June 2006 20.60 209.00
5 May to September 2005 8.00 361.00
6 May 2005 to May 2006 2.30 168.50
7 April 2005 to June 2006 48.80 359.70
8 April 2005 to June 2006 17.50 285.30
Particulars Cost
Appraised value of foregone fixed assets P 29,044,000.00
Cash payment to LMG 11,200,000.00
Lease expenses incurred during extension of Ground Lease 16,520,236.34
Agreement
Contract price for the demolition of the foundations and/or 629,503,111.00
footings of certain structures and transfer of 8 sets of diesel
generating units, its auxiliary equipment and other plant
assets from Pinamucan, Batangas to Dingle, Iloilo
Total P 686,267,347.34
61
REASONABLE CONTRACT ARRANGEMENTS
b) The plant site for NMPC 1 & 2 was provided by the IPP,
ALSONS International, Inc. For the use of such site, NPC
agreed to pay ALSONS an amount of P24.643 million for back
rentals. The offer by ALSONS to sell the site to NPC for P 43.4
million is still for consideration by the NPC Board.
On November 19, 1992, another contract was entered into with the
same IPP for the supply of 40 MW bunker-fired diesel generating
power station (NMPC 2 or IDPP 2) incorporating therein the terms and
conditions of the original contract except as otherwise amended
including a co-operation period of twelve (12) years.
Under the agreement, NPC shall provide the site for the purpose of
building and operating the power station at no cost to the contractor.
Apparently, NPC was not able to provide the site and the IPP built the
power plant at its own site.
The project has been transferred to Under this condition, the NPC would
NPC last July 2003. There were no longer have other option but to
62
REASONABLE CONTRACT ARRANGEMENTS
Under the lease contracts, NPC will pay the Lessor monthly rentals
ranging from P722,681.25 to P946,631.40 as tabulated below:
Co-op. Approximate
period rental for the
Power Plant (years) Monthly rental co-op. period Remarks
1. Subic 15 P 900,000 P 162,000,000 Monthly rental of
Bunker- P 9.00/sq. m., of
fired Diesel which P4.50 is
Power shouldered by
Plant/ ENRON, the IPP.
ENRON II
63
REASONABLE CONTRACT ARRANGEMENTS
Co-op. Approximate
period rental for the
Power Plant (years) Monthly rental co-op. period Remarks
2. Navotas I 15 1-5 yr. P 529,200.00 105,099,120 Monthly rental
& II 6-10 yr. 582,120.00 increased from
11-15 yr 640,332.00 P640,332 to
4/05-3/06 946,631.40 P946,631.40
effective April
2005
3. Mindanao 25 Industrial lot P 678,275.00 203,482,500 Industrial lot w/
Coal-fired (annual rental total area of
Thermal P 8,139,300) 542,620 sq. m. at
Power Plant annual rental of
Offshore & foreshore 44,406.25 P15/sq. m. subject
(annual rental to increase upon
P 532,875) ------------- acquisition by the
P 722,681.25 13,321,875 lessor of another
========= lot with an area of
11,586 sq. m.
which will form
part of the leased
land.
Offshore &
foreshore lot with
total area of
213,150 sq. m. at
P2.50/sq. m.
annually
Total P 4 83,903,495
Further review disclosed that at the expiration of the lease contracts, all
permanent improvements will be vested to the lessors, thus, negating
the benefits to be derived under the BOT scheme as illustrated below:
IPP Details/Remarks
1. Subic Bunker- On January 17, 1993, NPC (lessee) entered into a ground lease
fired Diesel Power agreement with Subic Bay Metropolitan Authority (SBMA) for the
Plant lease of a parcel of land with approximate area of ten (10) hectares.
The land shall be used as the site of the plant to be constructed by
ENRON, an IPP with a BOT contract with NPC.
The BOT contract provides that on the transfer date, ENRON shall
transfer to NPC all its right, title and interest in and to the fixtures,
fittings, plant and equipment and all improvements comprising the
power station. The intent of the provision could, however, not be
realized as under Article VI Section 6.1a of the lease contract, all
improvements erected or installed on the leased land by or on
behalf of the lessee and which have been permanently affixed to
the leased land of the facility (the “permanent improvements”)
shall become the property of the lessor. These exclude all
improvements acquired by lessee through its own funds, or funds
of the subtenant, that remain removable from the leased land
(lessee’s improvements) which shall be considered personal
property and shall remain the property of the NPC.
64
REASONABLE CONTRACT ARRANGEMENTS
IPP Details/Remarks
2. Navotas Gas In 1988, NPC entered into IPP contract with Hopewell Project
Turbine Power Management Company Limited for the supply of a gas turbine
Station (Navotas I power station (Navotas I and II Gas Turbine Power Station) on a
& II) build, operate and transfer scheme. For this purpose, NPC entered
into contract with the Philippine Fisheries Development Authority
(PFDA) in 1989 for the lease of 29,400 sq. meters lot for 15 years.
The lease contract was renewed on April 1, 2005 covering one year
period from April 1, 2005 to March 31, 2006. Under the renewed
lease contract, the area covered was only 26,078 sq. meters.
Annual
rental per
Description Area sq. m.
Industrial lot to be used as the 554,206 sq. m. P 15.00
plant site
Offshore and foreshore areas for 213,150 sq. m. 2.50
the construction and use of the
jetty
The two lease contracts provide that upon their termination, the
lessor may retain any and all permanent and/or immovable
improvements on the property without any right on the part of the
lessee to claim for the cost or value of such improvements,
provided that, lessee shall be allowed to remove or otherwise
dispose of the improvements, equipment and facilities.
It was also noted that under the lease contract with the PIA, NPC was
required to pay annual rental within the first 10 days of the first month
of the year which is tantamount to advance payment. Moreover, the
contract provides for one year deposit and one year advance rental
payable upon execution of the agreement.
Thus, for the first year alone, NPC was obligated under the contract to
pay an amount of P26,016,525 representing one year deposit, one year
advance payment and one year annual rental. It would also appear that
the PIA is willing to sell the property as the contract provides an option
for NPC to purchase the site within three years from execution of the
lease agreement with the initial payments to form part of the purchase
65
REASONABLE CONTRACT ARRANGEMENTS
Mindanao CFTPP
The Land Lease Agreement has the provision for
NPC to purchase the project site although at present,
NPC is still leasing the same. Negotiation for the
purchase of the project site in on-going.
On COA’s recommended course of action
66
REASONABLE CONTRACT ARRANGEMENTS
the guaranteed electricity which are being paid for by the NPC.
Payment of IPP fees were supposed to have been based on the
results of tests.
Under NPC contracts with the IPPs, in general, the IPPs are required to
demonstrate the safety and reliability of the power station and its associated
equipment. One way of demonstrating the capability of the plant is through
the conduct of annual testing such as Efficiency, Capacity and Reliability
Tests. The conduct of tests would also provide an opportunity to validate
the nominated capacity of each unit. For each test conducted, the IPP and
NPC are required to issue a joint field certificate attesting to the completion
of such tests.
The team, however, noted that while this is a responsibility of the IPPs, the
costs for conducting these tests were charged to the account of the NPC.
Thus, in most cases, NPC did not strictly enforce or even waived the
conduct of testing when payments of IPP fees were supposed to be based on
the results of test.
Under this condition, there is no assurance that the power station and its
associated equipment were performing within the required performance
parameters. The required testing for each power plant and the reasons for
failure to conduct each tests are discussed below:
Malaya Section 8, Item 3.0 of the contract Plant testing was done only on June 8,
Thermal requires the conduct of performance 1998. No succeeding tests were done on
Plant test of the power complex and its the power plant. Thus, compliance with
equipment to cover boiler efficiency the required heat rate could not be
test; turbine heat rate test; capability established.
test; and auxiliary power consumption
test. NPC is paying for the Energy Minimum
Offtake computed at 70% of the
The Net Guaranteed Heat Rate is Guaranteed Dependable Capacity. If no
required to be maintained under testing was regularly undertaken, the
Section 6.2 of the Contract of Malaya NPC’s basis of payment may not be
I and II following the completion date accurate.
and shall not be greater than the
following heat rate (Btu/Kwh) for The conduct of heat rate tests is likewise
each Unit measured at the site important in the computation of fuel
conditions: consumption. If the unit cannot be
After BTU/KWH operated at full load due to NPC’s fault,
Rehab the basis for computing the fuel
until year Malaya I Malaya II consumption for the said period shall be
5 9900 9600
6 9950 9630
the heat rate value shown on the heat rate
7 10000 9658 curve for the year corresponding to the
8 10050 9687 average load. If the unit was not
9 10100 9716
10 10150 9745
operated at full load due to some
11 10200 9775 technical problems or due to the
contractor’s fault, the basis for
67
REASONABLE CONTRACT ARRANGEMENTS
68
REASONABLE CONTRACT ARRANGEMENTS
Northern Schedule 14.1 provides that the heat NPC-Energy Services Department
Mindanao rate of the power station may be tested informed the team that there was no
Power at the request of NPC not oftener than available data regarding performance
Corporation once in any calendar year, and such testing of NMPC 1 while, there were no
(NMPC) 1 test shall be conducted by the data pertaining to 1996-1998 tests for
and 2 Contractor and witnessed by NPC’s NMPC 2. The last test was conducted on
authorized representative. If the NPC October 19, 2005 as part of the Transfer
test shows that the Guaranteed Heat Technical Due Diligence for NMPC 2.
Rate cannot be met, the contractor is
allowed a period of one (1) month to The absence of data on testing of NMPC
make adjustments and take corrective 1 and 2 during the above-mentioned
measures to ensure that guaranteed years would imply that NPC was not
heat rate is met. If the guaranteed heat validating the reported heat rates of the
rate still cannot be met after the power plants. In such case, the required
Contractor’s test, the contractor shall, corrective actions, should there be any,
at its own expense take corrective had not been undertaken and payment of
measures and inform NPC of its energy fees not accordingly adjusted.
readiness for further tests, provided,
however, that in such event, the
Energy Fees shall be adjusted in
accordance with the computation of
fees, commencing from the date of the
NPC Test until the date the guaranteed
heat rate is met.
Testing of power plants is necessary to ascertain and ensure that they are
safe and operating efficiently and economically at the guaranteed capacity.
Testing is likewise important in order to ascertain the propriety of fees paid
to IPPs which are stipulated to be computed on the basis of test results.
69
REASONABLE CONTRACT ARRANGEMENTS
Today, because of the WESM dispatch Just the same, if the contract would not
regime, all plants are required to be be revised, the NPC would
tested based on the contract provisions. continuously shoulder the testing costs
as stipulated in the contract.
Malaya Thermal PP
Despite this unclear provision, NPC This showed then that test was done
persuaded KEPHILCO to conduct the only after eight (8) years for Malaya
test on both Units of Malaya during the K1 since the last recorded test was
Malampaya Maintenance shutdown done in 1998. Despite the absence of
from Nov. 22 - Dec. 16, 2006. Malaya test, NPC was continuously paying the
K1 passed the test but Malaya K2 was IPP based on contracted capacity.
not subjected to the same test due to During CYs 2000 to 2004, these units
run out of bunker fuel. generated only about 15% to 38% of
their annual guaranteed generation.
Both units however showed they can
still operate at full load when they were
dispatch at rated capacity to augment
the power supply in Luzon Grid during
the Malampaya Maintenance
shutdown.
70
REASONABLE CONTRACT ARRANGEMENTS
The performance testing was conducted This is precisely the point. Due to
until 1997 on Block A and 1999 on expensive costs of testing, NPC is
Block B. However, the conduct of constrained to waive the conduct of the
Post-C Inspection Performance Test on same. Considering that plants, by
Block A and B was waived by NPC nature, is subject to deterioration and
since 1999 (Please refer to Attachment de-rating, it could not be assumed that
“1”). An estimated cost of P8 Million the results of testing in 1997 or 1999
(less net revenue from the dispatched are still true in 2004 or 2005. It maybe
energy) is needed to complete a Post-C true that previous performance tests
inspection performance test of a conducted in 1997 and 1999 did not
combined cycle block. With this cost reflect any deviation. This is expected
involved, there was a need to further considering that these plants are
evaluate the benefits that NPC would relatively new at that time as these
derive in the conduct of such test in the were commercially operated only in
future. As per contract, the test is 1994.
intended only as basis for NPC whether
or not to grant bonus to Alstom if the
net heat rate results are lower than
1.03% of the guaranteed heat rate or for
Alstom to compensate NPC if the
results are higher than 1.03%. Based on
the information gathered, there had
been no instances during the past PTs
that either NPC was compensated or
Alstom charged bonus as a result of
deviations or conformance to net heat
rate guarantee.
71
REASONABLE CONTRACT ARRANGEMENTS
NPC and PSALM (as IPP traders) are A great portion of performance test
now requiring performance tests of costs is fuel cost which is shouldered
IPPs as mandated by WESM. The only by NPC. This is precisely the reason
cost to NPC during performance test of why NPC waived the conduct of tests
IPPs is the fuel cost net of revenue in some cases.
from the generated power.
Provided by TRANSCO
While it is true that performance tests The team recognizes the importance of
are chargeable to the account of NPC, the conduct of performance test as this
such test will prove that nominations is practically the only way to prove that
can be delivered by the plant/unit the plant would be able to deliver the
which in turn shall be the basis of contracted capacity aside from
capacity fee. NPC has the option to dispatching the same at its full
waive these tests if, in its evaluation, capacity. Since it is the responsibility
the conduct of these tests would be of the IPPs to demonstrate their plants’
costly on its part like the case of oil- capability to produce the
based power plants. contracted/guaranteed capacity, such
tests should be charged to the IPPs and
not to the NPC. As it is, NPC had to
waive the conduct of the test due to
expensive costs of testing.
72
REASONABLE CONTRACT ARRANGEMENTS
If the IPP contract is silent on who will It would be of great help to the
shoulder the costs of the performance government and the consumers as well
and other unit tests, then it is our if the NPC and TRANSCO would work
opinion that the energy delivered for this.
resulting from the tests can be made
free of charge to NPC. This
arrangement will ensure that the IPP
will conduct the tests judiciously.
Provided by PSALM
NPC is only responsible for the supply Unfortunately, the cost of fuel which
of fuel during the conduct of the annual represents the biggest cost in the
performance guarantee test of the IPP conduct of performance test is the one
plants. All other costs relative to the being shouldered by NPC. For this
tests such as calibration of instruments reason, NPC at times waived the
(except the billing meter) and other conduct of tests.
administrative costs are for the account
of the IPP sponsors.
Performance tests for some IPP plants The irregular conduct of performance
such as Malaya, Subic, Bauang, Limay test due to the very high cost of fuel
CC and Salcon Land-based GT are not may prove disadvantageous to NPC as
being conducted on a regular basis due it may be paying for guaranteed energy
to the very high cost of fuel of said which the plants are not capable of
plants. Anyway, these plants are on producing. Moreover, while these
economic shutdown. plants are on economic shutdown, NPC
continuously pays fixed fees as
provided in the contract.
Provided by DOE
73
Chapter 3
74
EFFICIENT FUEL MANAGEMENT
INTRODUCTION
It is the declared policy of the State that all resources of the government shall be
managed, expended or utilized in accordance with law and regulations, and
safeguarded against loss or wastage through illegal or improper disposition,
with a view to ensuring efficiency, economy and effectiveness in the operations
of government (Section 2, PD 1445). It is therefore, imperative for government
units to apply control measures that are geared towards attainment of efficient,
economic and effective operations. Such measures may be incorporated in the
agency’s policies, regulations, standard operating procedures and contracts
entered into.
Under NPC’s contracts with IPPs, NPC is under obligation to supply fuel to
IPPs for the generation of electricity, start up and shutdown cycles or
conversion into electricity in the case of Energy Conversion Agreements. For
this purpose, NPC entered into contracts with various oil companies to deliver
fuel to the concerned IPPs. For the period January 2004 to June 2005 alone,
NPC spent about P 35.73 billion for fuel supplied to IPPs.
As provided for in the ECA, the fuel to be supplied by the NPC would be based
on forecasted fuel needs to be submitted by the concerned IPPs. The team,
however, noted that apparently, NPC entered into contracts with various oil
companies for the delivery of fuel prior to determination of the actual needs
resulting in increasing inventory of fuel materials and supplies in the past three
years which accumulated to P34 billion as of December 2005.
OBSERVATIONS
75
EFFICIENT FUEL MANAGEMENT
It was further provided under Article 6.1.b that KEILCO shall only use
natural gas to test and operate the power station, except to the extent that
the NPC otherwise requires the use of diesel fuel to test the performance of
the power station using diesel fuel.
The team, however, noted that while fuel requirements was not yet
established and still dependent on the generation forecasts, NPC already
entered into Gas Sale and Purchase Agreement (GSPA) on December 30,
1997 with Shell Philippines Exploration B.V and Occidental Philippines,
Inc. (Shell/Oxy), the Service Contractor, for the purchase of Natural Gas
from its Reservoir for the 1200 MW Ilijan Power Plant for a period of 20
years. The fuel requirements should be prepared in accordance with the
FSMA. The FSMA was entered into only in November 2000 which
requires KEILCO, among others, to submit to NPC, monthly estimates of
Natural Gas and Diesel fuel usage for commissioning and testing of the
power station, complete tests and Annual Fuel Forecast.
The GSPA provided, among others, that NPC shall pay for 164 TJ Daily
Contracted Take-or-Pay Natural Gas tendered for delivery by the Sellers,
whether taken by NPC or not. The contracted volume was adjusted yearly
by the volume properly nominated by NPC but was not delivered by
Shell/Oxy. The contracted take-or-pay quantity for CYs 2002-2005 follow:
Contracted Quantity/Take-or-pay
Year quantity ( in GJ )
2002 59,860,000
2003 59,860,000
2004 60,024,000
2005 59,860,000
76
EFFICIENT FUEL MANAGEMENT
Evaluation revealed that the annual natural gas contracted quantities for the
four-year period were 141.01% to 194.57% of the forecasted requirements
and 122.42 % to 191.23% of the actual consumption as illustrated below:
IN GIGAJOULES
Monthly Contracted Qty Actual Excess
Contracted Forecasted as % of Deliveries/ Contracted Contracted Qty
Quantity Quantity forecast Consumption Quantity as % of actual
Month
(A) (B) (A/B) (C) (A-C) (A/C)
* 2002
77
EFFICIENT FUEL MANAGEMENT
IN GIGAJOULES
Monthly Contracted Qty Actual Excess
Contracted Forecasted as % of Deliveries/ Contracted Contracted Qty
Quantity Quantity forecast Consumption Quantity as % of actual
Month
(A) (B) (A/B) (C) (A-C) (A/C)
* Based on forecasted generation as per Approved Operating Budget Monthly Details for FY 2002 and FY 2004
Forecasted quantities for the first six months of CY 2002 not available
It may even be noted that while the contracted quantities could no longer be
consumed, NPC did not negotiate for the reduction in contracted quantity.
This then resulted in increasing investment in stored fuel for the three year
period which was valued at P31.280 billion in 2005 as illustrated below:
78
EFFICIENT FUEL MANAGEMENT
The NPC’s obligation under this contract was guaranteed by the National
Government. In the event of NPC’s failure to honor its obligations, the
corresponding amount is deducted by the Shell/Oxy from its dues to the
Department of Energy (DOE) representing the share of the Government
from the net proceeds or Quarterly Assigned Petroleum Amount from
Malampaya. As of December 2005, NPC’s liability to DOE amounting to
P5.438 billion is recorded in the books of the NPC as part of “Due to the
Philippine Government and its Agencies.”
In the event that the Net Government Share in a given Contract Year is still
insufficient to pay for the Natural Gas, NPC is authorized under Section 4
of Administrative Order (AO) No. 381 dated February 17, 1998 to avail
itself of the Deferred Payment Facility. As disclosed in the report of the
IPPCM-South Luzon Operation, NPC was granted a deferred payment
facility by Shell Philippines Exploration, B.V., (SPEV), et.al. of US$350
million, of which US$295.89 million was already availed of by NPC as of
December 31, 2005. All charges to the said facility is due and payable on
December 31, 2009.
It was further provided in the AO that in the event that these amounts are
still not sufficient, the balance due to the Sellers under the Performance
Undertaking shall be paid from any available government sources or funds.
The GSPA required NPC to consume It would appear then that the NPC
the 164TJ Daily Contracted Quantity proceeded in contracting 164TJ of
(DCQ) which is based on 80% capacity natural gas on December 30, 1997
utilization of the 1200MW ICCPP. The based on the 80% capacity utilization
GSPA was executed prior to NPC of the plant despite constraint in the
entering into an ECA with KEILCO. Biňan-Dasmariňas line. This deficiency
The ECA will support the viability of was claimed to have been corrected
the Malampaya Gas Project of the only in February 2005. It is worthy to
Government. The estimated 80% mention that during the period 2002 to
capacity utilization throughout the 2005, the plant is operating only from
Cooperation Period is just proper and 30% to 45% of its guaranteed
attainable since ICCPP is designed to generation.
operate as a base load plant hence, the
164TJ DCQ is a reasonable estimate of
the daily fuel requirements of the plant
79
EFFICIENT FUEL MANAGEMENT
Lastly, the difference between the As provided under Article 9.3, the
contracted quantity and the actual cost of excess contracted quantity may
volume of natural gas delivered to NPC only be recovered in the event that
(Stored Fuel) can still be recovered actual consumption for the year
pursuant to Article 9.3(1) and 9.4 of the exceeded the annual contracted
GSPA. quantity. As discussed earlier, annual
consumption ranged only from 30% to
45% of the annual contracted quantity.
The bases of the amounts indicated for These were the amounts reflected in the
accumulated stored fuel (P 31.2 NPC’s financial statement as of
Billion) and fuel inventories (P2.113 December 31, 2005.
Billion) as of 31 December 2005, need
to be clarified and validated.
80
EFFICIENT FUEL MANAGEMENT
81
EFFICIENT FUEL MANAGEMENT
Records show that contracts for the supply of fuel and diesel oils to IPPs
with existing Energy Conversion Agreements with NPC covering the
period January 1 to December 31, 2004 were awarded to Petron Corp. and
Pilipinas Shell Petroleum Corp. in the total amount of P2.31 billion.
Analysis, however, revealed that of the total amount, P2.113 billion were
intended for IPPs without forecasted fuel requirements, and in most cases,
not also included in the Annual Procurement Plan as tabulated below:
Contracted Qty
(in kiloliters)
Plant/Barge Total Remarks
Fuel
Diesel Contract
Oil
Cost
Petron Corporation
1. Bataan CCPP 3,956 35,733 P 841,847,901 Diesel not included in both forecasted fuel requirements and
Annual Procurement Plan (APP). Fuel oil not included in the
forecasted fuel requirement but included in the APP.
2. Subic II DP 413 367 10,332,431 Diesel not included in the APP but included in the forecasted fuel
requirements. Fuel oil not included in the forecasted fuel
requirement but included in the APP.
3. Ogden-Edison DP 562 647 14,375,420 Diesel and fuel oil not included in both forecasted fuel
4. Sual CFTPP 298 5,749 57,371,218 requirements and APP.
5. Pagbilao CFTPP 9,600 - 140,678,385 Diesel not included both in the forecasted fuel requirement and
6. Ilijan NGPP 17,741 - 256,048,550 APP.
7. Rosario DP(MCI) - 62,929 751,798,852 Fuel oil not included in the forecasted fuel requirements but
included in the APP.
Sub-total 34,575 510,708 P2,072,452,757
Current Assets
Materials and Supplies for operation
Fuel Oil P 615,123,621 P 1,007,837,067 P 872,331,971
Coal 231,607,383 643,343,255 992,181,202
Diesel Oil 184,909,817 339,907,857 732,847,827
Thermal Chemicals 42,425,378 45,918,381 57,032,101
Total P 1,074,066,199 P 2,037,006,560 P 2,654,393,101
As the fuels contracted were not needed, these were transferred to other
IPPs with likewise no need for the same as discussed in the next page.
82
EFFICIENT FUEL MANAGEMENT
IPP Particulars
Ilijan Natural It may be noted that the main fuel of this plant is natural gas. Diesel is required
Gas Power only for start-up and for testing performance of the power station as may be
Plant (NGPP) required by the NPC. However, as reflected in the schedule, NPC entered into
contract with Petron Corp. on June 7, 2004 for the supply of 17,741,000 liters of
diesel for the period March to December 31, 2004 for a contract price of
P256,048,550 on consignment basis.
Further evaluation revealed that before this contract was entered into, Ilijan
NGPP has inventory balance of 23,420,525 liters of diesel as of May 25, 2004
broken down into:
Quantity
Particulars
(in liters)
NPC stocks out of terminated contracts 15,120,414
stored at the IPP fuel tanks
Balances from deliveries as of May 25, 2004 8,300,111
charged against contracts entered into on
July 4, 2002 and valid until June 30, 2004
with option to extend as mutually agreed
upon
Total 23,420,525
Since Ilijan NGPP has no need for additional fuel, deliveries during the billing
period October 25 to November 25, 2004 were diverted to another IPP, the
Bataan Combined Cycle Power Plant (BCCPP) with likewise substantial
inventory balances as of October 25, 2004 of 5,565,901 liters. This inventory is
also more than the needs of BCCPP. Thus, the diverted deliveries now formed
part of its existing inventory as of April 2005 of 6,886,854 as illustrated
below:
In Liters
Drawdowns=
Consumption
Inventory, +Used for Inventory,
Billing Period Beginning Deliveries blending Ending
10/25/04-11/25/04 5,565,901.11 4,719,572.48 2,578,941.28 7,706,532.31
11/25/04-12/25/04 7,706,532.31 - 746,831.06 6,959,701.25
12/26/04-12/25/04 6,959,701.25 - - 6,959,701.25
01/01-01/25/05 6,959,701.25 - 18,382.36 6,941,318.89
01/26/05-02/25/05 6,941,318.89 - 23,902.52 6,917,416.37
02/26/05-03/25/05 6,917,416.37 - 5,906.17 6,911,510.20
03/26/05-04/25/05 6,911,510.20 - 24,655.68 6,886,854.52
Meanwhile, out of the total inventory balance of Ilijan NGPP as of June 25,
2004 of 23,420,525, only 154,440 liters were consumed as of January 25, 2005
as tabulated below:
In Liters
Drawdowns =
Inventory, Consumptions + Inventory,
Billing Period Beginning Used for blending Ending
6/25/04-7/25/04 23,480,525 21,274 23,459,251
7/25/04-8/25/04 23,459,251 5,941 23,453,310
08/25/04-09/25/04 23,453,310 26,119 23,427,191
83
EFFICIENT FUEL MANAGEMENT
IPP Particulars
Rosario Diesel There was no forecasted fuel oil requirement for MCI in CY 2004. However, in
Power Plant or the APP, it was indicated that the IPP has fuel oil requirement of 52,441,000
Magellan liters. While the quantity indicated in the APP was only 52,441,000 liters, NPC
Cogeneration entered into contract with Petron on August 9, 2004 for the supply of 62,929,000
Inc. (MCI) liters which is 10,488,000 liters higher than what was indicated in the APP. Of
the total quantity contracted, 6,736,060 liters were delivered between July 9,
2004 to August 8, 2004 or prior to the signing of the 2004 contract.
It was further noted that fuel deliveries under this contract during CY 2004 were
consumed by the MCI to generate energy delivered to its other customers as
tabulated below:
2004
Sual Coal- While there was no forecasted requirement and programmed procurement for
Fired Power diesel and fuel oil in CY 2004 for Sual CFPP, NPC entered into contract with
Plant (CFPP) Petron on June 7, 2004 for the supply of 298 and 5,749 kiloliters of diesel and
fuel oil, respectively, covering the period March to December 31, 2004.
Records show that prior to the signing of this contract on May 25, 2004, NPC
has existing contract for the supply of fuel oil to Sual CFPP and inventories as
tabulated below:
Quantity
Particulars (in liters)
NPC stocks out of terminated contracts stored
at the IPP fuel tanks 1,886,956.30
Delivery as of May 25, 2004 out of contracts
entered into on July 4, 2002 and valid until 1,415,043.32
June 30, 2004 with option to extend as
mutually agreed upon.
Total 3,301,999.62
While the contract with Petron was on consignment basis, NPC was obligated
under the contract to pay all unconsumed fuels at the end of the contract period
with total quantities of 1,544,235.73 liters amounting to P19,148,831.90. This
resulted in accumulated balance of 3,308,448.76 liters as of April 25, 2005.
84
EFFICIENT FUEL MANAGEMENT
NPC is not in the practice of entering The audit disclosed that the GSPA
into supply contracts with the oil fixing the minimum quantity of natural
companies without prior determination gas to be purchased was entered into on
and approval of its fuel requirements. December 30, 1997, way ahead the
The quantity for procurement is based FSMA which was only entered into in
on the generation and fuel consumption November 2000. The estimated gas and
forecast provided by the Power diesel fuel consumption then was
Economics Department and the established only in 2000.
approved Fuel Procurement Plan.
Documents provided to the team also
disclosed that contracts for P2.113
billion were intended for nine (9) other
IPPs with either no forecasted fuel
requirement (not included in the fuel
consumption forecast) or not included
in the Annual Procurement Plan or
both.
On COA’s recommended course of
action
NPC had already conducted actual It would appear then that while NPC
transfer of fuel stock from a was aware that additional costs, in
decommissioned power plant to an addition to carrying costs, would still
operating power plant. NPC entailed be incurred in transferring excess fuel
additional cost for hauling and from one plant to another, still it is not
provisions for loading equipment and prudent enough to ensure that only
facilities required for the withdrawal of needed fuel is contracted.
fuel from the decommissioned plant.
Oil-based fuel presently stored at the This condition could have made NPC
IPPs storage tank can not be easily more prudent in its actions.
transferred to other IPP or NPC power
plants due to the absence of the loading
equipment and facilities. Installation of
this equipment and facilities may also
cause disruption in plant operations.
Technically, the transfer of fuel is
feasible but with cost as mentioned.
NPC’s fuel supply contracts with the This only shows that NPC was aware
oil companies already provide the that the contracted quantities would
transfer of fuel stock allocation from exceed the plants requirements.
one power plant to another for Instead of providing transfer of fuel
operational flexibility. The unlifted stock allocation from one power plant
volume of fuel from one plant can be to another, NPC should exercise
allocated to another plant in order to prudence in estimating the fuel needs
meet its fuel requirement. and in entering into contract.
85
EFFICIENT FUEL MANAGEMENT
86
EFFICIENT FUEL MANAGEMENT
It was also noted that the 800 liters prescribed limitations for each start-up
and shutdown cycles for each generating unit in four (4) IPPs with different
capacities and heat rates could not be considered reasonable as these would
affect fuel utilization:
The rated capacity and heat rate of a generating unit have bearing on fuel
consumption. Such being the case, fuel consumption of the above-
mentioned generating units for each start-up and shutdown cycle should not
be the same and vary from unit to unit. Allowing a maximum of 800 liters
for each start-up and shutdown cycle per unit without regard to its heat rate
or rated capacity is not also beneficial to the government. This manifests
absence of a policy in setting allowable limit of fuel for these activities.
87
EFFICIENT FUEL MANAGEMENT
The IPP contracts already provide As discussed in the report, seven (7)
limitation on the fuel used for activities contracts have either no Fuel Supply
without energy generation. NPC will Management Agreement (FSMA) or
enforce close monitoring on with FSMA but have no limitations
compliance with this provision. provided therein or in the contract.
88
EFFICIENT FUEL MANAGEMENT
The NPC’s Energy Conversion Agreement (ECA) with the MCI was
entered into on September 23, 1993. This was followed by an FSMA
entered into on July 14, 1994 which provides that NPC will supply fuel not
only to be used by MCI for conversion into energy to be supplied to NPC
but likewise with its other client, the Cavite Export Processing Zone
Authority (CEPZA). The fuel used by MCI to address the needs of its other
client will be deducted from its billing to NPC. In effect then, NPC would
be supporting the operations of MCI to meet its commitment to deliver the
power requirements of CEPZA.
This provision is actually not in accordance with Article 2.9 of the ECA
which provides that the fuel to be supplied by NPC should not include the
fuel to be used to meet MCI’s obligation to CEPZA as this is supposed to
be provided by MCI or CEPZA.
During CYs 2004 and 2005, out of the total MCI fuel consumption of
130,726,734 liters, only 2,848,495 liters were used to deliver energy to
NPC as tabulated below:
89
EFFICIENT FUEL MANAGEMENT
Apparently, the costs of energy delivered by MCI to NPC are not even
enough to pay the cost of fuel delivered by NPC to MCI for conversion into
energy delivered to CEPZA. Thus, as of July 2006, NPC’s records revealed
that receivable from MCI is now valued at P656.186 million. It maybe
mentioned that the NPC’s operation is funded from loans, part of which
was already assumed by the national government.
NPC has a pending case with Magellan As it is, it would still take time before
Cogeneration Inc. (MCI) on this NPC can recover from the MCI.
matter. Meanwhile, the government shoulders
the repayment of loans used to finance
the operations of NPC.
5. The minimum inventory levels set for seven (7) IPPs were way beyond the
IPPs’ actual requirements resulting in accumulation of fuel inventories.
These are good for 6 to as long as 686 months consumption.
90
EFFICIENT FUEL MANAGEMENT
required to maintain minimum inventory levels of fuel oil and diesel at the
IPPs in the following quantities:
1. Malaya TPP 35,771,000 Not specified The minimum inventory level for fuel oil
was set at 35.77 M liters for contract year
July 2002 to Dec. 2003. There were no
specified inventory levels for fuel oil for
the contract years 2004 to 2005.
2. PB 117 3,500.000 200,000 Same level of minimum inventory level set
for fuel and diesel oil through out the
3. PB 118 3,500,000 200,000
period.
4. Bauang Diesel 16,000,000 202,000 From Aug to Sept 2005, the minimum
inventory levels for fuel and diesel oil were
not specified.
5. Subic II DPP 10,400,000 114,000 Same level of minimum inventory set for
fuel and diesel oil throughout the period.
6. Ogden-Edison DPP 4,740,000 141,000 No minimum inventory level specified for
the period Aug to Sept 2005.
7. Sual CFTPP 2,400,000 680,000 Same level of minimum inventory set for
fuel and diesel through out the period
8. Rosario DPP 1,300,000 No contract No changes in the setting of minimum
inventory level for the 3 year period.
9. Ilijan CCPP Not specified 17,118,000 Same level for diesel oil set throughout the
period
10. SPPC 3,000,000 32,000 Same level throughout the period set for
fuel and diesel oil.
Fuel Oil:
PB 117 3,500,000 8,387,875.73 11,281,813.11 0.41 0.36 0.31 0.37
PB 118 3,500,000 9,034,093.87 11,856,679.14 0.35 0.36 0.30 0.39
Bauang Diesel 16,000,000 714,369.96 4,314,010.38 3.71 4.05 22.40 16.36
Subic II DPP 10,400,000 448,003.82 4,481,431.98 2.62 2.32 10.07 23.21
Ogden-Edison DPP 4,740,000 *2,430,413.38 2,609,094.36 1.82 1.95 - -
Sual CFTPP 2,400,000 366,720.59 561,119.76 6.06 4.28 6.54 4.61
Rosario DPP 1,300,000 5,827,018.33 7,252,998.58 0.18 0.18 0.22 -
SPPC 3,000,000 3,731,028.00 6,537,543.52 0.70 0.66 0.45 0.80
Malaya TPP 35,771,000 1,685,156.67 25,157,690.17 1.80 1.42 21.33 13.86
Diesel Oil
PB 117 200,000 730.07 24,405.94 8.19 29.42 273.95 225.40
PB 118 200,000 3,475.04 44,358.87 4.51 12.78 57.55 21.38
Bauang Diesel 202,000 47,746.24 201,516.51 1.00 1.02 4.23 3.51
Subic II DPP 114,000 16,675.73 125,001.69 1.10 0.91 2.00 6.84
Ogden-Edison DPP 141,000 47,372.41 *29,161.16 2.98 4.84 - -
Sual CFTPP 680,000 4,542.22 12,452.38 54.61 149.71 116.98 73.31
Ilijan NatGas PP 17,118,000 24,970.00 106,063.33 293.58 685.54 161.98 73.31
SPPC 32,000 2,724.28 8,398.71 11.75 6.46 4.05 3.81
Legend:
* - Co-operation period ended June 24, 2004
91
EFFICIENT FUEL MANAGEMENT
Ilijan CCPP – The 17,188,000 liters Considering that Ilijan plant could no
minimum fuel inventory level longer consume /make use of the
consumable in 686 months as available natural gas, there is no need
reported by COA seems to be to maintain contingency fuel of this
computed based on the actual fuel magnitude. Moreover, records would
consumption of the plant during show that from January 2003 to June
start up and operation without 2006, average monthly fuel
generation against the same consumption ranged only from 24,970
inventory level at the Ilijan CCPP to 106,063 liters.
fuel storage tank. This should not be
the case since the inventory level is
being maintained as a contingency
measure computed at full load in
case natural gas is unavailable.
Based on this condition and
considering that Ilijan CCPP has a
consumption rate of 3.9M liters/day
at 1200MW, the minimum stock
level of 17,118,000 liters of diesel
fuel will only last for about 5 days.
In the case of Fuel Oil, used as main As discussed earlier, Subic II was
fuel of oil-fired IPP power plants, among those IPPs without fuel
the inventory levels are reasonable requirements for CY 2002, yet included
92
EFFICIENT FUEL MANAGEMENT
With regard to Sual CFTPP, whose Apparently, while fuel oil and diesel
main fuel is coal, Fuel Oil and would be used only as start-up fuel,
Diesel are for low load and start-up substantial quantities were required to
fuel of the plant, respectively. be maintained.
Depending on actual dispatch, low
load and start-up fuel consumption
may increase or decrease
accordingly. Except for Ilijan
NGPP, Diesel Fuel is used as start-
up fuel of the IPP plants. However,
Ilijan NGPP requires Diesel Fuel as
an alternative fuel in case of non-
availability of its main fuel, Natural
Gas. NPC has a contractual
obligation to the operator of the
plant to provide the alternative fuel
that is sufficient to sustain operation
for five (5) consecutive days at full
load. Hence, the considerably high
inventory level.
We wish to inform you that the The team recognized that these factors
minimum inventory level should not would affect the inventory level.
be based on the plants’ average However, as discussed in the report,
monthly consumption alone. Other even the IPPs without fuel
factors should also be considered, requirements, which maybe due to
such as: accumulated inventories, were still
included in the contract for the supply
a) Procurement lead time from of additional fuel. This is the main
advertisement to contract approval. In
93
EFFICIENT FUEL MANAGEMENT
94
Part V
Recommendations
95
RECOMMENDATIONS
RECOMMENDATIONS
To remedy the deficiencies noted, the team recommends the following courses
of action for consideration by the NPC:
1. Further negotiate with the IPPs to lower the fees considering NPC’s
financial condition at present, percentage of power plant utilization and
the IPPs responsibility under the contract to demonstrate the plants’
capability to provide the guaranteed capacity/energy.
3. Ensure that the power plants to be transferred are free from any liens
and encumbrances created by the IPP.
7. Require the conduct of test considering that payment of fees are based
on guaranteed capacities which could only be established through tests.
The cost of performance test should be shouldered by the IPP.
8. Stop the practice of entering into contracts with oil companies without
first determining the fuel needs. Considering the accumulated stored
fuel of P31.2 billion and fuel inventories of P2.113 billion as of
December 31, 2005, reduce the contracted take-or-pay quantity of
natural gas and all types of fuel to quantities actually needed as
determined from historical records.
96
RECOMMENDATIONS
97
Submitted in compliance with MS/TS Office Order Nos. 2005-036 and 2005-
036A dated July 6 and November 11, 2005, respectively.
Reviewed by:
Approved by:
98