Customer Interfacing Work For Boiler - Indorama - 28 July 2023

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

No.

Item / Picture Categorize Interface Description of Remain Action Status Remark


Gas flow meter already install by customer. Customer will dismantle gas flow meter.

Wiring from Gas flow meter to Boiler panel not Thermax will give recommendation for Piping
yet finish gas flow meter.
After Indorama finish piping work, thenm gas
Customer & flow meter can install and wiring to Boiler Panel.
1 Boiler/ Gas Pipe
Thermax And Gas flow meter Thermax already onsite.

Over Flow & Drain FWT not yet done AS per discuss & As per contract for this
overflow is Indorama scope. Will done at Monday
2 August 2023

2 FWT Customer Scope

Blow down line, end connection not yet finalise Already coordinate will go trow Pit near Bpoler
for the final end line house as photograph
Piping keep it near building with proper support

Thermax will done it , max at Monday 31 July


Boiler / Piping 2023
3 Thermax
Blow down

Cable Grounding Not yet pulling As per discussion, Electrical can use common
earthing pit near genset
Position of Pit Need to be Check with customer For Intrument earthing will provide by customer.
Under 1 Ohm for resistance max at 2 August
2023

Need 2 Pit : For Electrical & Electronic that After that grounding can be pulled and
Customer & customer scope terminations.
4 Boiler Electrical
Thermax
Termination from panel to pit will be by Thermax
No. Item / Picture Categorize Interface Description of Remain Action Status Remark
Power for Thermowiz panel not yet done by Customer confirm, will ready max in Monday 31
customer July 2023

5 Boiler Electrical Customer Scope

Condensate return line from customer not yet Already done


finish Close

Boiler / Feed
6 Customer Scope
Water

Pressure gauge not yet install for gas line by Customer confirm, will ready max in Monday 31
Customer July 2023

7 Gas Line Customer Scope

Solenoid valve not yet install then connect to Customer confirm, will ready max in Monday 2
Panel Boiler for Make up supply Feed Water Line August 2023

8 Customer Scope
No. Item / Picture Categorize Interface Description of Remain Action Status Remark
Gas line pipe to Thermix not yet finish Thermax to finish install Gas Train by max 31
July 2023, Then customer will finish it max at
Monday 1 August 2023

9 Customer Scope

Compressed air not yet ready Customer confirm, will ready max in Monday 31
July 2023

10 Customer Scope