MATERIAL LAYDOWN FOR

THE RDMP PROJECT RU V


BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 1 of 5

Work Method

Instalasi Kabel FO Shelter CCTV – Server Rack Office

PROJECT : Replace Radio Backup Link JO 75


LOCATION : RDMP JO office 75 , East Kalimantan,Indonesia
OWNER : RDMP JO

7 Novemeber
001 ACTIVITY PREVIEW Pandu Rahutomo Hasbianur Rasyid
2022

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED


MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 2 of 7

REVISION LOG

REV. NO. DATE PAGE DESCRIPTION

7 NOVEMBER
001 ACTIVITY PREVIEW
2022

2
MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 3 of 7

TABLE OF CONTENTS
1. PURPOSE & SCOPE.......................................................................................................................... 4
2. WORK STEP....................................................................................................................................... 4
3. NEEDS................................................................................................................................................ 4

3
MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 4 of 7

1. PURPOSE & SCOPE

The main task / target are installing fiber optic cable 4 core from Server rack office JO 37 to CCTV shelter
tower JO 37

2. WORK STEP

A. Land Preparation

Check safety equipment (Helmet, Full Body Harness,Hand gloves,Safety shoes)

Check all tools (Put tools to bag)

Make sure work area is clear and no other disturbing activity

B. Prepare to Climb

Make sure manpower is in FIT condition and wear all safety equipment (Helmet, Full Body

Harness,Hand gloves,Safety shoes)

Install Stair at Pole or tower make anchor point for secure the stair/ledger

C. Climb

Climbing the Leadger/Stair makesure three point contact is fully implemented, and bring down all

equipment,

E. Install Radio To tower

* Climb the stair and install cable hanger in every poles

* Install Media converter and Slicing FO in box tower

* Install Media converter in office rack

F. Test Link

Make sure all configuration is working well and link work properly, Test Bandwidth

4
MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 5 of 7

NEEDS

2.1. In this work must be considering to several aspects.

Considered including:

a. Materials

b. Equipment

c. Labour with full standard safety as the work.

Three aspects above must be considered and prepare before work casting is done.

3. K3 ANALYSIS

Personnel

• Supervisor

• Safetyman

• Qualified Manpower (certified with working at height)