Professional Documents
Culture Documents
A) Jeddah - S TIA Guidelines V1 0 - February 2015
A) Jeddah - S TIA Guidelines V1 0 - February 2015
Version 1.0
February 2015
Municipality of Jeddah
Kingdom of Saudi Arabia
Foreword
This document is Jeddah Municipality’s official guidance on transportation and traffic impacts and
considerations that must be accounted for in the process of development planning, approval and
construction in the Municipality.
The formal title of this document is Transportation Impact Assessment Guidelines. The issuing author
of record and document administrative manager is the Directorate of Traffic Engineering of the
Jeddah Mayoralty.
The document has an important and informative subtitle: Developers and Consultants Manual, or
DCM. It is the development and consultant community, including engineers, architects and land
planners that are engaged by developers, that is the primary audience for the Manual, and that needs
to stay informed and up to date with the Manual and future revision. The Manual establishes, among
other things, minimum educational, certification and experience requirements for Professional Traffic
Engineers engaged in traffic impact assessment studies for developments within the Municipality.
Informally within the Municipality, or even in correspondence, the document may be referred to as
the “TIA Guidelines”, or “Developers and Consultants Manual”, or “DCM”, they all refer to the same
document.
If you are reading this as a hard copy document, it may not be up-
to-date! The most current version is always posted and maintained The users of this
at: http://www.jeddah.gov.sa/TIAguidelines.php, along with useful document should
anticipate periodic
links, references, look-up tables, and forms. Developers and updates to the TIA
Consultants are advised to check this web location frequently for guidelines and
most current versions and updates. No other notification of changes requirements.
Table of Contents
1.0 Introduction ............................................................................................. 1-1
1.1 What is Transportation Impact Assessment (TIA)? ........................................................ 1-1
1.2 Administrative Overview and Mission ............................................................................. 1-3
1.3 Scope of the DCM .......................................................................................................... 1-5
1.4 Acronyms, Terms and Definitions .................................................................................. 1-6
1.5 DCM Guidelines Document Structure ............................................................................ 1-6
Index of Tables
Table 5-1: Elements of a TIA Report ...................................................................................... 5-1
Table 6-1: No Significant Impacts Finding Report Structure .................................................... 6-1
Table 7-1: Transportation Impact Study Report Structure ...................................................... 7-1
Table 8-1: Subarea Transportation Plan Report Structure ..................................................... 8-1
Table 11-1: Link Capacities and Speed Limit Assumptions .................................................. 11-1
Table 11-2: Standard Parameters ......................................................................................... 11-4
Table 11-3: LOS Definitions for Public Transport Services .................................................. 11-5
Table 11-4: MUTCD Traffic Signal Warrants ........................................................................ 11-6
Table 11-5: Signal Warrants for Forecasted Volumes .......................................................... 11-7
Table 11-6: Signalized Intersection Level of Service (LOS) Definitions ............................... 11-8
Table 11-7: Signalized Intersection Thresholds for Mitigation .............................................. 11-9
Table 11-8: Unsignalized/Roundabout Intersection LOS Definitions .................................... 11-9
Table 11-9: Unsignalized/Roundabout Intersection Thresholds for Mitigation ..................... 11-9
Table 11-10: LOS Definitions for Weaving Segments ........................................................ 11-10
Table 11-11: LOS Definitions for Merge and Diverge Segments ........................................ 11-10
Table 11-12: Basic Segment Thresholds for Mitigation ...................................................... 11-11
Table 11-13: LOS Criteria for Pedestrian Walkways with Random Flow ........................... 11-11
Table 11-14: LOS Criteria for Platoon-Adjusted Pedestrian Walkways .............................. 11-12
Table 11-15: LOS Criteria for Pedestrians at Signalized Intersection ................................ 11-12
Table 11-16: Level of Service Standards in Jeddah ........................................................... 11-13
Table 11-17: Entry/Exit Lane Capacities for Car Parks ...................................................... 11-13
Table 11-18: Provision of Areas for Delivery and Service Vehicles.................................... 11-15
Table 11-19: Vehicle Classification for TMC ....................................................................... 11-17
Index of Figures
Figure 2-1 Jeddah Development Process ............................................................................... 2-1
Figure 2-2 Pre-TIA Process .................................................................................................... 2-3
Figure 2-3 Jeddah TIA Process .............................................................................................. 2-7
Figure 2-4 Post-TIA Process ................................................................................................. 2-12
List of Appendices
Appendix- A Acronyms and Abbreviations used in this Manual
Appendix- B TIA Application Form
Appendix- C Minimum Land Use Threshold for at least a TIS
Appendix- D Documentation Checklists
Appendix- E Internal Trip Capture
Appendix- F Pass-By Trips
Appendix- G Recommended Parking Rates
Appendix- H Technical Details for Parking Dimensions (MOMRA)
Appendix- I Typical Drawings
1.0 Introduction
The type of a TIA varies in scope and complexity depending on the type and size of
the proposed development.
The output of a TIA forms the basis of a conceptual plan The TIA establishes
and consequently detailed design for the development important design
details of the site plan
and surrounding improvements. If there will be future
and, is some cases,
traffic problems resulting from a proposed development the surrounding
(either directly caused by the development or due to network and the
existing traffic deficiencies in the area), this needs to be Municipality
acknowledged in the TIA, and ways to mitigate the
Parking and
deficiencies identified.
circulation is a key
issue for every
Similarly, the TIA must address all issues related to on- development site and
site parking, internal circulation and safety. Also the for every TIA
interface between the development and the surrounding road network is important, as
is adequate provision for service vehicles.
A TIA should be mandatory not only for new construction but also for
for all new land plans if the land use intensity meets the minimum
threshold for a TIS (100 vph two-way generated trips). The TIA for these
plans should take into account not only the safety and circulation of
the internal road network of the individual land plan, but it should also
be in harmony with the external transportation network. This will
minimize the possibility of road network problems and of lopsided
roadway plans that do not align well with adjacent subdivision as
frequently is the case in Jeddah. Land use spatial distribution and
intensity should be carefully planned for optimum accessibility and
efficient transportation network. Adequate right of way should also be
dedicated/reserved beforehand in the TIA for future use.
There are many problems evident in Jeddah because TIA’s were not carried
out in in the planning stage, which resulted in lopsided planning and non-
aligned road networks across and through subdivisions. For example:
Success in this mission is critically important to future of the whole of the Municipality
and its relationship to the Kingdom, and, more specifically, to the continued success
of the development community as a partner and stakeholder in the Jeddah landscape.
The Municipality has established a number of goals in this effort, including these that
specifically relate to the DCM:
Improve on the quality of technical information that is submitted to the Municipality for
approval.
[The Municipality needs better information for better decisions and outcomes]
Establish improved administrative logging and tracking of project data and submittals.
[The Municipality wants to keep track of project information for the benefit of all]
It is emphasized that, while the DCM provides certain technical and administrative
guidance for assessing traffic and transportation issues, the users of the DCM, the
developer and consultant community, should consider this guidance in the light of
the above goals as the ultimate intent of the Municipality.
The former TIA process also suffered from some developers short circuiting the
technical review process. The current recommendations set out the exact steps a
developer has to take through the entire development process.
Integrate and facilitate actions that are in harmony with the Building Permit Department
(BPD) as well as the Jeddah Local Plan (JLP) and Municipality Strategic Plan.
Improve the technical quality of TIA's by setting appropriate minimum qualifications for
engineers and firms conducting the studies.
Establish a recommended rating system for Consultants and their engineers to ensure the
standards are maintained over time.
Streamline the review and approval process so the process does not hamper growth, but
at the same time not compromising with high standards.
Establish a standard set of procedures, rules, and MOE's that will serve as basis to resolve
potential disputes between Developers and Amana.
Provide the initial technical basis for the design of a “TIA Website” which will enable online
submissions and make the process more accessible and efficient.
The Jeddah Transportation and Traffic Engineering Department (TTED) has prepared
these guidelines to streamline the current development process and to provide
guidance to developers and consultants in the preparation of a TIA, where the TIA is
integrated with the entire development process.
The TIA process developed for Jeddah is based on not only the current international
best practices for TIA procedures and guidelines but is also geared to local practices
and conditions in Jeddah. The guidelines follow a multimodal approach to
transportation improvements, giving consideration to alternate transport modes
including public transport and non-motorized modes including walking.
This manual details the development process within the Municipality with particular
focus on the TIA process and also the minimum reporting requirements associated
with a TIA document. Following these guidelines in the preliminary stages of the
development planning process will provide for a more consistent and efficient review
process.
Additionally, with a properly designed site and surrounding transportation network with
adequate capacity to handle the anticipated transportation demands, a development
is more likely to achieve success.
The three sequential stages of a new development (including changes and additions
to an existing development) are shown in Figure 2-1.
TIA Process
STEP 1 Obtain Krooki (land deed) papers that show ownership and approved access
points.
STEP 6 Initiate the Building Permit Process with the Building Permit Department.
In some cases a TIA may be required for other reasons Safety or operational
such as safety or operational problems, even though issues can also
trips generated may be below requirement thresholds. trigger the need for a
TIA
In the listing above, the typical characteristics and See other parts of the
DCM for specific
treatments noted for each of the three types of study
details and
are generalizations only; more detail on these attributes requirements
is presented in subsequent sections of the DCM.
The Amana is
A key outcome differentiator among the three types is
obligated to assess
shown in red above; that is, effect and impact effect caused by the
mitigation needs on the external transport network development on the
servicing the site. This ranges from “no effect/no transport network,
mitigation” for small development projects under the No and determine
relevant mitigation.
Significant Impact Finding category, to “likely
Large projects may
effect/probable mitigation” for large projects under the require
Subarea Transportation Plan category. Mitigation of some
type
2.2.4 Role of Trip Generation in Determination of TIA
Approach
Trip generation is a key factor in impact assessment
and development proposal review. A primary metric is
the highest number of raw additional peak trips Trip generation is a
key factor and will
generated by the proposed development at full build-
always be closely
out1. In considering and reporting trip generation in the reviewed
TIA application, only raw generated trips are to be used,
before any reduction is applied. The required
1This would entail highest of adjacent street weekday morning, afternoon, or evening peak. Near large retail areas, the weekend
peak hour may represent the highest peak hour of the week. Determining the peak hour requires knowledge of the proposed land
use and of local traffic patterns. It should also be noted that for the purpose of determination of the class of study only raw
generated trips should be used, without any discount for internal capture, pass-by and/or modal split (the discounts should be
applied in the report as needed but not for study type determination).
adjustments for internal trip capture, modal split and pass-by can be applied later in
the process.
Data sources for trip generation rates are always an important part of
transportation impact assessment. The shaded box below provides important
guidance on how this is to be approached for Jeddah projects:
In absence of local Jeddah data, the latest version of Riyadh Trip Generation Manual
(RTGM) will be used for the initial determination type of TIA study. In case where
RTGM does not have trip rates for land use or peak hour the latest versions of other
manuals can be used with prior approval of the Amana Reviewer. The order of
preference for trip generation rates is as follows:
The order of priority for choosing trip generation rates between Abu Dhabi and Dubai
shall be whichever manual was most recently updated.
Until there is a Jeddah Trip Generation Manual available, the RTGM shall be
used to determine the minimum intensity of individual land use thresholds, as
listed in Appendix-B, for at least a TIS-level TIA that is based on generated
trips only. The list in Appendix-B lists the minimum intensities of independent
land use variables (based on the RTGM) that generate at least two-way 100
vph trips during the highest peak hour at full-build-out of the proposed
development.
Zone change
Land use not compatible with current and/or
future zoning
Prevailing safety issues such as high accident rates
Operational issues such as site access near a major interchange or
roundabout
Access Management
Parking issues
Amana Reviewer's Discretion
Reviewer. This is typically required for small developments. NSIFR typically require
an assessment of parking requirements, site circulation and access to the site. No
Methodology Report is required for NSIFR development projects. Requirements of an
NSIFR are detailed in Chapter 6.0.
For each plot development within the Subarea Transportation Plan, a separate Plot
TIS (or NSIF, if there are no significant impacts for the plot in question) will be required
later on. The requirements for a Subarea Transportation Plan Report are described in
Chapter 8.0.
Concurrently with issuance of the NTB Amana will tentatively update the Jeddah
Transportation Master Plan Model (JTMP) to include the proposed development and
related transportation improvements. It is expected that Amana will maintain the JTMP
and continuously update the Model as new developments are approved.
n. MUTCD
o. HCM
5. At least 70% rating by Jeddah Consultants' Rating System (JCRS)
Amana.
The weighted rating system will award points for completed TIA's as well as
experience and resources. There are also categories which require minimum
conformity without which a firm would not be allowed to undertake TIA's. The items
included are as follows:
The JCSR system is a means to monitor the performance of Consultants and their
Responsible Engineers. If the rating falls below the minimum threshold for a TIA
Category the Consultant will be taken off the list of pre-qualified consultants for that
category.
The same minimum qualifications also applies to the Amana review staff.
The Developer is required to hire a Design Firm at the beginning of the development
process. The Design Firm will be responsible for taking the proposed development
through the entire development process. For the TIA part of the development process
the Design Firm will be either registered for the appropriate TIA and have a qualified
responsible engineer or will hire a TIA firm that is registered with Amana and has a
qualified responsible engineer.
All TIA reports (NSIFR's, TISR's and STPR's) are required to be signed and sealed by
a qualified engineer in charge of preparation of the report. It is also required that the
reports be completed in a local Jeddah offices. All consultants are expected to
exercise due diligence and good engineering judgment in reaching meaningful and
reasonable conclusions.
After obtaining the necessary Building Permit the developer's TIA consultant will file a
TIA Application (TIAA). A TIAA is required for all developments even if they generate
less than 100 peak hour two-way trips at full build-out of the development. The
determination of which type of study and report are required will be made by the
Amana Reviewer. The type of study will also determine the relevant set of required
documents.
It should be noted that the initial TIA Application should be attached with all
subsequent approvals and permits.
The Amana Reviewer will assess the application, assign a project ID, and determine
the relevant TIA type. Upon review and approval of the application the Amana
Reviewer will provide the developer/consultant with an approved copy of the
application identifying the appropriate required TIA type.
If a TIS or STP is required, the consultant shall proceed with the scoping
meeting and Methodology Report document according to information detailed
in Chapter 5.0.
The elements of a TIA report will depend on the type and scale of the development as
well as the discretion of the Amana Reviewer. Depending on the type of TIA all
elements may not be required.
The various elements of the three types of TIA's are summarized in Table 5-1. The
items marked with red "X" are mandatory for all TIA's.
Copy of the original TIA application and all previous TIA applications if
applicable
A table detailing the submission/revision history
A title page including the following information:
o Designation of TIA type by Amana (i.e. whether a NSIF, TIS or STP)
o TIA Tracking Number (as supplied by Amana)
o Project Name (as provided on TIA Application)
o Name and Contact Information of Responsible Engineer of Consultant
o Address of Responsible Engineer's Jeddah office where report will be
prepared
o Registration Information of Responsible Engineer
o Name and Contact Information of Owner/Developer
o Date of Submittal
The following information must be included within the header of TIA Reports on all
pages:
o Number of residents
o Limits of the study area (graphical illustration)
Background Traffic:
o Graphical or tabular display of the background traffic at all horizon years
including current year
Development Traffic:
o Assumptions used in trip generation (including growth factor, trip
reduction rates, etc.)
o Graphical or tabular display of the development traffic at all horizon
years.
Combined Traffic:
o Graphical or tabular display of the combined traffic for all horizon years
and hours.
Include a table detailing the type and size (densities) of land use of the development
and by zones if any (such as for TIS or STP). The table should follow the format below:
Land Use Type Unit Quantity Phase Build-out Year for Phase
Include a diagram at an engineering scale clearly showing the location of the proposed
site, size of the land uses and overall site layout including driveways. This figure
should be included on an aerial graphic showing the surrounding area.
Include a drawing clearly showing the extent of study limits as agreed with the Amana
Reviewer. The preliminary study area will be defined at scoping meeting with the
Amana Reviewer.
The preferred approach in defining the study limits in Amana is to identify which
roads/junctions experience a 10% difference (5% in existing congested areas)
in critical/highest peak hour two-way traffic flows brought about by the
development as compared to background traffic.
This applies to all phases of the project both individually and in total. The Consultant
shall revise the preliminary study limits as needed to meet these requirements.
The following information must be included within the header of all Methodology
Report pages:
A Methodology Report shall be completed for all projects which have been categorized
as requiring a TIS or an STP. The initial stage of completion for a TISR or STPR
involves a meeting with the TTED or Jeddah Municipality Representative (Reviewer).
This meeting shall be held prior to any work being initiated on the Methodology Report.
The purpose of this meeting will be to define the following items required for completion
of the Methodology Report:
Following the scoping meeting, the Methodology Report phase of the TIA process can
begin. The Methodology Report is meant to be short and concise document, detailing
the required information in the form of tables, diagrams and figures.
The goal of the Methodology Report is to define the key assumptions associated with
a proposed development, establish the appropriate analytical approach, and allow for
Amana approval prior to initiation of the transportation analyses portions of a project.
All information shall be provided unless previously agreed upon in writing by the
Reviewer. Any agreed upon changes must be included and documented within the
report.
Mandatory Site Visit Report including observed road conditions and traffic
operations (Required for all TIA's)
List the traffic surveys used, source, time the surveys were undertaken, locations and
peak periods covered by each source. List and justify all assumptions and adjustments
made. All surveys must be provided as soft copy with the report. The survey data
needs to be provided in a standardized format as detailed in Section 11.13 of the
DCM.
Local Jeddah trip generation rates are preferred and encouraged as long as they are
backed by an approved study. Any trip generation study must be approved in advance
by the Amana Reviewer and methodology for such must be documented in the TIA
report (in the Methodology Report for TIS and STP's).
The final codes or methods utilized must be confirmed with the Amana Reviewer and
should provide the worst case trips totals. A mixture of trip rates to get the worst-case
scenario is acceptable.
Trip generation information shall be provided for each peak period identified for
analysis by the Reviewer. Typically this would include weekday morning, afternoon,
and evening peaks, and even for weekends if the proposed land uses are projected to
have higher trip rates on weekends, such as for shopping centers.
The initial trip generation calculation shall not include any reductions for
internal capture, pass-by trips, or modal split.
Directional split should also not be adjusted unless justified by a local study
with prior approval of the Amanas Reviewer.
If several phases of completion apply, clearly indicate which land uses are being
included in which phase and summarize for each phase.
Provide a table showing trip generation for each land use type/ code. The trip
generation table should follow the format below for each phase individually and
cumulatively relevant to which trip rates are available:
Include drawings or figures for each phase showing the projected distribution of
entering and exiting trips associated with the development including the percentage
and total number of trips (one drawing for each peak period for each analysis year).
divisible by 5 leading to the Regional build-out year 2030. This will help Jeddah
Municipality in programming future developments in a 5-year CIP cycle.
Use agreed upon growth rates for these adjustments. These adjustments should be
rounded-up and not rounded-down. For example, if the proposed site's (or its phases)
have a build-out in 2014, the existing counts and background traffic should be
forecasted for 2015 horizon year. Similarly, if a build-out is in year 2017 for instance
then the adjusted horizon year will be 2020.
In case of an STP a year 2030 horizon year will be required in addition to all
interim horizon years if any.
For STP future horizon years should also include the build-out year for the JTMP which
is currently year 2030.
The background growth is developed to project future traffic volumes within the area
of the proposed development. The method utilized to estimate the growth in traffic
should be established based upon discussion with the Amana Reviewer. One of the
following methods shall be used:
TIA for a site within STP: For proposed development sites within a STP, the
background traffic shall be derived from the STP. If the opening year of the
proposed site development is different than the STP, traffic flows can be
TIA for a site within STP: If the infrastructure of the approved STP has not been
implemented at the time of preparing the TIA, the existing and future scenarios
will be analyzed using the proposed infrastructure of the STP. Highlight any
changes that have been made since approval of the STP that would impact on
conditions immediately surrounding the development. Horizon years for the
analysis are the opening year of each phase of the proposed site development
and the build-out year based on the JSP (2030).
Provide a drawing illustrating the future transportation flows in and around the
proposed development site for the Full Build-Out scenario. These flows should take
into consideration all developments and infrastructure committed for the relevant
horizon years (to be agreed with Reviewer). Volumes shall be provided for all peak
hours and analysis horizons included in the study.
The results of the capacity analysis shall be detailed in the report in tabular format
including Level of Service (LOS), delay, and volume/capacity (v/c) ratio for all
approaches and overall intersection. Also include delay, LOS and v/c ratios for critical
movements if movement v/c >=0.90. The capacity analysis table should follow the
format below:
Intersection Approach(es)
Intersection Name
Delay LOS v/c Ratio Delay LOS v/c Ratio
The results of the capacity analysis shall be reviewed as per the requirements detailed
in Chapter 11.0. If mitigation is shown to be necessary, then additional analyses are
needed to determine the results of any proposed mitigation strategies.
The outputs of all capacity analyses shall be included within an appendix. All
worksheets shall be labeled by location, peak hour, analysis horizon, and alternative.
Storage Lane/Queue Analysis shall also be completed for signalized and unsignalized
intersections within the study area. Queue and storage requirements shall be
calculated based on peak volumes of each specific movement and adjacent through
lane queues shall be taken into account in the development of the storage lane length
recommendations.
Storage lane length calculations shall also be performed for site exits to verify
adequate stacking is available to the closest internal intersection.
The results of the storage lane length/queue analysis shall be detailed in the report in
tabular format including existing storage length and 95th percentile queue for all peak
periods and analysis horizons. The storage lane length/queue analysis table should
follow the format below:
The results of the queue analysis shall be reviewed to determine areas where the
added traffic from the development significantly increases existing queues. If
mitigation is shown to be necessary, then additional analyses are needed to determine
the results of any proposed queue mitigation strategies. Queue analysis should
identify all location where the estimated 95th percentile queue length for an individual
movement exceeds the available queue storage. Improvement strategies shall be
analyzed within the report to mitigate identified storage/queue deficiencies.
The outputs of all queue analyses shall be included within an appendix. All worksheets
shall be labeled by location, peak hour, and analysis horizon.
type of roads
functional classification
posted speeds
number of lanes
parking activity (if minimum of 50 maneuvers per hour in urban areas)
bus blockages if any
significant pedestrian activity
types of junction control
junction geometrics and any unusual geometrics like skew
proposed capacities of roadway links
access management
safety, including sight distances (for example as any obstacles within sight
triangles for junctions such as caused by street furniture and/or vegetation)
The results of the link capacity analysis shall be detailed in the report in tabular
format including Level of Service, v/c ratios, volumes, lanes, capacities and
queues for all roadway links. A drawing clearly showing all links analyzed within
the report and link capacity analysis results shall also be included within the
report.
The results of the link capacity analysis shall be reviewed according to the
requirements of Chapter 11.0. If the requirements cannot be met, then
additional analyses are needed to determine the operations of the proposed
internal network.
The results of the capacity analysis shall be detailed in the report in tabular
format including Level of Service, delay, and v/c ratio for all approaches and
overall junction. It should also include rows for all turn moves showing a
minimum v/c of 0.90 along with 95th percentile queues for these turn moves or
if a turn move shows queues of more than 50m.
The junction capacity analysis table should follow the format below:
The results of the link capacity analysis shall be detailed in the report in tabular
format including Level of Service, v/c ratios, volumes, lanes, capacities and
queues for all roadway links. A drawing clearly showing all links analyzed within
the report and link operational analysis results shall also be included within the
report.
The results of the link capacity analysis shall be reviewed according to the
requirements of Chapter 11.0. If the requirements cannot be met, then
additional analyses are needed to determine the operations of the proposed
external network.
Freeway Ramp
Location No. No. LOS
Speed Volume Speed Volume
Lanes Lanes
Capacity and Level of Service (LOS) analyses shall be evaluated for all
proposed mitigation strategies at junctions, weaving segments, and
merge/diverge segments identified as requiring additional analysis based upon
the results of the external analysis.
The results of the mitigation strategy analysis shall be detailed in the report in
tabular format including Level of Service, delay, and v/c ratio for all roadway
links. Results shall be compared to capacity analysis results without mitigation.
Provide discussion on the results of the mitigation strategy analysis.
Provide a drawing clearly showing all parking spaces provided within each zone of the
development, highlight all parking facilities and number each parking space.
All parking requirements must be met 100% within the limits of the development
and all parking design must meet the requirements shown with the
recommended parking rates.
Provide a table showing the parking demand calculated based on the recommended
parking rates in Appendix- G or as rates agreed with the Amana Reviewer. If a
suitable land use type is not available surveys can be undertaken to determine an
appropriate local rate (to be agreed with the Reviewer).
All turning radii and dimensions for the parking spaces and access to these parking
spaces must comply with current MOMRA standards as shown in Appendix- H and
must be checked using Vehicle Tracking or similar software.
For extensions to existing developments, the parking rates established from a parking
study will be acceptable for use (to be agreed with Amana Reviewer).
Accident history, if available, should be analyzed. Visibility and sight distances should
also be assessed for existing and future years.
Provide discussion on the design and operations of pedestrian routes and crossings.
Show how pedestrian network internal to the proposed site connects with the external
network.
Changes (if any) to the present and planned public transportation network need to be
approved by Amana explicitly prior to implementation. The cost of changes needed is
to be identified and presented in the report.
Include drawings and discussions on the anticipated pedestrian walking times to/from
public transport facilities. Include diagrams showing 5 min, 10 min, and 15 min time
intervals.
Based upon the above information provide discussion on the ability of the proposed
alternate transportation modes to meet the modal split targets identified within the
Methodology Report.
Taxi rank, access and circulation should also be discussed if applicable as for
shopping centers.
Develop and explain proposed mitigations in a concise format in the report. Include
conceptual designs and for intersections also include phasing plan and cycle time if
signalized. Also discuss signal warrants for all new signals.
Compare modeling results (with, without and mitigated) for each measure, showing
the Level of Service for all approaches and highlight critical movements.
The mitigations presented (grade separation, free right turns, extending tapers, etc.)
must be based on volume and /or safety criteria and not design preference. Where
mitigations for one user group (e.g. cars) negatively impact facilities for another user
group (e.g. pedestrians) the negative impact must be mitigated (e.g. pedestrian
bridge).
Calculate the developers regional cost share. The principles and methodology for cost
share calculation are presented in Section 2.4.
Local mitigations required to provide safe and sufficient access to the development
will be 100% at the cost of the developer.
Summarize the cost estimates and calculated cost share in a table in the following
format for each horizon year:
List all variations from standard procedures that have been agreed with the Amana
Reviewer.
Approved minutes of meeting for all agreements with the Reviewer should be attached
in an appendix of the TIA report.
5.30 Recommendations
Go to 9.0 for more details.
For small developments, generating less than 100 trips during the highest peak hour,
a No Significant Impacts Findings Report (NSIFR) document is sufficient for review
and approval by Amana.
At a minimum, the NSIFR shall include the sections identified in Table 6-1. Any
variation from the required structure listed below needs to be agreed with the Reviewer
and documented in meeting minutes.
For Details Go To
Report Elements
Section Number
Seal of Registered Responsible Engineer on Cover 5.1
Project Tracking Information 5.2
Executive Summary 5.3
Project Description 5.4
Site Access and Circulation 5.9
Trip Generation 5.10
Future Horizon Years 5.15
Parking Demand, Design and Circulation 5.19
Access Management 5.20
Safety Issues 5.21
Pedestrian Access 5.22
Service and Emergency Vehicle Access 5.24
Construction Transport Impacts 5.26
Assumptions and Agreements 5.29
Recommendations and Approval Plans 9.0
Appendices as Required
The following section details the required elements and scope of a Transportation
Impact Study Report (TISR). A TIS is required for sites generating 100 - 2499 trips
during the highest peak hour. The TISR will consist of a report document
supplemented by drawings and appendices containing technical data.
At a minimum, the TISR shall include the sections identified in Table 7-1. Any variation
from the required structure listed below needs to be agreed with the Reviewer and
documented in meeting minutes.
For Details Go To
Report Elements
Section Number
Seal of Registered Responsible Engineer on Cover 5.1
Project Tracking Information 5.2
Executive Summary 5.3
Project Description 5.4
Study Limits 5.5
Methodology Report 5.6
Existing Conditions 5.7
Existing Volumes 5.8
Site Access and Circulation 5.9
Trip Generation 5.10
Trip Reductions 5.11
Other Known Developments 5.12
Planned Road Improvements 5.13
Trip Distribution 5.14
Future Horizon Years 5.15
Background Traffic Growth 5.16
Future Volumes 5.17
Traffic Analysis 5.18
Parking Demand, Design and Circulation 5.19
Access Management 5.20
Safety Issues 5.21
Pedestrian Access 5.22
Public Transport Assessment and Taxi Access 5.23
Service and Emergency Vehicle Access 5.24
Freight Transport Assessment 5.25
For Details Go To
Report Elements
Section Number
Construction Transport Impacts 5.26
Mitigation Plans 5.27
Cost Estimate and Development Share 5.28
Assumptions and Agreements 5.29
Recommendations and Approval Plans 9.0
Appendices as Required
The following section details the required elements and scope of a Subarea
Transportation Plan Report (STPR). A STP is typically required for sites generating
2,500+ trips during the peak hour. The STPR will consist of a report document
supplemented by drawings and appendices containing technical data.
At a minimum, the STPR shall include the sections identified in Table 8-1. Any
variation from the required structure listed below needs to be agreed with the Reviewer
and documented in minutes of meeting.
For Details Go To
Report Elements
Section Number
Cost Estimate and Development Share 5.28
Assumptions and Agreements 5.29
Recommendations and Approval Plans 9.0
Appendices as Required
After the approval of a TIA (whether a NSIFR, TISR or STPR), the Consultant is
required to prepare a standalone report including Recommendations and Approval
Plans as appropriate for the type of TIA. The formal approval of the TIA will only be
issued after the Recommendations and Approval Plans have been submitted and
approved by Amana.
9.1 Recommendations
The recommendations from the TIA study shall be in a standalone chapter and are
meant to be reviewed independently from the TIA report. These recommendations
should include all recommendations of the study supported by drawings and plans as
appropriate. These recommendations should be divided into two parts (except for the
NSIFR, which may only require the first part):
Location of the development (in the top right hand corner of the title box)
Concept design of proposed mitigations (junction designs, etc. - figures)
Road accesses to the development
Internal circulation of the development
Public transportation facilities within and surrounding the development
Typical cross-section roads
Pedestrian access and circulation facilities
Table of land uses
Table detailing trip generation
Parking Plan including table detailing parking requirements and supply
Approval box for Amana approval
All Approval Plans shall be folded in A4 size with the front page showing the title and
approval box.
Land use, trip generation, parking demand and supply for each plot or block (as
agreed with the Amana Liaison Engineer), maximum building height for each
plot
Location of the development and all mitigation measures
Plot boundaries
Right of Way for all agreed transport infrastructure within the development
(road, public transportation, cycling, pedestrian infrastructure)
Road hierarchy, public transportation network
Typical cross-sections for all internal roads
Concept design of proposed mitigations (junction designs, etc.)
Phasing of master plan implementation
Approval box for Amana approval
The Jeddah Transportation Master Plan (JTMP) has been a comprehensive 3-year
study of the city’s transport needs up to 2030. The Jeddah Transport Model (JTM) is
part of the JTMP. The JTM has been approved for use, and the following protocols
will apply to be reviewed and approved by the Amana Reviewer.
Once a TIA application has been submitted and reviewed, the Amana Reviewer will,
in consultation with the Jeddah Transportation Master Plan Consultant, determine
whether a strategic transport modeling exercise is required and inform the consultant
of the decision and, where modeling is required, which of the following four protocol
options is to be used:
For a Plot TIS within a STP where the STP has been previously approved, the
flows from the STP can be used unless the Amana Reviewer determines
otherwise.
For small TIS projects where background flows only are required, Amana
Reviewer will provide the flows from JTM as appropriate. Manual distribution of
the development traffic will be required by the consultant.
For large and medium sized TIS/STP projects - Qualified consultants will be
provided remote access to the JTM to undertake the modeling.
In all cases where strategic modeling or modeling output is required, the consultant is
to include a request for data as a part of their Methodology Report.
Modeling outputs shall be provided in the STP Report appendices. Depending on the
number of junctions analyzed, a softcopy of the outputs may suffice to avoid
unnecessary prints (to be agreed with the Amana Reviewer). All modeling files must
be provided as softcopy.
The following sections describe the analysis assumptions which should be used in all
Jeddah TIA reports. Any exception from the standards and thresholds presented
below need to be discussed in detail in the TIA and agreed with the Amana Reviewer.
Expressway – divided highway with at least 2 lanes in each direction, designed for
high-speed through traffic with at least partial control of access.
Arterial – serves the major centers of activity of an urban area. Arterial roads serve
the longest trip desired and represent highest traffic volume corridors. They carry a
high proportion of the total urban area travel on a minimum of kilometerage.
Collector – collects traffic from local subdivision areas and channels it into the arterial
system. Collector roads provide both land access and traffic circulations, within
residential neighborhoods, commercial and industrial areas. In reverse, they distribute
trips from the arterial roads through these areas to their ultimate destination.
Ramp – sloped road of an interchange connecting two or more road planes at different
levels. Usually it is a short section of road which allows vehicles to enter or exit a
highway.
Rural 2-Lane Highway – undivided high-speed principal road outside of urban areas,
serving long trips between urbanized areas of major generators
Local Road – provides direct access to abutting land and serves as access to the
higher order system. Through traffic is deliberately discouraged on local roads.
Both these methods rely on the use of projected growth factors to existing year traffic
data. The methods assume that the recent percentage of growth in traffic will continue
in the future. These factored forecasts are most reliable for relatively short periods of
time (5 years or less) and for existing areas where there is still room for growth. This
method is not recommended for longer than 5 years also not for entirely new areas.
Ideally, the growth factors are obtained based on traffic counts taken in the past few
years.
FD = BC*(1 + i*n)
Where:
FD = future year demand
BC = base year count
i = growth rate per year
n = number of years between base year and future year
FD=BC*(1+i)n
Compounded growth is suitable for a short-term forecast for areas which have room
for new growth.
It should be noted that some areas and roadways may see more growth than others
and some congested roadways may see less growth than other adjacent less
congested roads because of the capacity limitation effect.
Analyses of road segments and weaving analysis for ramps and merges should be
undertaken using HCS which uses HCM procedures. The methodology applied must
be clearly explained in the report. The Reviewer may require the Consultant to use
micro-simulation to assess weaving and merges.
1. Junctions
a. interchanges: (HCS, SYNCHRO, SimTraffic or VISSIM)
b. roundabouts
i. unsignalized roundabouts: SIDRA Intersection
ii. signalized roundabouts: VISSIM
c. intersections
i. unsignalized intersections: SYNCHRO, SimTraffic
ii. signalized intersections: SYNCHRO, SimTraffic
2. Road Segments: HCS, VISSIM or SimTraffic
Typical parameters to be used in the analysis are listed in Table 11-2 below. Any
variations of these parameters need to be discussed and agreed with the Reviewer.
Parameter Value
Peak Hour Factor (PHF) 0.92
Minimum Yellow Clearance Interval 4 seconds
Minimum All-Red Clearance Interval 2 seconds
Ideal Intersection Capacity per Exclusive Through
1,900 pc/hr/lane
Lane
Ideal Intersection Capacity per Shared Through
1,650 pc/hr/lane
Lane
Ideal Intersection Capacity per Left/Right Lane 1,750 pc/hr/lane
Ideal Intersection Capacity per U-Turn Lane 1,550 pc/hr/lane
Based on existing classified traffic count data.
If existing count data is unavailable, or for
Proportion of Truck/Heavy Vehicle Traffic
proposed new roadways, present
assumptions to Amana Reviewer
Measures of Performance
Level of
Service Service Span of
Headway
(LOS) Frequency Service Comments
(min)
(veh/hr) (hr)
A > 6.0 0-10 19-24 Passengers do not need schedules
Frequent Service, passengers consult
B 4.01 – 6.0 11-14 17-18
schedules
Maximum desirable time to wait if
C 3.0 – 3.99 15-20 14-16
transit vehicle is missed
D 2.0 – 2.99 21-30 12-13 Service unattractive to choice riders
E 1.0 – 1.99 31-60 4-11 Service available during hour
F <1.0 >60 0-3 Service unattractive to all riders
(Source: “Highway Capacity Manual”, 2010, TRB)
The investigation of the need for a traffic control signal for existing roadways shall
include an analysis of the applicable factors contained in the following traffic signal
warrants, as listed in Table 11-4 and other factors related to existing operation and
safety at the study location:
It should be noted that the above procedures are recommended for existing roadways
for the short-term, up to 5 years, for acceptable accuracy of 4-hour and 8-hour
volumes.
For future developments on new roads, where it may not be possible to predict 8-hour
hour volumes with the necessary accuracy, Average Hourly Volumes (AHV) can be
derived from forecasted peak hour volumes (PHV). The AHV is an approximation of
average 4-hour or 8-hour volumes and is calculated as shown below:
or AHV = (AmPHV + PmPHV) / 4 (if both AM and PM peak hours are available)
Table 11-5 is used to assess future signal warrants with AHVs derived from forecasted
PHVs.
Given the uncertainty in forecasted future volumes, Justification 1 and
Justification 2 should both be met at least 120% for an existing intersection and
at least 150% for a new intersection.
For new installations, new area developments, a common cycle time for all
intersections must be selected (usually 90s to 120s). For existing installations or
intersection within an already existing signal area, the cycle time must be in line with
adjacent signalized intersections.
Table 11-5: Signal Warrants for Forecasted Volumes
Minimum Warrant Complaince1
Minimum
Requirement
Requirement
2 or more Lanes
Justification
AHV along
b 120 170 120 170
Minor Street
Total of
Major Street
a AHV entering 480 720 600 900
volumes (in
PCU)
Delay to crossing traffic
Combined car
2 and
pedestrian
volume
b 50 75 120 170
crossing
major street
from minor
streets
1
Justification 1 and 2 are required to be met 120% for an existing intersection and 150% in the case of a new intersection
(Adapted from Ontario Traffic Manual, Book 12, MTO, July 2001)
F Mitigation required
F Mitigation required
The Level of Service (LOS) definitions for merge and diverge segments are given in
Table 11-11 below. The LOS is based on the density in pc/km/lane.
The need for mitigation on segments is based on the thresholds presented in Table
11-12. Any exception from the following thresholds needs to be discussed in detail in
the TIA and agreed with the Amana Reviewer.
Table 11-13 applies when pedestrian flow along the facility is random. Table 11-14
applies when platoons of pedestrians form along the facility, for example, when a
signalized crosswalk is located at one end of the portion of the facility being analyzed.
Table 11-13: LOS Criteria for Pedestrian Walkways with Random Flow
Measures
LOS Average Space Flow Rate Description
2
(m /p) (p/min/m)a
Ability to move in desired path, no need to
A > 5.5 ≤ 16
alter movements
Occasional need to adjust path to avoid
B > 4 – 5.5 > 16 - 23
conflicts
Frequent need to adjust path to avoid
C > 2.2 – 3.7 > 23 - 33
conflicts
Speed and ability to pass slower pedestrians
D > 1.5 – 2.2 > 33 - 49
restricted
Speed restricted, very limited ability to pass
E > 0.75b – 1.5 > 49 - 75
slower pedestrians
Speeds severely restricted, frequent contact
F ≤ 0.75b >75
with other users
a. Pedestrians per minute per meter of walkway width.
b. In cross-flow situations, the LOS E–F threshold is 1.2m2/p.
(Source: “Highway Capacity Manual”, 2010, TRB)
A < 10
B >10 – 20
C > 20 – 30
D >30 – 40
E > 40 - 60
F > 60
(Source: “Highway Capacity Manual”, 2010, TRB)
It should be noted that the assessment in Table 11-17 applies to automated security
processing only. For manual security processing, it is recommended that an average
service time be determined (e.g. from observed processing time at similar security
gates) and used for queuing analysis.
A volume/ capacity ratio > 1.0 will not be accepted. For access roads with a volume/
capacity ratio > 0.5 a queuing assessment will be required. The assessment shall be
based on the following formula:
The results shall be presented in a table comparing average, 95% queue and available
queuing capacity, based on 7 meters per vehicle.
When dealing with a combination of different types of developments, the total spaces
required should be determined by adding the individual components and rounding
upwards to the nearest space.
For residential flat buildings, the total spaces required are determined by adding the
individual components and rounding upwards to the nearest space. Service area
requirements for residential flat buildings may be waived in cases where visitor parking
spaces are available to trucks and delivery vans. The various provisions are
summarized in Table 11-18.
The raw data is to be processed and presented in an Excel spread sheet format and
should include:
Obvious errors (e.g. periods when tubes and detectors are not working) are to be
highlighted and omitted from subsequent analysis.
In addition any unusual traffic patterns such as due to accidents or inclement weather
should be noted and omitted from analysis. Holidays should also be omitted.
In addition any unusual traffic patterns such as due to accidents or inclement weather
should be noted and omitted from analysis. Holidays should also be omitted.
At roundabouts, where the consultant does not propose to use cameras, the
consultant must set out a detailed methodology of how the counts will be conducted.
For large roundabouts an Automatic Number Plate Matching (ANPR) surveys or
Camera Recorded Counts are required unless agreed with the reviewer.
The raw data is to be processed and presented in an Excel spread sheet format and
should include:
Again, errors, such as periods when tubes/detectors are not working, are to be
highlighted and omitted from calculations.
2 Project Name:
Amana Registration Number for TIA Consultant: Attach Copy of TIA Consultant Registration
Responsible Engineer:
3
Amana Registration Number for Responsible Engineer: Attach Copy of Responsible Engineer Registration
Address:
Owner's Name:
Design Firm:
4
Design Firm Address:
Source of Trip Generation. Please use in the following priority (using latest editions):
9
1) Jeddah Trip Generation Manual (if available) 2) Riyadh Trip Generation Manual 3) Other (with prior Amana approval)
Comments:
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
1 Residential
Area in m2 0.0021 47,619 47,000
101 Villas
No. of Villas 1.537 65 65
Area in m2 0.007 14,286 14,000
102 Residential Buildings
No. of Apartments 0.384 260 260
Area in m2 0.0022 45,455 45,000
103 Compounds No. of Apartments 0.30 333 330
No. of Residents 0.07 1,429 1,400
Area in m2 0.00225 44,444 44,000
104 Private Housing Compounds
No. of Apartments 0.19 526 500
2 Industrial Uses
Area in m2 0.00043 232,558 232,000
201 Industrial Cities
No. of Workers 0.04 2,500 2,500
Area in m2 0.05 2,000 2,000
202 Industrial Parks No. of Workers 0.86 116 110
No. of Workshops 6.04 17 15
Area in m2 0.016 625 6,000
203 Industrial Workshops
No. of Workers 1.349 74 70
3 Educational Uses
Area in m2 0.02479 4,034 4,000
No. of Students 0.29 345 300
301 Universities
No. of Staff members
1.32 76 75
and employees
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
Code Land Use Type (L.U.) Independent Variable Highest Peak Hour Minimum-L.U. Thresholds Recommended Value
10 Religious Uses
Area in m2 2.91 34 35
1004 Cemeteries
Number of Graves 0.01077 9,285 9,300
Included?
No. Required Elements of a TIA Report Comments
Yes No
1 Consultant and Project Team approved and authorized?
2 Site Plan showing existing roads and buildings
3 Map showing Approved Plan for the surrounding area
4 Committed developments and committed transport network projects
Drawing showing existing intersections and access points’ traffic
5
control and spacing in relation to the surrounding network
6 Proposed land use, type and intensity
16 Trip Generation and trip reductions (if any) except for mode split
17 Trip Distribution
18 Mode Split (if relevant)
19 Trip Assignment
Reviewer Name:____________________________________Signature:________________________Date:__________________
All internal trip reductions shall be approved by the Amana Reviewer prior to commencement of a TIA study.
Fast-food Restaurants 35 %
Banks 15 %
Supermarket 20 %
All Pass-by trip reductions shall be approved by the Amana Reviewer prior to commencement of a TIA study.
Residential uses
Commercial uses
Stores, Warehouses and similar indoor uses 1 space / 70 m2 JLP and JMGHB
Service Uses
Sports Centers 2 spaces / 5 spectators + bus space / 150 spectators JLP and MOMRA
Health uses
Educational uses
Industrial uses
Religious uses
Sources:
Jeddah Local Plan (JLP)
Jeddah Municipality Guide for High-Rise Buildings (JMGHB)
Ministry of Municipalities and Rural Affairs (MOMRA)
Riyadh Trip Generation Manual (RTGM)
-يجب وضع المداخل والمخارج في الجانب األيمن وسط المباني بالشوارع شكل رقم (. )4
-في حالة كون الشارع اتجاه واحد فإنه يقترح أن يكون المدخل والمخرج يسار الشارع ،ألن حركة الدوران لليسار
أسهل من حركة الدوران لليمين ،فضالً عن أن مسافة الرؤية بالنسبة للدوران لليسار أفضل منها في الدوران لليمين .
-أال يقل عرض المدخل أو المخرج عن 3.5م .
-في حالة ما إذا كان المدخل والمخرج معا ً من فتحة واحدة فال يقل عرض الفتحة عن (7.5م) ويوضع فاصل لحركة
المرور ال يقل عن 50سم .
– 2 – 3 – 2معايير تصميم المواقف
أ – األبعاد
-يجب أن تؤمن المساحة المخصصة للسيارة الواحدة ( سيارة الركاب العادية )PASSENGER CARبحيث
تضمن سهولة حركة السيارة عند دخولها للموقف وخروجها منه .
-األبعاد التالية توضح الحد األدنى لألبعاد المناسبة لوقوف أي نوع من أنواع سيارات الركاب العادية وكما هو موضح
بالشكل رقم (. )5
-الطول = 5.50م .
-العرض = 2.60م .
-في حالة الوقوف المتوازي يكون الطول 6.5م ،والعرض 2.5م .
-أبعاد الموقف بزاوية انحراف (ن) عن الرصيف :وهي األبعاد التي تساعد المصمم على استنتاج المسافات والمساحات
التي تشغلها السيارات بعد تحديد زاوية االنحراف المطلوبة وكما هو موضح بالشكل رقم ( )6جدول رقم (. )1
– 1 – 5 - 2موقع المواقف
يجب أن يكون الموقع بعيداً عن التقاطعات ،ويفضل أن يكون بين المباني لمنع الزحام في الشوارع .
– 2 – 5 – 2مداخل ومخارج المواقف
أ – المداخل :يعتمد تصميم المدخل على ما إذا كانت المواقف ستكون ذات خدمة ذاتية أو بمساعدة أحد العاملين ،
وعندما تستخدم المواقف ذات الخدمة الذاتية فإنه يمكن للمركبات أن تتدفق بسهولة .
وهذه األنواع من المواقف تقدم معدل تدفق يتراوح بين 300إلى 500سيارة في الساعة .
وعندما تستخدم المواقف بمساعدة أحد العاملين فإنه يتعين أن تكون هناك مساحة تخزين ،ومساحة التخزين المطلوبة
(مساحة احتياطية) تعتمد على نسبة متوسط وصول الزبون إلى معدل خدمة عامل المواقف .ويبين الشكل رقم ()13
المساحة االحتياطية المطلوبة لمعدل وصول السيارات المتعددة .فمثال لنفترض أنه في فترة الذروة تصل سيارة كل 50
ثانية ،وتستغرق 45ثانية حتى يتمكن عمال المواقف من توقيفها في الموقف ،فإن نسبة الوصول ونسبة التخزين في هذه
الحالة تكون على التـوالي 72 = 50 ÷ 3600 :و 80 = 45 ÷ 3600سيارة /ساعة .
وهكذا فإن نسبة التخزين تكون = 1.11 = 72 ÷ 80مرة من نسبة الوصول ،ومن الشكل رقم ( )13تتطلب مساحة
االحتياطي سعة 14سيارة .
ب – المخارج :يكون لمخارج المواقف عامل في كبينة يقوم بمعالجة البطاقة وتحصيل األجرة ،وعلى هذا األساس
تتحدد معدالت خروج السيارات بواقع أقل من 250سيارة في الساعة ،وللعمل على زيادة هذا المعدل فإنه تم تطوير طرق
متعددة لتحصيل األجرة ،هذه الطرق تؤدي إلى زيادة معدالت خروج السيارات من 300إلى 500سيارة في الساعة .
– 3 – 5 – 2تصميم المنحدرات واألدوار
أ – المنحدرات
هي المسطحات المائلة التي تمكن السيارات من االنتقال من مستوى إلى آخر ،وتضمن نزول وصعود السيارات عليها
بطريقة سليمة وآمنة بحيث توفر الميول المناسبة لذلك ،ويوضح الجدول رقم ( )5أنواع المنحدرات المختلفة بالمواقف .
عقارب اتجاهان
الساعة 17.38م
حلزوني اتجاه واحد
باتجاه 9.57م
م وال يقل عن 4.57
معاكس
3.96م لحركة م9.14 م 5.18
لحركة اتجاهان
.الصعود
عقارب م14.32
الساعة
* يتم الفصل في حركة المرور في المنحنيات ذات االتجاهين .
- 1المنحدر المستقيم .
وعادة ما يستخدم للمداخل والمخارج بالموقف لتسهيل عملية الدخول والخروج ووضوح الرؤية .
أ – أال يزيد ميول المنحدر عن . % 15
ب – في حالة زيادة ميل االنحدار عن %15فيجب أن تكون هناك مرحلتا انتقال في بداية ونهاية المنحدر ،واليزيد
ميل أي منها عن %15واليزيد طول أي منها عن5.00م مع وجود مرحلة انتقالية وسيطة واصلة (رابطة)بينهما ال يزيد
ميلها عن %18وكما هو موضح بالشكل رقم(. )14
ج – عند استخدام المنحدرات للوصل بين أدوار الموقف فقط يكون ميل المنحدر بها بين( 10إلى)%13
د – في حالة استخدام المنحدرات كمواقف للسيارات فإن الميل بها يكون بين ( 5و . ) % 8
يفضل أن تكون الطوابق أفقية ،و االرتفاع الصافي ال يقل عن 2.50م وارتفاع الدور األرضي 3.75م لكي يسمح
باستيعاب المركبات المرتفعة ،وأن تكون المساحة التي تشغلها السيارة من 37.2 – 27.5م. 2
– 4 – 5 – 2اإلشارات الداخلية
لما كانت مواقف السيارات تعتبر امتداداً لنظام الشوارع ،فإن هناك حاجة لوجود لوحات إرشادية وتوجيهية ،ويتعين
أن تكون متناسقة مع اللوحات القياسية بالشوارع .
ويجب أن تصمم اإلشارات بعد استكمال الموقف .والدراسة التي يوصى بها هي القيادة داخل الموقف بسيارة بعد أن
يستكمل ،وتحدد مواقع اإلشارات على ضوء مشاهدة الخطوط ،ومواقع السيارات الواقفة ،وعوائق الرؤية مثل األشعة
. واألعمدة العاكسة
– 5 – 5 – 2المصاعد
أ – يجب أن تكون جميع المصاعد مجهزة لخدمة المعاقين والعامة من مستخدمي المواقف على حد سواء بحيث تصل
جميع أدوار الموقف ببعضها بما في ذلك القبو .
ب -يراعى أن يتم تزويد المصعد بجرس إنذار وهاتف لمخاطبة مكتب خدمات الموقف في حالة تعطل المصعد.
ج – تحدد عدد مصاعد الموقف كما هو موضح بالجدول رقم (. )6
جدول رقم ()6
ب – كما يمكن أن تتكون أرض المواقف من األسفلت وكما هو موضح بالشكل رقم (-18ب) وكالتالي:
– 1طبقة من األساس الحجري سماكة 20سم بعد الرص .
– 2طبقة تأسيس أولى باألسفلت السائل بمعدل 1.50كجم/م.)MCI( 2
– 3طبقة أساس من خرسانة األسفلت الساخن بسمك من 5سم إلى 7سم بعد الرص .
: االشتراطات الميكانيكية- 4
– 1 – 5اشتراطات عامة
أ -أن يكون التصميم والتنفيذ متمشيا ً مع أحد النظم المحلية أو العالمية .
ب -أن يراعى توفير خدمة مستمرة وطويلة بصورة اقتصادية وأدنى تكلفة للصيانة .
ج – أن تكون المعدات واألجهزة الكهربائية من النوع المغلق لحمايتها من الغبار .
د -شدة اإلنارة :ويتم تصميم اإلنارة طبقا ً للقيم القياسية الموضحة بالجدول التالي :
جدول رقم ()7يوضح الحد األدنى لشدة اإلنارة
– 3أن تركب اللوحات غاطسة في الجدار أو ظاهرة عليه بحيث يكون طرفها السفلي بارتفاع ال يقل عن (150سم )
عن سطح البالط ،وتحتوي على القواطع اآللية باألعداد والسعات المناسبة لألحمال .
ب -لوحات التوزيع الرئيسية :
– 1أن تصنع من ألواح معدنية بسماكة ال تقل عن (1.50مم) على شكل خزانة مدهونة ببوية الفرن ،ومستوى العزل
فيها ال يقل عن (500ف) .
– 2أن يتم تركيب عدد 4قضبان توزيع نحاسية بالمقاطع المناسبة ،ويخصص أحد هذه القضبان لخط التعادل الذي
يتم عزله عن جسم اللوحة باإلضافة إلى قضيب األرضي المتصل بجسم اللوحة .
– 3أن تجهز اللوحة بأجهزة القياس التالية :
أ -عدد 1جهاز لقياس الجهد (فولتميتر ) مع مفتاح اختبار لقياس الجهد .
وعدد 3جهاز لقياس التيار (أمبيرميتر) مع محوالت التيار المناسبة ) .وعدد 3لمبات بيان .
ب -أن يترك فراغ كاف ٍ في أسفل اللوحة بارتفاع ال يقل عن 30سم من القاعدة لربط كابالت التغذية بنقط النهايات
المثبتة بهذا الفراغ .
ج – أن يراعى عدم ربط الكابالت مباشرة في األجهزة أو ربط أكثر من كابل في نقطة نهاية واحدة .
د -أن يتم تركيب اللوحة على مجرى خرساني أو قاعدة أسمنتية بارتفاع 20سم عن سطح األرض .
– 6 – 5شبكة التأريض
أ – تؤرض جميع وحدات اإلنارة والمآخذ الكهربائية والقطع المعدنية غير الحاملة للتيار الكهربائي في األجهزة
الكهربائية وحديد تسليح األساسات للمباني .
ب – في حالة استخدام كابالت مسلحة بين اللوحات الفرعية والرئيسية يمكن استخدام تسليح الكابل كموصل تأريض .
ج – أال تزيد مقاومة األرضي عن 25أوم .
– 1 – 6المداخل والمخارج
أ – أن يزود كل مدخل وكل مخرج بعالمة مضيئة توضح المدخل أو المخرج كتابة .
ب -أن يزود كل مدخل بلوحة تحدد االرتفاع المسموح به للدخول ،وتوضع هذه اللوحة بحيث يسمح لها بالحركة عند
مالمستها لسطح السيارة التي تتجاوز االرتفاع المسموح به .
ج – أن توضع حواجز متحركة على المداخل والمخارج في المواقف الخاصة ،وكذلك المواقف العامة التي يقوم عليها
مستثمرون .
د – أن يتم التأكد من نظامية ميول األرضية أو األرصفة المؤدية لمداخل المواقف أو مخارجها ،بحيث تكون الميول
بطريقة تضمن عدم ارتفاع منسوب الرصيف أو هبوطه أمـام المداخل أو المخارج بشكل يعـوق حركة المشاة أو المعوقين
،كما يتم تخطيط الرصيف المؤدي للمداخل أو المخارج بلون واضح لتأمين سالمة عبور المشاة ،وكما تم إيضاحه بالشكل
رقم (. )12
– 2 – 6المنحدرات
أن تستخدم موانع االنزالق ( النتوءات) بأرضية منحدرات المداخل والمخارج لمنع انزالق السيارات عند الصعود
والحد من سرعتها عند النزول .انظر الشكل رقم ()21
– 3 – 6األرصفة
عمل مصدات خرسانية مسلحة بأرضية الموقف تساعد على وقوف السيارة بالحيز المحدد لها ،وتحول دون إعاقة
السيارات لحركة المشاة عند وقوفها وكما هو موضح بالشكل رقم (. )22
– 4 – 6أجهزة اإلطفاء
أ -أن يزود كل طابق بأجهزة اإلطفاء الالزمة ،وتتبع تعليمات السالمة التي يطلبها الدفاع المدني في هذا الصدد .
ب -أن تزود المواقف متعددة األدوار بنظام إطفاء مناسب يعمل آليا ً عند الحاجة .
– 5 – 6حماية الجدران واألعمدة
أ -أن توضع المصدات الخرسانية المسلحة أمام اإلطارات األمامية للسيارات بأرضية الموقف لكل سيارة وبمسافة ال
تقل عن 76سم عن حائط الموقف إلى منتصف المصدة وكما هو موضح بالشكل رقم (-23أ ) .
ب – أن توضع زوايا معدنية أو أي مادة أخرى مقاومة للصدمات والصدأ وبأبعاد مناسبة على زوايا األعمدة بالموقف
لتأمين سالمتها ولحمايتها من الصدمات وكما هو موضح بالشكل رقم (-23ب ) .
– 1 – 7التشغيل
أ – أن يتم تشغيل الحواجز المتحركة على مداخل ومخارج ومواقف السيارات آليا ً أو بواسطة عامل في المواقف
الخاصة والمواقف العامة التي يقوم عليها مستثمرون .
ب -أن يتم وضع العالمات اإلرشادية التي تحدد السرعة بالموقف والدالة على االتجاهات والمنعطفات والمنحدرات
ومخارج الطوارئ واالرتفاعات ودورات المياه والمصاعد ،ويتم تشغيل العالمات المضيئة اإلرشادية آليا ً أو عن طريق
غرفة التحكم ،ويتم تشغيل إشارات الطوارئ آليا ً .
ج – أن يتواجد مراقب يقوم باإلشراف على تشغيل الموقف تكون من مسئولياته التأكد من عدم استخدام الموقف لغير
الغرض الذي أنشئ من أجله .
د -أن تسجل أرقام لوحات السيارات التي تبقى بالموقف أكثر من 24ساعة مع إبالغ المرور والشرطة عنها مالم يكن
هناك تفاهم مسبق عليها ،ويتم هذا اإلجراء بالمواقف الخاصة وأيضا ً بالمواقف العامة التي يقوم بتشغيلها مستثمرون .
– 2 – 7الصيانة
أ -أن يجرى الكشف على أجزاء المبنى اإلنشائية بالمواقف دوريا ً وإجراء الصيانة الالزمة لها .
ب -اختبار جهاز إطفاء الحريق اآللي بالموقف دوريا ً ،وتتم صيانة جميع أنابيب طفايات الحريق الموجودة بالموقف
دوريا ً .
ج – تجرى صيانة مواسير تصريف المياه ومضخات المياه والخزانات دوريا ً .
د -صيانة جميع العالمات اإلرشادية ومصابيح اإلنارة وتبديل التالف منها وصيانة العالمات المضيئة .
هـ -تنظيف الموقف من األتربة والنفايات بصفة دائمة .
و -صيانة األجهزة الميكانيكية الخاصة بتجديد الهواء دوريا ً .
ز -أن يتم صيانة المصاعد بصفة دورية .
ح – دهان الخطوط الموجودة بأرضية الموقف دوريا ً .
– 3 – 7مكتب خدمة الموقف
أ – أن يتم توفير مكتب لخدمة ا لموقف وذلك في المواقف العامة على أن يكون بموقع يشرف على حركة الدخول
والخروج .
ب -أن تكون مسئولية المكتب مالحظة السيارات بالموقف ومراقبة الدخول والخروج ،باإلضافة إلى اإلشراف على
صيانة الموقف وتوفير المتطلبات الضرورية لتشغيله على أفضل وجه .
SHO
ME
ART
PS (1
AP
)
SHOPS
OFFICE
PAR
SUPER MARKET
KING
MAR
APARTMENTS
MOS
SUP
LOT
PARK
KET
QUE
(11)
ER
VILLA
(3)
(10)
PLOT BOUNDARY
MOSQUE
PARKING LOT
EXISTING
RECOMMENDED
SHO
PAR
VILL
PS (4
K (9
AS (7
SHO
)
PS (2
)
)
OFF
ICE
(5)
VILL
AS
(8)
Plots Land Use Land Use Code 1 Independent Variable Used Land Use Intensity for Trip Generation Total Area (Sq. m) Total Trips Generated 2 (vph)
THE SITE
SIGN POST
THE SIGNAL HEADS
SIT
E
Site Location
After Mitigation
THE
SIT
E KINGDOM OF SAUDI ARABIA
MINISTRY OF INTERIOR
Before Modifications
PLOT BOUNDARY
PAINTED AREA
COLUMN
WALL
HANDICAP STALLS
UP
DOWN
Site Location
UP
DOWN
1:15
After Modifications
PLOT BOUNDARY
PAINTED AREA
COLUMN
WALL
HANDICAP STALLS
UP
DOWN
Site Location
UP
DOWN
1:15
(6)
NTS
SHO
ME
ART
PS (1
AP
)
SHOPS
OFFICE
PAR
SUPER MARKET
KING
MAR
APARTMENTS
MOS
SUP
LOT
PARK
KET
QUE
(11)
ER
VILLA
(3)
(10)
PLOT BOUNDARY
MOSQUE
PARKING LOT
EXISTING
RECOMMENDED
SHO
PAR
VILL
PS (4
K (9
AS (7
SHO
)
PS (2
)
)
OFF
ICE
(5)
VILL
AS
(8)
Plots Land Use Land Use Code 1 Independent Variable Used Land Use Intensity for Trip Generation Total Area (Sq. m) Total Trips Generated 2 (vph)
THE SITE
SIGN POST
THE SIGNAL HEADS
SIT
E
Site Location
After Mitigation
THE
SIT
E KINGDOM OF SAUDI ARABIA
MINISTRY OF INTERIOR
Before Modifications
PLOT BOUNDARY
PAINTED AREA
COLUMN
WALL
HANDICAP STALLS
UP
DOWN
Site Location
UP
DOWN
1:15
After Modifications
PLOT BOUNDARY
PAINTED AREA
COLUMN
WALL
HANDICAP STALLS
UP
DOWN
Site Location
UP
DOWN
1:15