Professional Documents
Culture Documents
CERT-12 - ZZ01.0 - Exercise 04 - FPSO and Metering
CERT-12 - ZZ01.0 - Exercise 04 - FPSO and Metering
1) For an FPSO, what are the 2 solutions (options) to obtain the hull
2) For a converted tanker into an FPSO, where are located the oil cargo pumps?
Speed mooring
x
Spread mooring
Internal sprig
Free mooring
Distributed mooring
x
Single point mooring - Internal turret
Sprig mooring
Peripheral mooring
External sprig
x
Single point mooring - External turret
4) Which mooring system is recommended to moor a large FPSO in the Gulf of Guinea
Sprig mooring
x
Spread mooring
Speed mooring
Weathervane mooring
Single point mooring -
5) Which mooring system is recommended to moor a large FPSO in the Gulf of Mexico
Sprig mooring
Spread mooring
Speed mooring
x
Single point mooring -
6) For an FPSO, what are the 2 recommended means that allow mooring and loading a crude oil tanker
1
Dynamic positioning loading
x
Direct loading of a tanker in tandem
Direct loading of a tanker side by side
Subsea loading
x
Loading of a tanker via a loading buoy
Loading of a tanker via a floating jetty
7) Indicate the right order to arrange safely the main modules on the FPSO main deck. Right order starting
from the Leaving Quarter LQ (main wind from LQ side)?
Modules to be arranged: Lay down area, Flare stack module, Leaving Quarter module, Oil treatment
modules, Utilities modules, Gas compression modules (give the order number from stern to the bow)
9) On a commercial metering unit, each line is fitted with turbine meter. Which main parameters are
measured and recorded by the line computer from that?
x
Water content / BSW
Number of turns of the turbine
x
Sample volume
Temperature of the oil
x
Oil density
Pressure of the oil
x
Emulsion quantity
10) On a bi-directional proving loop which parts delimit the reference proving volume?