Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Contract ID: 23BC0155

Name of Project: Repair/Improvement of Carriageway Along Jct. Ayaga – Abulug – Ballesteros – Aparri Rd
Location of the Contract: Ballesteros, Cagayan

S-Curve
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8

Description Amount Pct. Wt. Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8

Billboards 18,270.00 1.21% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
OSHP 45,675.00 3.01% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38%
Mobilization/Demobilization 160,000.00 10.56% 5.28% 5.28%
Removal of Actual Structures/Obstruction 416,212.32 27.47% 13.73% 13.73%
Unsuitable Excavation 226,108.96 14.92% 14.92%
Subgrade Preparation 33,278.36 2.20% 1.10% 1.10%
Aggregate Subbase Course 115,796.75 7.64% 3.82% 3.82%
PCCP, 0.20m 499,844.46 32.99% 8.25% 8.25% 8.25% 8.25%

Total 1,515,185.85 100.00%


Weekly Progress 19.54% 34.10% 13.69% 8.77% 8.77% 8.77% 0.53% 5.81%
Cumulative Progress 19.54% 53.65% 67.34% 76.12% 84.89% 93.67% 94.19% 100.00%

You might also like