The Correction
Corrective Action Taken
Check those actions taken to prevent recurrence. Fill in the appropriate box for corrective actions decided upon or planned by not yet
initiated or completed.
1. Reinstructed of those involved 8. Action to improve clean-up 15. Correction of necessary congestion
2. Reprimand of those involved 9. STA done 16. Improved personal protective equipment
3. Discipline of those involved 10. Revision of STA 17. Order regular pre-job instructions
4. Reinstruction of others doing the job 11. Equipment repair or replacement 18. Order use of safer materials
5. Temporary reassignment of person 12. Action to improve design 19. Check with manufacturer
6. Permanent reassignment of person 13. Action to improve construction 20. Inform all departmental supervision
7. Action to improve inspection 14. Installation of guard or safety device 21. Other than above
In all disabling and medical treatment injuries, describe details of your corrective action:
Conduct training on Refinery Instruction 503 with all employees, Reinforce following procedures and
specifications, Implement plan not to use plate on hydro-test without approval from professional
engineer with specifications, Develop a plan to notify engineering when deviations from ewo's are required,
Communicate to all employees to use all resources such as; engineering, co. rep's, QC, Safety, etc.
Person responsible for Corrective Action Target Date Date Completed
Signatures: