EQUIPMENT

JOCKY PUMP DATE /……….

EQUIPMENT TAG

JP - 01

LOCATION

CUP-2 BUILDING / ZONE-2 / LOWER LEVEL

 In
 Operation Not in Operation

SR.No

DESCRIPTION

DATE

JP-01

REMARKS

Weekly

Check the operation of machine

Check un-usual noise and vibration.


3

Check for leakage and at the Mechanical Seal.

Check valve seals for leakages

Check valves for proper operation and setting

Operate manually each pump


Weekly

Check the operation of machine

Check un-usual noise and vibration.

Check for leakage and at the Mechanical Seal.

Check valve seals for leakages


5

Check valves for proper operation and setting

Operate manually each pump

Weekly

Check the operation of machine

Check un-usual noise and vibration.


3

Check for leakage and at the Mechanical Seal.

Check valve seals for leakages

Check valves for proper operation and setting

Operate manually each pump


Weekly

Check the operation of machine

Check un-usual noise and vibration.

Check for leakage and at the Mechanical Seal.

Check valve seals for leakages


5

Check valves for proper operation and setting

Operate manually each pump

WEEKLY SERVICE PLANNED PREVENTIVE MAINTENANCE REPORT

ENGINEER SIGN FOREMAN SIGN TECHNICIAN SIGN