RA - 16 - For Production Delivery Installation of Hollow Core Elements
RA - 16 - For Production Delivery Installation of Hollow Core Elements
Project Abu Dhabi Future School Program - Phase 8, Package 1, Al Falah KG
Subject RISK ASSESSMENT for Production Delivery Installation of Hollow Core Elements
NOTE:- This Risk Assessment is prepared in line with the METHOD STATEMENT for Production Delivery Installation of Hollow Core Elements
Rev. 00; and it covers all activities described in this Method Statement.
Page 1 of 1
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
1 Preparing the General Factory Workers, staff, 3 4 12 H All Personnel involved in the activities HSE officer. 1 3 3 L OSHAD SF- Pre-
hollow core bed Hazards ,Person visitors, must be HSE Inducted. Cast Construction-
environment Supervisor. V 3.0- July 2016
al Injuries, MS & RA to be briefed out to all
Property personnel & should be available at Site
Damage factory. engineer OSHAD SF-
Supervisors/Foreman communicates Hazardous
hazards, Risk involved and the Materials- V 3.0-
sequence of work to the work force July 2016
Page 1 of 2
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
2 Working at Slip, fall, personal Workers, staff, 3 3 9 M No work shall be carried out in dark Supervisor. 1 3 3 L OSHAD SF-
Night, poor injuries, visitors area. Adequate task lighting must be General Workplace
illumination HSEO, Site Amenities- V 3.0-
damaged and provided and in such a way it does
engineer July 2016
defective not cast shadows around the work
product area.
3 Applying mold Unsafe handling Workers, staff 3 4 12 H Trained and competent persons Supervisor. 1 3 3 L OSHAD SF-
releasing agent of chemical. handle the chemicals. Hazardous
Operatives Materials- V 3.0-
Hand skin Chemical should be stored at
allergy, eye designated area in the dip trays. Storekeeper July 2016
injury, Eye protection must be used and
Page 1 of 3
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
4 Damaged power Injury to person, Workers, staff 3 4 12 H All electrical equipment’s must be Maintenance 1 3 3 L OSHAD SF-
tools, untrained electrocution, inspected on regular basis including dept. Portable Power
persons, sockets, cables, and discs. Tools- V 3.0- July
HSE officer. 2016
All users must be trained and
competent for using the portable Supervisor. OSHAD SF- 15.0
electrical equipment. Electricity- V 3.0-
Operatives
Suitable grinder’s discs must be used July 2016
for the grinding works.
All hot works must be provided with OSHAD SF- Permit
approved hot works permit. to Work Systems- V
Suitable and appropriate PPE must 3.0- July 2016
be used prior using the electrical
equipment’s.
Exclusion zone with sign board must
be posted in the workplace area.
Management cable must be managed
to avoid any tripping hazards in the
workplace.
Only the allowed voltage of the
project requirements must be used for
Page 1 of 4
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
5 Pre-stressing, Serious Injuries Workers, staff, 3 4 12 H Only competent personnel are Supervisor. 1 3 3 L OSHAD SF- Pre-
Pre-tensioning of Fatalities visitors, allowed to perform the stressing Cast Construction-
strands, casting Operatives. V 3.0- July 2016
activity.
and concreting Hydraulic jack machine must be HSE officer. OSHAD SF-36.0
regularly inspected and 3rd party Plant and
certified must be available. equipment V 3.0-
Operators for the hydraulic jack July 2016
machine must be 3rd party certified
and competent.
During the stressing, no full exclusion
zone must be provided around the
area and unauthorized personnel
should not be allowed to enter the
area.
Ensure that the alarm is working
Page 1 of 5
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
6. Curing of Personal Injuries, Workers, staff, 3 3 9 M All personnel must be keeping away Supervisor. 1 3 3 L OSHAD SF- Pre-
Precast Boiler leak and visitors, from steam to avoid skin burn. Cast Construction-
elements-steam environment Maintenance V 3.0- July 2016
explosion, All steam distribution line must be
curing by boiler dept.
Environmental periodically inspected and repaired by
OSHAD SF-36.0
issues the competent person. Operatives. Plant and
Sign boards and must be posted and equipment V 3.0-
HSE officer.
isolation must provide. July 2016
Boiler must be controlled and
operated only by the competent
personnel. And should have 3rd party
certificate
Fire equipment’s must be provided
Page 1 of 6
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
7. Storage of Personal Injuries Workers, staff, 3 4 12 H Procedures should be in place for Supervisor. 1 3 3 L OSHAD SF- Pre-
hollow core Property Damage visitors, parking of vehicles in and around/in Cast Construction-
slabs in the environment Logistic V 3.0- July 2016
Obstruction of the factory.
factory officer.
assigned Involved Engineer will coordinate with
emergency Logistics Officer for allocation of HSE officer
routes unloading and storage area.
Physical/ hard barriers to be installed.
Provide adequate signage.
Route maps with identification points
should be clearly displayed
Signs and notices should be in place
Page 1 of 7
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
8 Lifting activity, Personal Workers, staff, 3 4 12 H Competent and certified riggers will Supervisor 1 3 3 L OSHAD SF- Safe
lifting the hollow Accidents arising visitors, be provided. HSE officer. Use of Lifting
core slabs to the from: environment All persons/workers must be trained Rigging Equipment and
trailer. Slips, trips and on MSRA prior to commencing any supervisor. Lifting Accessories-
falls. loading, unloading and erection of Project V 3.0- July 2016
manager.
Unsafe lifting lead precast elements. OSHAD SF- Plant
Operator.
to fall of Rigger to communicate to Crane and Equipment- V
materials, crane operator via radio transmitter. 3.0- July 2016
collapse. Rigging Supervisor should control the
Vehicle impact whole lifting activity.
Plant impact No workers are to commence lifting
Falling from back operation without adequate
of delivery supervision.
vehicles. The operator and crane should have
Crash injuries ADM approved valid 3rd party
Pinch point to certificates.
Page 1 of 8
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
9. Transporting of Personnel being Workers, 3 4 12 H Only Driver with the correct license Supervisor 1 3 3 L OSHAD SF- Traffic
hollow core struck by drivers, staff, code with valid license will be allowed Logistic Management and
elements from reversing/ public, to drive delivery vehicle/ trailer. officer Logistics- V 3.0-
the factory to the maneuvering Necessary permit required for Drivers July 2016
project using vehicles, transporting odd size element must
flatbed trailer Fall of materials be obtained.
from the trailer. Driver must be following the
maximum speed limit for heavy
vehicle.
Provide Banks man with trailer for
signaling in the factory and site areas.
Reverse alarm and bacon light should
Page 1 of 9
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
be on the trailer.
Precast element must be loaded and
straps correctly to avoid movement
causing damage or loss of load while
in transit on the way to the site.
Correct type of lashing, straps must
be used for heavy precast elements
load.
Oil leak from 3 3 9 M Only delivery vehicle with valid Loading 1 3 3 L OSHAD SF- Traffic
defective/ poorly registration license will be used for Supervisor Management and
maintained deliveries of Precast Element to site. Logistics- V 3.0-
Logistic July 2016
transport vehicle Drivers must ensure that delivery
officer
vehicle has been inspected daily to
ensure it is in good condition before Drivers
loading and transporting the elements
on to the site.
Driver should maintain the inspection
checklist of the trailer.
In case of any spillage from the
vehicles contaminated soil must be
properly disposed and spill kit must
be provided by Main Contractor.
10 Arrival of Personal Injuries Workers, staff, 3 4 12 H All workers must have a valid EID and Supervisor 1 3 3 L OSHAD SF- Permit
personnel at Property Damage visitors, Insurance card. to Work Systems- V
site. Check work environment Logistic 3.0- July 2016
PTW controls.
location for All the vehicles in the working area
Page 1 of 10
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
space and should have reverse alarm. officer OSHAD SF- Safe
obstacles. Enter All persons should undergone site Use of Lifting
work location HSE officer Equipment and
HSE induction.
with assist crane Conduct TBT prior to start the Job. Operatives Lifting Accessories-
and trailers. Rig Mandatory PPE shall be worn by all V 3.0- July 2016
cranes at lifting personnel.
location. Set up OSHAD SF- Plant
All equipment/ vehicles inspected and and Equipment- V
cranes at lifting
approved by HSE/logistic dept. 3.0- July 2016
location.
All operators shall have approved
operator license & 3rd party
certificates.
All personnel to be fully briefed on
tasks and responsibilities
together .with the correct use of PPE
& job related training.
Prepare ground in advance. Verify
ground bearing pressure with client.
No fuel filling when machine is
running/hot.
Unauthorized entry of personnel to be
restricted.
Thorough visual inspection of the
area and ground conditions to be
carried out.
Temporary warning signs.
Proper traffic management.
Page 1 of 11
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
11. Set up the Personnel being Workers, staff, 3 4 12 H All personnel involved in crane lifting Supervisor 1 3 34 L OSHAD SF- Plant
delivery vehicle visitors, Public, HSE officer 4 and Equipment- V
struck by operations must be trained with
in designated reversing/ environment specific method statement risk Operators 3.0- July 2016
safe offloading maneuvering assessment.
zone OSHAD SF- Traffic
vehicles. Vehicle Toolbox talk/ Daily safety task Management and
or falling into instruction must be done daily before Logistics- V 3.0-
excavations. work commence. July 2016
The delivery vehicle must park on firm
level ground.
12. Set up the Personnel injury Workers, staff, 3 4 12 H Ground must be compacted and Supervisor 1 3 3 L OSHAD SF- Safe
mobile crane from lifting plant visitors, Public, leveled prior set up of the crane. L
Use of Lifting
and correct type environment HSE officer Equipment and
& equipment The lifting zone must be isolated with
of lifting failure warning tape or nylon rope with Operators Lifting Accessories-
equipment warning tape and appropriate safety V 3.0- July 2016
signage must be posted. OSHAD SF- Plant
Unauthorized personnel should not and Equipment- V
be allowed inside the exclusion zone. 3.0- July 2016
All lifting plant & equipment must be
inspected by the competent person
and the copy of 3rd party certificate
must be valid and available.
All crane operator and rigger man
must have a valid ADM approved 3rd
Page 1 of 12
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
party certificate
Mobile crane out riggers must be fully
extended and seated in leveled and
compacted ground with proper
outrigger board/pad/plate.
No curtains or any means of vision
barriers will not be allowed on
drivers / operators cabin.
13. Stacking and Personnel injury Workers, staff, 3 4 12 H Stacking of Precast Element must be Supervisor 1 3 3 L OSHAD SF- Pre-
Storage of from material visitors, leveled ground condition. Otherwise Cast Construction-
hollow core collapse of environment direct installation from delivery vehicle V 3.0- July 2016
slabs Precast will be done to avoid stacking on site.
Elements Supervisor must ensure that ground
materials condition is leveled, firm and
compacted to prevent collapse.
Stacking area must be isolated from
pedestrian with hard barricade.
14. Lifting of the Personnel injury Workers, staff, 3 4 12 H Lifting supervisor will ensure that all Lifting 1 3 3 L OSHAD SF- Safe
hollow core from lifting plant visitors, lifting plant & equipment must be supervisor Use of Lifting
slabs from & equipment environment inspected daily before use and 3rd Equipment and
designated Operators Lifting Accessories-
failure or unsafe party certificate must be valid and
stacking area. operation available. V 3.0- July 2016
lifting the hollow core slabs from the
trailer the lifting clamps or belts shall
Page 1 of 13
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
15. Disconnecting Personnel injury Workers, staff, 3 4 12 H Supervisor to ensure that work at Supervisor 1 3 3 L OSHAD SF- Safe
the sling from from falling from visitors, heights must be provided with fall Use of Lifting
the Precast environment HSE officer Equipment and
heights protection such as edge protection
Element lifting otherwise must be used when edge Operatives Lifting Accessories-
points protection in not possible to put in V 3.0- July 2016
place. OSHAD-SF– COP
Everyone should be trained for the 23.0 – Working at
use of safety harness and retractable Heights– V 3.0
lanyard using.
In case of ladder will be used to reach
the lifting points the length of ladder
must be at least 3 rungs/ steps higher
than that of the working platform, over
reaching should be avoided when
Page 1 of 14
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
16 Moving Man-machine Workers, staff, 3 4 12 H Provide separate access for Supervisor 1 3 3 L OSHAD SF- Traffic
vehicle’s, interface/Vehicle visitors, pedestrian and vehicle traffic. Management and
equipment’s environment HSE officer Logistics- V 3.0-
/ Plant impact Keep plant away from traffic and
operatives e.g. Physical barriers, Logistic July 2016
banksman. officer OSHAD SF- 53.0
Drivers trained on site requirements. EHS management
Operatives
Minimize the need for plant to reverse during construction
e.g. arrange for drive in, stop and work- V 3.0- July
drive out. 2016
All reversing operations to be under
the control of trained and competent
Banksman.
Operators to be made aware of
vehicle routs and other operations
close to plant.
Beacon light and reverse alarm
should be on the all vehicles and
equipment’s.
Procedures should be in place for
parking of vehicles in and around the
Page 1 of 15
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
site.
Site Engineer will coordinate with site
Logistics Officer for allocation of
unloading and storage area
17 Unsafe stacking Obstruction of 3 3 9 M Route maps with identification points Main 1 3 3 L OSHAD SF- 17.0
of materials on assigned should be clearly displayed by Main contractor Safety signage and
the access. emergency Contractor. HSE officer signals- V 3.0- July
routes Signs and notices should be in place 2016
setting out standards and controls. Element6-
Do not stack any materials or park Emergency
any vehicles on the emergency route. management
18 Manual handling Personal Injuries Workers, staff, 3 3 9 M Ensure trailer/pickup is parked on Supervisor 1 3 3 L OSHAD SF- Manual
of various such as cuts and visitors, even and compacted ground. Handling and
materials for environment HSE officer Ergonomics- V 3.0-
abrasions Ensure that only one trailer at a time
unloading and involving upper is being offloaded. Operatives July 2016
erection body and limbs; Ensure that sufficient area behind the
activities. strains, muscle, trailer is available for offloading the
muscle injuries plant.
or fractures, Ensure that the truck/trailers properly
either as a result secured when offloading.
of falls or Ensure that operators are wearing
dropping heavy appropriate PPE and Hi visibility
objects. vests.
Operators shall not use mobile
phones during driving and during the
Page 1 of 16
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
offloading operation.
Cranes/ equipment’s glass should not
be covered/ curtained.
Use of mechanical means to move
material is preferred.
Gloves are mandatory and must be
worn to protect against cuts,
scratches and punctures.
Workers to ensure that there are no
obstructions in the direction they will
be carrying the load.
Workers to ensure that they know the
approximate weight of the load prior
lifting.
Workers to take position bend knees
and secure grip of the load being
lifted. Lift the load keeping back
straight, arms close to body and
strong leg muscles to take the strain
of the load.
Worker must not carry a load which
obstructs vision. Use mechanical aid
such as trolleys.
Worker should avoid twisting the
trunk whilst lifting or carrying a load.
Worker shall seek assistance if the
load is too heavy. Supervisor to
Page 1 of 17
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
19 Lifting and Failure to follow Workers, staff, 3 4 12 H No workers are to commence lifting PM,CM, 1 3 3 L OSHAD SF- Safe
erection method visitors, Public, operation without adequate Use of Lifting
activities of environment Supervisor Equipment and
statement supervision.
hollow core instruction. The construction manager is Lifting Accessories-
element. Fatality, Personal responsible for all activities related to V 3.0- July 2016
Injuries. erection and must comply with the OSHAD SF- 22.0
Fall/collapse of Method Statement & Risk barricading of
element from the Assessment. hazards- V 3.0- July
crane Supervisor to provide necessary 2016
Property Damage briefing on Method Statement to
workforce on daily basis. OSHAD-SF– COP
23.0 – Working at
Supervisor to check the sequence of
Heights– V 3.0
work and must keep it safe.
MS, RA, check list etc. should be
available at work location.
Ensure use of safe scaffolds and
green tag on the scaffold prior to use
it.
Wearing the full body harness with
double lanyard and securing it at all
the times, provide certified fall
arrestor system in case the full body
Page 1 of 18
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
Incorrect position Workers, staff, 3 4 12 H 3rd party certificates required for Lifting 1 3 3 L OSHAD SF- Plant
Page 1 of 19
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
of Crane during visitors, Public, crane and operatives. Supervisor and Equipment- V
lifting operation. property Daily inspection to be conducted by 3.0- July 2016
Operators
operatives. Keep record of daily
OSHAD SF- Safe
inspection.
Use of Lifting
All working platforms must be Equipment and
compacted and leveled prior to the Lifting Accessories-
commencement of erection. V 3.0- July 2016
The Site / Erection Engineer / Mobile
Crane Operator to ensure that the
crane outrigger placement area is
free from any underground utilities /
buried services.
Outriggers must be fully extended
and wooden pads of sufficient size
and strength must be used to
distribute the load.
Crane Operator along with the rigger
must ensure that the slewing area of
crane counter weight is free from any
obstruction.
Lifting equipment Workers, staff, 3 4 12 H All lifting equipment must be 3rd party Supervisor 1 3 3 L OSHAD SF- Safe
failure. visitors, Public, certified and tagged by an appointed Use of Lifting
property HSE officer Equipment and
person. All damaged slings, chains,
shackles and lifting clutches must be Operatives Lifting Accessories-
removed from site immediately. V 3.0- July 2016
Daily visual Inspection of the lifting
Page 1 of 20
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
Page 1 of 21
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
21 Weather Crane / load Workers, staff, 3 4 12 H Lifting operations and working at Project 1 3 3 L OSHAD SF- Safe
Conditions collapse, poor public, visitors, heights to be suspended until weather manager Use of Lifting
Sandstorms, visibility property conditions improve and visibility is Equipment and
High Winds, Fog HSE Lifting Accessories-
clear. This is the responsibility of the
engineer V 3.0- July 2016
Safety Officer to provide the “All
Clear” notice.
Mobile cranes should have the
anemometer for monitoring of the
wind speed.
22 Working at Fall from the Workers, 3 4 12 H Only Trained and competent persons Supervisor 1 3 3 L OSHAD SF-
heights. height, serious visitors, allow for the work at height activity. Working at Heights-
property HSE officer V 3.0- July 2016
injury, fatality, Work at height permit should obtain
fall of material , and approved before the activity. Operatives OSHAD SF- - V
property damage Open holes/ opening should be
Page 1 of 22
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
Page 1 of 23
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
23 Hot work Flying objects Workers , staff 3 3 9 M Hot work permit required prior to start HSE officer 1 3 3 L OSHAD SF- 28.0
activities. Cut Injury any hot work at site. hot work operation-
Supervisor V 3.0- July 2016
Abrasive Wheel All gas cutting equipment must be
Injury inspected and repair by the Project
Disintegration of competent technician periodically. manager
cutting disc Only trained and competent person to
Fire use gas cutting equipment.
Electrocution Ensure that combustible and
flammable material free from the work
area.
Internal trained fire watch is to be
Page 1 of 24
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
23 Working at direct Heat stress/ heat Workers , staff 3 3 9 M Drink plenty of water HSE officer 1 3 3 L OSHAD SF- Safety
sunlight/ high illness. All personnel to be made aware of in the Heat- V 3.0-
temperature Supervisor July 2016
symptoms of heat stress through
briefing & tool box talks. Project OSHAD SF-
TBT should be conducted by manager General Workplace
supervisor/ HSEO to all work forces Amenities- V 3.0-
regarding heat illness. July 2016
Strictly follow the summer break
timing as per the municipality.
Drinking water provided for the each
work locations and every worker
should have thermoses cans.
Page 1 of 25
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
24 Poor Trips and Falls Workers, Staff, 3 3 9 M Keep work area clean and tidy. Supervisor 1 3 3 L OSHAD SF-
housekeeping, Personal injuries Visitors Elevate cables to prevent tripping 54.0waste
improper Operatives management- V
hazard.
stacking of Tools shall not be kept on walkways Housekeepi 3.0- July 2016
materials and shall be stored in tool box on ng team
completion of work.
All workers to clean their respective
work areas after completion of work
or prior to end of shift.
Waste shall be collected and
disposed in accordance to site safety
waste disposal provision and must be
disposed according to Abu Dhabi
Municipality guidelines ( Centre of
waste Management Regulations)..
Keep walking aisles and roadways
clear.
Stack the materials properly and
provide temporary barricading.
25 Emergency Fire All personnel 3 4 12 H All personnel to be safety inducted. AEGC 1 3 OSHAD-SF –
Train and inform all employees 3 Codes of Practice
Page 1 of 26
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
Page 1 of 27
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
I have read, understood and accept the conditions of this method statement & Risk Assessment.
Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
All operatives involved with this job must sign below
I have read, understood and accept the conditions of this method statement and Risk Assessment.
Page 1 of 28
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 016
Package 1, Al Falah KG Sector 1C plot P3
Rev. 00
Sr. Emirates ID
Name Emp. No. Designation Date Signature Remarks
No. No
1
2
3
4
5
6
7
8
9
10
11
12
13
Page 1 of 29
RISK ASSESSMENT