ENERGY SECTOR, TRANSFORMER WORKS Page 1 of 2

Customer: REC Power Development & Consultancy


Preliminary detailed Test plan for Sl. No. I300306-01
LTD Final Test: xx.xx.xxxx to xx.xx.xxxx
Routine and Type Tests
Rating: 8.33MVAr, 245/√3kV, 1-Φ Shunt Reactor Day Day 1 Day 2 Day 3 Day 4 Day 5
Reference standard: IEC 60076-6 and Customer’s Specifications Date xx.xx.xxxx xx.xx.xxxx xx.xx.xxxx xx.xx.xxxx xx.xx.xxxx
Seq. Tests according to Inspection and Test Plan Time 0900-2000 0900-2000 0900-0000 0000-2200 0900-2100
1. Oil BDV, Moisture Content, & DGA prior to all tests(1) Routine X
2. Check on CTs ratio and polarity Internal X
3. Measurement of winding resistance Routine X
4. 2kVAC Voltage withstand test between core, frame and earth for 1 minute Routine X
5. Meas. of Insulation resistance between core, frame and earth for 1 minute at 2kVDC. Routine X
6. Measurement of Insulation Resistance and Polarization Index Routine X
7. Measurement of Capacitance and Tan delta of Winding and Bushings at 5kV & 10kV Routine X
Knee point voltage meas of Reactor upto 1.5pu by DC charging-discharging method
8. Type X
In cold state
9. Full Wave Lightning Impulse Voltage withstand test on Neutral Routine X X
10. Full Wave lightning impulse with Chopped Wave Lightning Impulse test on Line terminals Routine X
11. Switching Impulse Voltage withstand test Routine X
12. Applied voltage test for 1 minute Routine X
13. Induced Over Voltage test with Partial Discharge measurement IVPD test Routine X
14. Dissolved Gas Analysis after dielectric and before temperature rise test (2) Routine X
15. Measurement of Reactance & loss at 90, 100 and 110% of Rated Voltage in cold State Routine X
16. Measurement of harmonics content of current at 245/√3kV Type X
17. Measurement of acoustic sound level in cold state at 245/√3kV in cold state Type X
18. Measurement of vibration in tank stress cold state at 245/√3kV (1.0 p.u.) Routine X
19. Measurement of vibration and tank stress in cold state at 269.5/√3kV (1.1 p.u.) Type X
Temperature Rise Test at 245/√3kV for 24 Hours
20. Type X X
(Thermal images Thermal images -start, 4 more times during test, steady state)
21. Meas. of Vibration and Tank Stress in hot state at 245/√3kV (1.0 p.u.) Type X
22. Measurement of Reactance and loss at 90, 100 and 110% of Rated Voltage in hot state Type X
23. Measurement of vibration and tank stress in hot state at 269.5/√3kV (1.1 p.u.) Type X
24. Measurement of Acoustic Sound Level at 245/√3 kV in hot state Type X
25. Dissolved Gas Analysis after Temperature Rise Test (3) Type X
26. Oil Leakage Test on Reactor tank Routine X X
27. Frequency Response Analysis test with oil Routine X
28. Dimensional & visual inspection of Reactor Routine X
29. Functional checks on Control Panels, accessories and protective devices and 2.0 kV test. Routine X
30. Test Report Signing Routine X
31. Tank vacuum test -Suppler test report Review X

Form No. EM-TR/QT/FR/22 Rev No:00 Date: 22.07.2016


ENERGY SECTOR, TRANSFORMER WORKS Page 2 of 2
Customer: REC Power Development & Consultancy
Preliminary detailed Test plan for Sl. No. I300306-01
LTD Final Test: xx.xx.xxxx to xx.xx.xxxx
Routine and Type Tests
Rating: 8.33MVAr, 245/√3kV, 1-Φ Shunt Reactor Day Day 1 Day 2 Day 3 Day 4 Day 5
Reference standard: IEC 60076-6 and Customer’s Specifications Date xx.xx.xxxx xx.xx.xxxx xx.xx.xxxx xx.xx.xxxx xx.xx.xxxx
Seq. Tests according to Inspection and Test Plan Time 0900-2000 0900-2000 0900-0000 0000-2200 0900-2100
32. Tank pressure test- Suppler test report Review X
33. Frequency Response Analysis test without oil Routine
Rev. 00 Test Plan according to: Technical specification of bus reactor up to 400kV Reactor and IEC 60076
Date:17.12.2021 Prepared By: Amol Mane

Note: Test Plan may change based on Manpower and Machine Availability.

Form No. EM-TR/QT/FR/22 Rev No:00 Date: 22.07.2016