MS Loading Unloading and Material Arrangement JO 37 Fiber Optic
MS Loading Unloading and Material Arrangement JO 37 Fiber Optic
Work Method
7 Novemeber
001 ACTIVITY PREVIEW Pandu Rahutomo Hasbianur Rasyid
2022
REVISION LOG
7 NOVEMBER
001 ACTIVITY PREVIEW
2022
2
MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 3 of 7
TABLE OF CONTENTS
1. PURPOSE & SCOPE.......................................................................................................................... 4
2. WORK STEP....................................................................................................................................... 4
3. NEEDS................................................................................................................................................ 4
3
MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 4 of 7
The main task / target are installing fiber optic cable 4 core from Server rack office JO 37 to CCTV shelter
tower JO 37
2. WORK STEP
A. Land Preparation
B. Prepare to Climb
Make sure manpower is in FIT condition and wear all safety equipment (Helmet, Full Body
Install Stair at Pole or tower make anchor point for secure the stair/ledger
C. Climb
Climbing the Leadger/Stair makesure three point contact is fully implemented, and bring down all
equipment,
F. Test Link
Make sure all configuration is working well and link work properly, Test Bandwidth
4
MATERIAL LAYDOWN FOR
THE RDMP PROJECT RU V
BALIKPAPAN
Doc. No.: Instalasi Kabel FO Shelter Rev No.: 000
Job No.: CCTV – Server Rack Office Page: 5 of 7
NEEDS
Considered including:
a. Materials
b. Equipment
Three aspects above must be considered and prepare before work casting is done.
3. K3 ANALYSIS
Personnel
• Supervisor
• Safetyman