3G U900 progress to synchronization - Ericsson

The progress for sync U900

As you know we have two kind of installation and the most installation are like figure 1:
In figure 1 we have 2G 1800 – 2G 900 – 3G 2100 and 3rd Carrier – LTE 1800 – LTE 2600 and U900
in this kind of installation 2G 1800 and LTE 1800 are share and 3G has two DUW 41 or other (DUW 30 –
31) and LTE has one DUS or in some cases used 2 DUS 41 or 31. In this installation we should follow
below synchronization to run U900.

1. DUS 41/1800 master by GPS cable should be connected to DUW 41/2100 master.
2. DUW 41/U900 slave by GPS cable should be connected to 2G DUG 1800
3. Both DUWs should be connected by F to F cable and IDL cable
4. Both DUSs should be connected by F to F cable and IDL cable (when you have two DUS)
5. DUG 900 and DUG 1800 should be connected by F to F cable
6. Both band of 2G should be in mixed mode ( DUG 900 – DUG 1800 ).

Note: when you are using F to F cable for DUGs you should change DBB in side of IDB to below progress
900 DBB should be 1101 and 1800 DBB should be 1102 and removed ESB cable. (Figure 1-1)

Amir Abbas Sepehrband +98-933-3210943


3G U900 progress to synchronization - Ericsson

Figure 1-1

Amir Abbas Sepehrband +98-933-3210943


3G U900 progress to synchronization - Ericsson

Second topology is below detail and need to follow as Figure 2 :

In figure 2 we have 2G 1800 – 2G 900 – 3G 2100 and 3rd Carrier – LTE 1800 – LTE 2600 and U900
in this kind of installation 2G 1800 used RUS 02 and LTE 1800 used RRUS 12 and 3G has two DUW 41 or
other (DUW 30 – 31) and LTE has one DUS or in some cases used 2 DUS 41 or 31. In this installation we
should use below synchronization to run U900.

1. DUW 41/U900 slave by GPS cable should be connected to 2G DUG 900


2. Both DUWs should be connected by F to F cable and IDL cable
3. Both DUSs should be connected by F to F cable and IDL cable (when you have two DUS)
4. DUG 900 and DUG 1800 should be connected by F to F cable
5. DUG 900 should be in mixed mode and DUG 1800 should be in single mode.

Note: when you are using F to F cable for DUGs you should change DBB in side of IDB to below progress
900 DBB should be 1101 and 1800 DBB should be 1102 and removed ESB cable. (Figure 1-1)

Note: The software version for both DUGs should be 78G or newer than 78G,

Amir Abbas Sepehrband +98-933-3210943