PRE-CONSTRUCTION PHASE
OCT OCT OCT OCT NOV NOV NOV SUN MON TUES WED THUR FRI SAT SUN MON TUES WED THUR FRI SAT COMPLETION
START DATE WORK RESOURSE DURATION STATUS (BY NOTES
PERCENT)
10/6/2023 10/16/2023 10/18/2023 10/24/2023 11/16/2023 11/20/2023 11/25/2023 11/26/23 11/27/23 11/28/23 11/29/23 11/30/23 12/01/23 12/02/23 12/03/23 12/04/23 12/05/23 12/06/23 12/07/23 12/08/23 12/09/23
PRE-CONSTRUCTION PHASE Dates (MM/DD/YY) below will automatically populate beginning with the Start Date entered above. Days of the week need to be updated manually.
SUN MON TUES WED THUR FRI SAT SUN MON TUES WED THUR FRI SAT SUN MON TUES WED THUR FRI SAT COMPLETION
START DATE WORK RESOURSE DURATION STATUS (BY NOTES
PERCENT)
03/07/27 03/08/27 03/09/27 03/10/27 03/11/27 03/12/27 03/13/27 03/14/27 03/15/27 03/16/27 03/17/27 03/18/27 03/19/27 03/20/27 03/21/27 03/22/27 03/23/27 03/24/27 03/25/27 03/26/27 03/27/27