Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 29

Document Risk Assessment

Abu Dhabi Future School Program - Phase 8,


Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

Project Abu Dhabi Future School Program - Phase 8, Package 1, Al  Falah KG

Employer MUSANADA Contract No.

Consultant: Al Suweidi Engineering Consultant LLC Date:

Contractor Al Eslah General Contracting Est Document No.

RISKASSESSMENT TEAM SITE REPRESENTATIVES

NAME DESIGNATION SIGNATURE NAME DESIGNATION SIGNATURE

Eng. Ayham Sabouni Project Manager Ahmed Hajeer Project Engineer

Eng.Zafeer Arif OSH Coordinator

Subject RISK ASSESSMENT for Production Delivery Installation of Hollow Core Elements

NOTE:- This Risk Assessment is prepared in line with the METHOD STATEMENT for Production Delivery Installation of Hollow Core Elements
Rev. 00; and it covers all activities described in this Method Statement.

Page 1 of 1
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Site OSH induction course for every


Parking at live worker working in this project.
road to drop or  Bus should be park at safe area with
carry workers. double indicators and gate should not OSHAD-SF– Codes
open until bust fully stop. Construction of Practice CoP
Unfamiliar with the
local situation and  Worker should not cross the road manager, 44.0 Traffic
the Safety rules until bus is move from road to clear Management and
OSH In Logistics – Version
1 sight for upcoming traffic.
Unfamiliar to the charge, 3.0
Mobilization of  Proper training and guidance for all
nature of work and Employees 3 2 6 M 1 1 1 L
Employees new workers HR staff,
weather condition OSHAD-SF –
 Minimum PPE must be worn at all Supervisor Codes of Practice
Lack of training times CoP 08.0 – General
&
 Follow site safety rules Workplace
Younger workers  Follow the traffic safety regulations Individuals Amenities – Version
Medically not fit  Medical Check up to be done 3.0
 Special care for young people and
should not be involved in high risky
work

1 Preparing the General Factory Workers, staff, 3 4 12 H  All Personnel involved in the activities HSE officer. 1 3 3 L OSHAD SF- Pre-
hollow core bed Hazards ,Person visitors, must be HSE Inducted. Cast Construction-
environment Supervisor. V 3.0- July 2016
al Injuries,  MS & RA to be briefed out to all
Property personnel & should be available at Site
Damage factory. engineer OSHAD SF-
 Supervisors/Foreman communicates Hazardous
hazards, Risk involved and the Materials- V 3.0-
sequence of work to the work force July 2016

Page 1 of 2
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

BEFORE activity starts.


 Weekly Tool Box Talks (TBTs)
 Adequate Supervision
 Compliance with PPE
 Certified equipment and operators
(Third party certificates).
 Regular maintenance schedule for
equipment and tools.
 MSDS to be available for materials &
COSHH training to be given for using
the hazardous/ chemical materials.
 Emergency numbers posted on sign
boards at clear location.
 Smoking is only allowed at smoking
areas

2 Working at Slip, fall, personal Workers, staff, 3 3 9 M  No work shall be carried out in dark Supervisor. 1 3 3 L OSHAD SF-
Night, poor injuries, visitors area. Adequate task lighting must be General Workplace
illumination HSEO, Site Amenities- V 3.0-
damaged and provided and in such a way it does
engineer July 2016
defective not cast shadows around the work
product area.

3 Applying mold Unsafe handling Workers, staff 3 4 12 H  Trained and competent persons Supervisor. 1 3 3 L OSHAD SF-
releasing agent of chemical. handle the chemicals. Hazardous
Operatives Materials- V 3.0-
Hand skin  Chemical should be stored at
allergy, eye designated area in the dip trays. Storekeeper July 2016
injury,  Eye protection must be used and

Page 1 of 3
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

provided eye wash facility.


 All chemicals must be received,
stored and handled according to
prescribed procedures in the MSDS.
 MSDS briefing conducted to work
force by supervisor & HSEO.

4 Damaged power Injury to person, Workers, staff 3 4 12 H  All electrical equipment’s must be Maintenance 1 3 3 L OSHAD SF-
tools, untrained electrocution, inspected on regular basis including dept. Portable Power
persons, sockets, cables, and discs. Tools- V 3.0- July
HSE officer. 2016
 All users must be trained and
competent for using the portable Supervisor. OSHAD SF- 15.0
electrical equipment. Electricity- V 3.0-
Operatives
 Suitable grinder’s discs must be used July 2016
for the grinding works.
 All hot works must be provided with OSHAD SF- Permit
approved hot works permit. to Work Systems- V
 Suitable and appropriate PPE must 3.0- July 2016
be used prior using the electrical
equipment’s.
 Exclusion zone with sign board must
be posted in the workplace area.
 Management cable must be managed
to avoid any tripping hazards in the
workplace.
 Only the allowed voltage of the
project requirements must be used for

Page 1 of 4
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

the electrical equipment’s.


 Fire equipment’s, (extinguishers,
blankets, sand bucket etc.) must be
available in the workplace prior
staring the work.
 Trained fire watcher must be
available in the workplace area.
 All the portable power tools will be
110 volt.
 Dead man switch should be available
on the power tools.

5 Pre-stressing, Serious Injuries Workers, staff, 3 4 12 H  Only competent personnel are Supervisor. 1 3 3 L OSHAD SF- Pre-
Pre-tensioning of Fatalities visitors, allowed to perform the stressing Cast Construction-
strands, casting Operatives. V 3.0- July 2016
activity.
and concreting  Hydraulic jack machine must be HSE officer. OSHAD SF-36.0
regularly inspected and 3rd party Plant and
certified must be available. equipment V 3.0-
 Operators for the hydraulic jack July 2016
machine must be 3rd party certified
and competent.
 During the stressing, no full exclusion
zone must be provided around the
area and unauthorized personnel
should not be allowed to enter the
area.
 Ensure that the alarm is working

Page 1 of 5
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

immediately prior staring the stressing


to caution the factory personnel and
unauthorized persons.
 Ensure that the protection steel fence
is provided at end area where the
competent persons start the stressing
of the strands.
 Ensure that a proper and suitable
PPE is worn by the users while
performing the stressing activity.
 Ensure that HSE personnel and
supervisor shall be available in the
area to prevent people from entering
the lifting zone.

6. Curing of Personal Injuries, Workers, staff, 3 3 9 M  All personnel must be keeping away Supervisor. 1 3 3 L OSHAD SF- Pre-
Precast Boiler leak and visitors, from steam to avoid skin burn. Cast Construction-
elements-steam environment Maintenance V 3.0- July 2016
explosion,  All steam distribution line must be
curing by boiler dept.
Environmental periodically inspected and repaired by
OSHAD SF-36.0
issues the competent person. Operatives. Plant and
 Sign boards and must be posted and equipment V 3.0-
HSE officer.
isolation must provide. July 2016
 Boiler must be controlled and
operated only by the competent
personnel. And should have 3rd party
certificate
 Fire equipment’s must be provided

Page 1 of 6
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

and inspected regularly.


 Responsible persons with contact
numbers must be posted for any
emergency cases.
 Regular clean up and slope floor to
prevent the contamination of the
water during the curing process
should be provided and in place.
 No personnel are allowed to enter the
area during the curing process.
 Wear suitable PPE.
 Boiler must be 3rd party inspected &
tested.
 Boiler area should have hard
exclusive zone and should be locked.

7. Storage of Personal Injuries Workers, staff, 3 4 12 H  Procedures should be in place for Supervisor. 1 3 3 L OSHAD SF- Pre-
hollow core Property Damage visitors, parking of vehicles in and around/in Cast Construction-
slabs in the environment Logistic V 3.0- July 2016
Obstruction of the factory.
factory officer.
assigned  Involved Engineer will coordinate with
emergency Logistics Officer for allocation of HSE officer
routes unloading and storage area.
 Physical/ hard barriers to be installed.
 Provide adequate signage.
 Route maps with identification points
should be clearly displayed
 Signs and notices should be in place

Page 1 of 7
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

setting out standards and controls.


 Do not store or stack the materials on
the access.
 Arrange or stack the materials
properly with wooden package under
the hollow core slabs, in order to
avoid the collapse.
 Slabs to be stacked safely so that
there is no risk of falling on personnel,
damage to property etc.

8 Lifting activity, Personal Workers, staff, 3 4 12 H  Competent and certified riggers will Supervisor 1 3 3 L OSHAD SF- Safe
lifting the hollow Accidents arising visitors, be provided. HSE officer. Use of Lifting
core slabs to the from: environment  All persons/workers must be trained Rigging Equipment and
trailer. Slips, trips and on MSRA prior to commencing any supervisor. Lifting Accessories-
falls. loading, unloading and erection of Project V 3.0- July 2016
manager.
Unsafe lifting lead precast elements. OSHAD SF- Plant
Operator.
to fall of  Rigger to communicate to Crane and Equipment- V
materials, crane operator via radio transmitter. 3.0- July 2016
collapse.  Rigging Supervisor should control the
Vehicle impact whole lifting activity.
Plant impact  No workers are to commence lifting
Falling from back operation without adequate
of delivery supervision.
vehicles.  The operator and crane should have
Crash injuries ADM approved valid 3rd party
Pinch point to certificates.

Page 1 of 8
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

body.  Provide proper exclusive zone with


signage for lifting area.
 All the lifting gears should have ADM
approved valid 3rd party certificate.
 Properly maintain the weekly check
list for the lifting tackles.
 The construction manager is
responsible for all activities related to
erection and must comply with the
Method Statement.
 Taglines to be connected to the load
in order to control the load to prevent
swinging / swaying during lifting
operation.

9. Transporting of Personnel being Workers, 3 4 12 H  Only Driver with the correct license Supervisor 1 3 3 L OSHAD SF- Traffic
hollow core struck by drivers, staff, code with valid license will be allowed Logistic Management and
elements from reversing/ public, to drive delivery vehicle/ trailer. officer Logistics- V 3.0-
the factory to the maneuvering  Necessary permit required for Drivers July 2016
project using vehicles, transporting odd size element must
flatbed trailer Fall of materials be obtained.
from the trailer.  Driver must be following the
maximum speed limit for heavy
vehicle.
 Provide Banks man with trailer for
signaling in the factory and site areas.
 Reverse alarm and bacon light should

Page 1 of 9
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

be on the trailer.
 Precast element must be loaded and
straps correctly to avoid movement
causing damage or loss of load while
in transit on the way to the site.
 Correct type of lashing, straps must
be used for heavy precast elements
load.

Oil leak from 3 3 9 M  Only delivery vehicle with valid Loading 1 3 3 L OSHAD SF- Traffic
defective/ poorly registration license will be used for Supervisor Management and
maintained deliveries of Precast Element to site. Logistics- V 3.0-
Logistic July 2016
transport vehicle  Drivers must ensure that delivery
officer
vehicle has been inspected daily to
ensure it is in good condition before Drivers
loading and transporting the elements
on to the site.
 Driver should maintain the inspection
checklist of the trailer.
 In case of any spillage from the
vehicles contaminated soil must be
properly disposed and spill kit must
be provided by Main Contractor.

10 Arrival of Personal Injuries Workers, staff, 3 4 12 H  All workers must have a valid EID and Supervisor 1 3 3 L OSHAD SF- Permit
personnel at Property Damage visitors, Insurance card. to Work Systems- V
site. Check work environment Logistic 3.0- July 2016
 PTW controls.
location for  All the vehicles in the working area

Page 1 of 10
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

space and should have reverse alarm. officer OSHAD SF- Safe
obstacles. Enter  All persons should undergone site Use of Lifting
work location HSE officer Equipment and
HSE induction.
with assist crane  Conduct TBT prior to start the Job. Operatives Lifting Accessories-
and trailers. Rig  Mandatory PPE shall be worn by all V 3.0- July 2016
cranes at lifting personnel.
location. Set up OSHAD SF- Plant
 All equipment/ vehicles inspected and and Equipment- V
cranes at lifting
approved by HSE/logistic dept. 3.0- July 2016
location.
 All operators shall have approved
operator license & 3rd party
certificates.
 All personnel to be fully briefed on
tasks and responsibilities
together .with the correct use of PPE
& job related training.
 Prepare ground in advance. Verify
ground bearing pressure with client.
 No fuel filling when machine is
running/hot.
 Unauthorized entry of personnel to be
restricted.
 Thorough visual inspection of the
area and ground conditions to be
carried out.
 Temporary warning signs.
 Proper traffic management.

Page 1 of 11
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Supervisor ensures designated


loading & offloading areas.

11. Set up the Personnel being Workers, staff, 3 4 12 H  All personnel involved in crane lifting Supervisor 1 3 34 L OSHAD SF- Plant
delivery vehicle visitors, Public, HSE officer 4 and Equipment- V
struck by operations must be trained with
in designated reversing/ environment specific method statement risk Operators 3.0- July 2016
safe offloading maneuvering assessment.
zone OSHAD SF- Traffic
vehicles. Vehicle  Toolbox talk/ Daily safety task Management and
or falling into instruction must be done daily before Logistics- V 3.0-
excavations. work commence. July 2016
 The delivery vehicle must park on firm
level ground.

12. Set up the Personnel injury Workers, staff, 3 4 12 H  Ground must be compacted and Supervisor 1 3 3 L OSHAD SF- Safe
mobile crane from lifting plant visitors, Public, leveled prior set up of the crane. L
Use of Lifting
and correct type environment HSE officer Equipment and
& equipment  The lifting zone must be isolated with
of lifting failure warning tape or nylon rope with Operators Lifting Accessories-
equipment warning tape and appropriate safety V 3.0- July 2016
signage must be posted. OSHAD SF- Plant
 Unauthorized personnel should not and Equipment- V
be allowed inside the exclusion zone. 3.0- July 2016
 All lifting plant & equipment must be
inspected by the competent person
and the copy of 3rd party certificate
must be valid and available.
 All crane operator and rigger man
must have a valid ADM approved 3rd

Page 1 of 12
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

party certificate
 Mobile crane out riggers must be fully
extended and seated in leveled and
compacted ground with proper
outrigger board/pad/plate.
 No curtains or any means of vision
barriers will not be allowed on
drivers / operators cabin.

13. Stacking and Personnel injury Workers, staff, 3 4 12 H  Stacking of Precast Element must be Supervisor 1 3 3 L OSHAD SF- Pre-
Storage of from material visitors, leveled ground condition. Otherwise Cast Construction-
hollow core collapse of environment direct installation from delivery vehicle V 3.0- July 2016
slabs Precast will be done to avoid stacking on site.
Elements  Supervisor must ensure that ground
materials condition is leveled, firm and
compacted to prevent collapse.
 Stacking area must be isolated from
pedestrian with hard barricade.

14. Lifting of the Personnel injury Workers, staff, 3 4 12 H  Lifting supervisor will ensure that all Lifting 1 3 3 L OSHAD SF- Safe
hollow core from lifting plant visitors, lifting plant & equipment must be supervisor Use of Lifting
slabs from & equipment environment inspected daily before use and 3rd Equipment and
designated Operators Lifting Accessories-
failure or unsafe party certificate must be valid and
stacking area. operation available. V 3.0- July 2016
 lifting the hollow core slabs from the
trailer the lifting clamps or belts shall

Page 1 of 13
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

be placed at a distance of 700-


800mm from the end of the slabs
 Lifting supervisor will ensure that
crane operator and rigger/ banks man
must have a valid 3rd party certificate.
 Pre use visual inspection of the slings
and lifting tackles.
 Follow the proper color code on the
lifting tackles.
 Crane operator and rigger/ banks
man must establish effective
communication.

15. Disconnecting Personnel injury Workers, staff, 3 4 12 H  Supervisor to ensure that work at Supervisor 1 3 3 L OSHAD SF- Safe
the sling from from falling from visitors, heights must be provided with fall Use of Lifting
the Precast environment HSE officer Equipment and
heights protection such as edge protection
Element lifting otherwise must be used when edge Operatives Lifting Accessories-
points protection in not possible to put in V 3.0- July 2016
place. OSHAD-SF– COP
 Everyone should be trained for the 23.0 – Working at
use of safety harness and retractable Heights– V 3.0
lanyard using.
 In case of ladder will be used to reach
the lifting points the length of ladder
must be at least 3 rungs/ steps higher
than that of the working platform, over
reaching should be avoided when

Page 1 of 14
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

using ladders at height.


 The tag lines must be connected to
both ends of the long Precast
Element/ hollow core element for
better control while suspended in the
air beyond hand reach.

16 Moving Man-machine Workers, staff, 3 4 12 H  Provide separate access for Supervisor 1 3 3 L OSHAD SF- Traffic
vehicle’s, interface/Vehicle visitors, pedestrian and vehicle traffic. Management and
equipment’s environment HSE officer Logistics- V 3.0-
/ Plant impact  Keep plant away from traffic and
operatives e.g. Physical barriers, Logistic July 2016
banksman. officer OSHAD SF- 53.0
 Drivers trained on site requirements. EHS management
Operatives
 Minimize the need for plant to reverse during construction
e.g. arrange for drive in, stop and work- V 3.0- July
drive out. 2016
 All reversing operations to be under
the control of trained and competent
Banksman.
 Operators to be made aware of
vehicle routs and other operations
close to plant.
 Beacon light and reverse alarm
should be on the all vehicles and
equipment’s.
 Procedures should be in place for
parking of vehicles in and around the

Page 1 of 15
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

site.
 Site Engineer will coordinate with site
Logistics Officer for allocation of
unloading and storage area

17 Unsafe stacking Obstruction of 3 3 9 M  Route maps with identification points Main 1 3 3 L OSHAD SF- 17.0
of materials on assigned should be clearly displayed by Main contractor Safety signage and
the access. emergency Contractor. HSE officer signals- V 3.0- July
routes  Signs and notices should be in place 2016
setting out standards and controls. Element6-
 Do not stack any materials or park Emergency
any vehicles on the emergency route. management
18 Manual handling Personal Injuries Workers, staff, 3 3 9 M  Ensure trailer/pickup is parked on Supervisor 1 3 3 L OSHAD SF- Manual
of various such as cuts and visitors, even and compacted ground. Handling and
materials for environment HSE officer Ergonomics- V 3.0-
abrasions  Ensure that only one trailer at a time
unloading and involving upper is being offloaded. Operatives July 2016
erection body and limbs;  Ensure that sufficient area behind the
activities. strains, muscle, trailer is available for offloading the
muscle injuries plant.
or fractures,  Ensure that the truck/trailers properly
either as a result secured when offloading.
of falls or  Ensure that operators are wearing
dropping heavy appropriate PPE and Hi visibility
objects. vests.
 Operators shall not use mobile
phones during driving and during the

Page 1 of 16
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

offloading operation.
 Cranes/ equipment’s glass should not
be covered/ curtained.
 Use of mechanical means to move
material is preferred.
 Gloves are mandatory and must be
worn to protect against cuts,
scratches and punctures.
 Workers to ensure that there are no
obstructions in the direction they will
be carrying the load.
 Workers to ensure that they know the
approximate weight of the load prior
lifting.
 Workers to take position bend knees
and secure grip of the load being
lifted. Lift the load keeping back
straight, arms close to body and
strong leg muscles to take the strain
of the load.
 Worker must not carry a load which
obstructs vision. Use mechanical aid
such as trolleys.
 Worker should avoid twisting the
trunk whilst lifting or carrying a load.
 Worker shall seek assistance if the
load is too heavy. Supervisor to

Page 1 of 17
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

promote team lift.


 Safety boots or shoes must always be
worn to protect toes from falling
loads.

19 Lifting and Failure to follow Workers, staff, 3 4 12 H  No workers are to commence lifting PM,CM, 1 3 3 L OSHAD SF- Safe
erection method visitors, Public, operation without adequate Use of Lifting
activities of environment Supervisor Equipment and
statement supervision.
hollow core instruction.  The construction manager is Lifting Accessories-
element. Fatality, Personal responsible for all activities related to V 3.0- July 2016
Injuries. erection and must comply with the OSHAD SF- 22.0
Fall/collapse of Method Statement & Risk barricading of
element from the Assessment. hazards- V 3.0- July
crane  Supervisor to provide necessary 2016
Property Damage briefing on Method Statement to
workforce on daily basis. OSHAD-SF– COP
23.0 – Working at
 Supervisor to check the sequence of
Heights– V 3.0
work and must keep it safe.
 MS, RA, check list etc. should be
available at work location.
 Ensure use of safe scaffolds and
green tag on the scaffold prior to use
it.
 Wearing the full body harness with
double lanyard and securing it at all
the times, provide certified fall
arrestor system in case the full body

Page 1 of 18
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

harness is not suitable.


 No loads are to be passed over the
heads of workers/public – the lifting
area is to be kept clear at all times.
 All loose materials in work area shall
be removed prior to work and while
working on edge, all small tools must
be secured by nylon rope to prevent
form falling down.
 Proper exclusive zone with signage’s
for the lifting area.
 Proper communication and signaling
to the operator.
 Supervisor to ensure that work at
heights must be provided with fall
protection such as edge protection
otherwise must be used when edge
protection in not possible to put in
place.
 Adequate Fall protection measures to
be implemented to ensure that there
is no risk for the erectors.
 Certified fall arrestor system and life
to be used in addition to the safety
harness.

Incorrect position Workers, staff, 3 4 12 H  3rd party certificates required for Lifting 1 3 3 L OSHAD SF- Plant

Page 1 of 19
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

of Crane during visitors, Public, crane and operatives. Supervisor and Equipment- V
lifting operation. property  Daily inspection to be conducted by 3.0- July 2016
Operators
operatives. Keep record of daily
OSHAD SF- Safe
inspection.
Use of Lifting
 All working platforms must be Equipment and
compacted and leveled prior to the Lifting Accessories-
commencement of erection. V 3.0- July 2016
 The Site / Erection Engineer / Mobile
Crane Operator to ensure that the
crane outrigger placement area is
free from any underground utilities /
buried services.
 Outriggers must be fully extended
and wooden pads of sufficient size
and strength must be used to
distribute the load.
 Crane Operator along with the rigger
must ensure that the slewing area of
crane counter weight is free from any
obstruction.

Lifting equipment Workers, staff, 3 4 12 H  All lifting equipment must be 3rd party Supervisor 1 3 3 L OSHAD SF- Safe
failure. visitors, Public, certified and tagged by an appointed Use of Lifting
property HSE officer Equipment and
person. All damaged slings, chains,
shackles and lifting clutches must be Operatives Lifting Accessories-
removed from site immediately. V 3.0- July 2016
 Daily visual Inspection of the lifting

Page 1 of 20
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

equipment, and lifting gear to be


done.
 Weekly & Monthly Inspection to be
carried out and recorded.
 Never exceed the specified safe
working load of crane and lifting
gears.
 No curtains or any means of vision
barriers will not be allowed on
drivers / operators cabin.
 Lifting chart kept in crane cab
(English version).
 Stop the lifting activity when the wind
speed reaches 38km/hr.
 In the adverse weather rain, dusty
wind, wind etc.. all the lifting activity
should be stopped.
Operator Error, Crane collapse, Personal injury, 3 4 12 H  Operators must be trained by 3rd Supervisor, 1 3 3 L OSHAD SF- Safe
20
communication fall the load from fatality, property party, certified and must be with not Use of Lifting
error damage HSEO Equipment and
crane, hit the less than 3 years of experience &
load knowledgeable of the work. Lifting Accessories-
 Communication arrangements (radio, V 3.0- July 2016
hand signals, lights etc.) to be in
place where Crane operator cannot
see the load to be lifted or where it is
being placed.
 Competent/approved rigger only to

Page 1 of 21
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

give signals to the operators while


lifting the elements.
 No multiple signals are allowed to be
given to the crane operator during
lifting.
Finger Trap while workers 3 3 9 M  Use tag line rope. Supervisor, 1 3 3 L OSHAD SF- Safe
controlling the  Keep away hand in between lifted Use of Lifting
HSEO Equipment and
load load.
 Use stick in between lifted load to Lifting Accessories-
prevent hand trap. V 3.0- July 2016
 Should use cotton dotted hand
gloves.

21 Weather Crane / load Workers, staff, 3 4 12 H  Lifting operations and working at Project 1 3 3 L OSHAD SF- Safe
Conditions collapse, poor public, visitors, heights to be suspended until weather manager Use of Lifting
Sandstorms, visibility property conditions improve and visibility is Equipment and
High Winds, Fog HSE Lifting Accessories-
clear. This is the responsibility of the
engineer V 3.0- July 2016
Safety Officer to provide the “All
Clear” notice.
 Mobile cranes should have the
anemometer for monitoring of the
wind speed.

22 Working at Fall from the Workers, 3 4 12 H  Only Trained and competent persons Supervisor 1 3 3 L OSHAD SF-
heights. height, serious visitors, allow for the work at height activity. Working at Heights-
property HSE officer V 3.0- July 2016
injury, fatality,  Work at height permit should obtain
fall of material , and approved before the activity. Operatives OSHAD SF- - V
property damage  Open holes/ opening should be

Page 1 of 22
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

covered and fix hard barricading, PM,CM 26.0 scaffold 3.0-


safety nets & signage’s to be July 2016
provided.
OSHAD SF- 37.0
 Provide adequate exclusion zone and
ladder- V 3.0- July
appropriate warning sign boards to 2016
prevent unauthorized entry around
the work at height area. OSHAD SF- 22.0
 Ensure green tag on the scaffold prior barricading of
to use it. hazards- V 3.0- July
 Unsecure and defective scaffolding 2016
must not be used. OSHAD SF- Permit
 Wearing the full body harness with to Work Systems- V
securing it at all the time, provide 3.0- July 2016
certified fall arrestor system in case
the full body harness is not suitable.
 Do not use the red tagged scaffold in
for any reason. Only green tagged
scaffold is safe to use.
 All scaffold systems shall be regularly
inspected by competent persons
every 7 days.
 Do not alter a scaffold. Only
competent person to make any
changes needed and must be re-
inspected.
 Ladders shall be inspected by the

Page 1 of 23
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

user prior its use.


 Do not allow to work on the ladder.
 Maintain 3 point contact on the ladder
and ladder must reach above 3
rungs/1 meter above the platform.
 Valid 3rd party certified YOYO/
retractable fall arrestor should use.
 Ensure adequate and competent
supervision for the work at height
activity.
 Proper access/ egress should
available for all the work at height
area.
 Emergency contact number available
on the work place.

23 Hot work Flying objects Workers , staff 3 3 9 M  Hot work permit required prior to start HSE officer 1 3 3 L OSHAD SF- 28.0
activities. Cut Injury any hot work at site. hot work operation-
Supervisor V 3.0- July 2016
Abrasive Wheel  All gas cutting equipment must be
Injury inspected and repair by the Project
Disintegration of competent technician periodically. manager
cutting disc  Only trained and competent person to
Fire use gas cutting equipment.
Electrocution  Ensure that combustible and
flammable material free from the work
area.
 Internal trained fire watch is to be

Page 1 of 24
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

provided where there is a risk of a fire


starting after hot work has been
suspended or competed.
 No personnel shall be allowed to
stand in front during the activity.
 Stand by fire extinguisher fire blanket
is to be at the work location.
 Grinder and grinding wheel shall be
checked prior to use
 Warning sign must be in place.
 All personnel working with hot work
must be wearing correct PPE Leather
glove, safety shoes, Aprons, Face
shields, Mask etc.

23 Working at direct Heat stress/ heat Workers , staff 3 3 9 M  Drink plenty of water HSE officer 1 3 3 L OSHAD SF- Safety
sunlight/ high illness.  All personnel to be made aware of in the Heat- V 3.0-
temperature Supervisor July 2016
symptoms of heat stress through
briefing & tool box talks. Project OSHAD SF-
 TBT should be conducted by manager General Workplace
supervisor/ HSEO to all work forces Amenities- V 3.0-
regarding heat illness. July 2016
 Strictly follow the summer break
timing as per the municipality.
 Drinking water provided for the each
work locations and every worker
should have thermoses cans.

Page 1 of 25
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Rest shelter provided at work


locations and Ac shelter provided for
the work force.
 Emergency contact number should
available on the work locations.

24 Poor Trips and Falls Workers, Staff, 3 3 9 M  Keep work area clean and tidy. Supervisor 1 3 3 L OSHAD SF-
housekeeping, Personal injuries Visitors  Elevate cables to prevent tripping 54.0waste
improper Operatives management- V
hazard.
stacking of  Tools shall not be kept on walkways Housekeepi 3.0- July 2016
materials and shall be stored in tool box on ng team
completion of work.
 All workers to clean their respective
work areas after completion of work
or prior to end of shift.
 Waste shall be collected and
disposed in accordance to site safety
waste disposal provision and must be
disposed according to Abu Dhabi
Municipality guidelines ( Centre of
waste Management Regulations)..
 Keep walking aisles and roadways
clear.
 Stack the materials properly and
provide temporary barricading.

25 Emergency Fire All personnel 3 4 12 H  All personnel to be safety inducted. AEGC 1 3 OSHAD-SF –
 Train and inform all employees 3 Codes of Practice

Page 1 of 26
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

situations Collision regarding fire Emergency Evacuation CoP 17.0 – Safety


Electrocution Plan. Signage and
Failure to  Initiate and maintain good Signals – Version
Evacuation housekeeping 3.0
 Ensure that all materials used in porta OSHAD-SF –
cabin construction are fire rated. Codes of Practice
 Ensure that enough firefighting CoP 43.0 –
Temporary
equipment are made available on
Structures - Version
site. ( Fire Ex., Fire Hose Reel)
3.0
 Ensure that fire alarm and Fire siren
OSHAD-SF –
are available on site and are fully Codes of Practice
functional. CoP 08.0 – General
 No smoking in non-designated areas. Workplace
 Ensurre that smoke detectors are Amenities – Version
installed inside all offices. 3.0
 Ensure that workers are trained- how OSHAD SF-
to fight fire, what to do in case of an Element- 5 –
emergency Training and
 Ensure that enough assembly points awareness and
are made available on site and competency
access to them is kept clear at all OSHAD-SF –
times. Element 6 -
Emergency
 Ensure emergency numbers are
Management
posted at strategic locations.
 Ensure that Evacuation plan is posted
on notice boards and all are informed

Page 1 of 27
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

about it during inductions.

Method Statement & Risk Assessment handover


Date: _ _ / _ _ /_ _ _

I have read, understood and accept the conditions of this method statement & Risk Assessment.
Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
All operatives involved with this job must sign below
I have read, understood and accept the conditions of this method statement and Risk Assessment.

Page 1 of 28
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Sr. Emirates ID
Name Emp. No. Designation Date Signature Remarks
No. No
1
2
3
4
5
6
7
8
9
10
11
12
13

Page 1 of 29
RISK ASSESSMENT

You might also like