TATA PROJECTS LIMITED, SERVICES SBG-IPMS.

PROJECT :

Document No:TPL / IPMS / MEP / PHE / 045 Rev:00

CHECKLIST FOR INSTALLATION OF SOIL AND WASTE GRAVITY TESTING


Name of Contractor: RFI No: Date :

Drawing No: Location :

Checked
Sl.No. Description Remarks
Not
Yes No
Applicable
1 Drainage approved drawing/material available on site

2 Cutouts opening done

3 Water proofing first coat/base coat completed before paipe laying

4 Check and ensure that routing of piping are as per drawing

5 Check for PVC outlet plugged

6 All traps filled with water

7 Initial level of water

8 Final level of water

9 Decrease in level of water


Soil and waste pipes shall be tested in sections after installation, by filling
10 up the stack with water.All openings and connections shall be suitably
plugged.
Entire drainage system shall be tested for water tightness and smoke
8
tightness during and after completion of installation.

9 Leakage observed
Additional Remarks :

CONTRACTOR PMC CLIENT

Name

Designation

Signature

Date