Office365 Project Schedule Template
Office365 Project Schedule Template
Office365 Project Schedule Template
1
2 DESIGN, PLAN 42 days
3 Hold project kickoff meeting 1 day
4 Build risk and issue tracking system 1 day
5 Develop Notes to O365 migration strategy 5 days
6 Identify the email coexistence strategy 1 day
7 Document all namespaces and domain names moving forward - UPN, SIP domain 5 days
8 Document forwarding namespace for Notes to Mimecast for migrated users 5 days
9 Plan DNS entries for O365 15 days
10 Plan DNS entries for Lync, Exchange & ADFS - Autodiscover, Outlook Anywhere, Federation 15 days
25 Define user migrations in batches and document VIPs, managers and associated admins 15 days
29 Communicate plans to team and get sign off from sponsor - handled with deliverables 1 day
60 Identify ADFS IP addresses, ports, virtual IPs for HW loadbalancer for network changes 2 days
61 Audit ADFS servers and check for any required service packs 1 day
62 Submit change requests for ADFS service pack updates and network updates 1 day
63 Complete ADFS service pack updates 1 day
64 ADFS changes to firewalls and NAT 1 day
65 Install second ADFS server and ADFS proxy servers (Dii side) 3 days
66 Setup O365 Exchange Online/Skype Online 1 day
67 Skype SIP domain - define valid SIP domains based on logon UPN 1 day
68 Client connectivity firewall port changes from Internal to O365 5 days
69 Infrastructure firewall port changes from internal & DMZ to O365 5 days
70 Configure ADFS for SSO with Azure AD 3 days
71 Enable single sign-on (identity federation) 3 days
72 Prepare your on-premises Active Directory for directory synchronization to Azure 22 days
73 Install the Directory Synchronization Tool and perform synchronization 22 days
74 Validate Dir Sync 1 day
75 Resolve open DirSync issues 2 days
76 Buy, Mint, Install certificates for Exchange, Skype for O365 2 days
77 Configure O365 Exchange - Connectors, mail flow, mobile 3 days
78 Configure O365 webservices for Exchange hybrid 2 days
79 Run hybrid configuration wizard for Exchange hybrid 3 days
80 Testing Outlook, F/B and Mail Flow 7 days
104 Communicate Development completed tasks to team and sponsors - Covered in meetings 1 day
111 Send out initial communications to users with dates - one mon, three wks, one wk 54.6 days
115 Reminder migration date and Instructions on first use sent to users 34 days
116 Migration from Notes to Exchange, 30 days mail, calendar, contacts 7 days
117 Assign licenses to users in O365 27 days
118 Sync mailbox data to Mimecast 20 days
119 Mailbox-enable all Ingredients users in O365 Exchange and change targetaddress to point to 28 days
Notes address (prep)
120 Change DNS records for Exchange O365 2 days
121 Change Internal and External Skype DNS entries to point to O365 2 days
122 Enable/Configure Exchange Activesync policies per BYOD policies per user or group 2 days
123 Reminder migration and Instructions for Mobile configuration sent to users 25 days
124 Order new devices/adjust plans to allow data (BB users) 35 days
125 Configure mobile phones and devices for Office 365 36 days
126 Change SMTP address and addressbooks for multi-functionals 25 days
127 Migrate calendar & contacts to O365 Exchange mailboxes (Quest migration) 25 days
128 Location1 migration from Notes to O365 (M1) 1 day
129 Location2 migration from Notes to O365 (M2) 12 days
138 Move users from Exchange to O365 2 days
139 Modify Notes person doc to be other internet person 27 days
140 Remove "targetaddress" from migrated user account to accept inbound email 26 days
141 Collect mobile devices 23 days
142 Milestone: Sync Mailboxes 0 days
143 Milestone: Location1 Migrated 0 days
144 Change DNS records for Exchange O365 - after migrations are completed 2 days
145 Milestone: Location2 Migrated 0 days
153 Milestone: Phone Migration Complete 0 days
154
155 HYPERCARE, STABILIZATION 62 days
156 Perform post-migration service testing 10 days
157 Welcome message and FAQs sent to users 52 days
158 Coordination to direct multi-functional devices to the new mail servers 25 days
159 Hypercare 60 days
160 Milestone: User Training and Hypercare Ends 0 days
161
1/31/2014 3/31/2014 0%
1/31/2014 1/31/2014 0%
1/31/2014 1/31/2014 3SS 0%
2/3/2014 2/7/2014 3 0%
2/6/2014 2/6/2014 3FS+3 days 0%
2/10/2014 2/14/2014 6FS+1 day 0%
2/10/2014 2/14/2014 7SS 0%
2/10/2014 2/28/2014 7SS 0%
3/11/2014 3/11/2014 28 0%
2/6/2014 5/20/2014 0%
3/17/2014 5/16/2014 19FS+27 days 0%
3/17/2014 5/16/2014 38SS 0%
2/10/2014 2/14/2014 3FS+5 days 0%
2/10/2014 2/12/2014 40SS 0%
2/14/2014 2/14/2014 45FF 0%
2/10/2014 3/14/2014 40SS 0%
2/10/2014 2/28/2014 47SS 0%
3/3/2014 3/3/2014 48 0%
3/18/2014 3/18/2014 48 0%
3/3/2014 3/3/2014 48 0%
2/6/2014 3/20/2014 3FS+3 days 0%
2/10/2014 2/27/2014 52SS+2 days 0%
2/10/2014 2/27/2014 52SS+2 days 0%
2/14/2014 2/14/2014 15FS-1 day 0%
2/18/2014 3/17/2014 7SS+6 days 0%
3/18/2014 3/24/2014 56 0%
3/3/2014 3/3/2014 54FS+1 day 0%
3/4/2014 3/5/2014 59 0%
3/6/2014 3/6/2014 60 0%
3/7/2014 3/7/2014 61 0%
3/13/2014 3/13/2014 62FS+3 days 0%
4/4/2014 4/4/2014 63FS+15 days 0%
3/17/2014 3/19/2014 63FS+1 day 0%
3/20/2014 3/20/2014 65 0%
3/20/2014 3/20/2014 65 0%
3/21/2014 3/27/2014 66 0%
3/21/2014 3/27/2014 66 0%
3/20/2014 3/24/2014 65 0%
3/20/2014 3/24/2014 70SS 0%
2/20/2014 3/21/2014 52SS+10 days 0%
2/20/2014 3/21/2014 52SS+10 days 0%
3/24/2014 3/24/2014 73 0%
3/25/2014 3/26/2014 74 0%
3/27/2014 3/28/2014 75 0%
3/31/2014 4/2/2014 47,76 0%
4/2/2014 4/3/2014 77FS-1 day 0%
4/4/2014 4/8/2014 78 0%
4/1/2014 4/9/2014 0%
3/10/2014 6/10/2014 0%
3/21/2014 6/5/2014 0%
4/14/2014 4/15/2014 90 0%
4/16/2014 4/17/2014 120 0%
4/16/2014 4/17/2014 120 0%
5/2/2014 6/5/2014 128SS-1 day 0%
3/10/2014 4/25/2014 34 0%
4/18/2014 6/6/2014 124FS-6 days 0%
5/5/2014 6/6/2014 128SS 0%
5/5/2014 6/6/2014 0%
5/5/2014 5/5/2014 0%
5/5/2014 5/20/2014 128SS 0%
6/9/2014 6/10/2014 137 0%
5/5/2014 6/10/2014 128SS 0%
5/5/2014 6/10/2014 128SS 0%
5/9/2014 6/10/2014 128FS+3 days 0%
4/1/2014 4/1/2014 118FS-4 days 0%
4/4/2014 4/4/2014 116 0%
5/28/2014 5/29/2014 137 0%
5/5/2014 5/5/2014 128 0%
6/10/2014 6/10/2014 141 0%
3/27/2014 6/20/2014 0%
6/9/2014 6/20/2014 136 0%
3/27/2014 6/6/2014 116SS 0%
5/6/2014 6/9/2014 145 0%
3/31/2014 6/20/2014 143FS-5 days 0%
6/20/2014 6/20/2014 159FF 0%
1/31/2014 6/27/2014 0%
1/31/2014 6/20/2014 0%