ROOT CAUSE ANALYSIS

VESSEL: SAMBA

TYPE OF INSPECTION: VETTING SIRE GAZPROM

PORT /COUNTRY: FOS FRANCE DATE:16/10/19

Item: 8.13 PRESSURE SENSOR FOR THE CARGO TANK 2P


WAS OUT OF ORDER. IT WAS SHOWING A PRESSURE
OF -7 WHILE THE PRESSURE OF IG WAS ABOUT 600
MBAR. A PRESSURE GAUGE WAS FITTED ON THE
VAPOUR LOCKS.
Root Cause: SIGNAL FROM RADAR ON 2P GOT FROZEN DUE TO
FAILURE ON RADAR UNIT INTERNAL FAULT
Corrective Action: ALL TERMINAL CONNECTIONS OF RADAR TERMINAL
BOX WERE CLEANED AND REDID, ESP. PAY
ATTENTION COMMUNICATION TERMINAL RS 485A-RS
485B (5&6). COMMUNICATION UNIT AND SAFETY
MODULE WERE RESTARTED. AFTER TANK CLEANING
OPERATION WE WILL CHECK EMITTER AND
REFLECTOR OF RADAR UNIT INSIDE THE TANK,

Estimated Completion 23/OCT/19


Date or Close-Out date:

Future Preventive Action: TECHNICAL ASSITANCE TO EVALUATE THE


POSSIBILITY TO REPLACE THE WHOLE UNIT OR
OVERHUALED.

Item: 12.3 THERE WASN’T SYSTEM IN PLACE FOR THE


ROUTINE RECEIPT OF
NAVIGATIONAL,METEOROLOGICAL ENVIROMENTAL
DATA INLCUDING ICE DATA.
Root Cause: VESSEL DOES NOT POSSESS WEATHER FACSIMIL TO
RECEIVE ICE NAVIGATIONAL WARNINGS

Corrective Action: WE HAD RAISED REQUISITON SAM-195091

Estimated Completion 3 MONTHS.


Date or Close-Out date:
ROOT CAUSE ANALYSIS

Future Preventive Action: HAVE ON BOARD THE WEATHER FACSIMIL.

Item: THE FUEL AND ENGINE OIL USE IN LIFEBOAT AND


RESCUE BOAT WERE NOT SUITABLE FOR
OPERATION IN SUB ZERO TEMPERATURES
Root Cause: NO ANTIFREZZING FOR FUEL AND OIL FOR SUB ZERO
TEMPERATURES

Corrective Action: VESSEL HAS RAISED REQUISITION SAM-195006

Estimated Completion 3 MONTHS


Date or Close-Out date:

Future Preventive Action: KEEP AND INVENTORY ON BOARD FOR ANTIFREEZING


ADDTIVES FOR ENGINE OF LIFESAVINGS BOATS.

Item:

Root Cause:

Corrective Action:

Estimated Completion
Date or Close-Out date:

Future Preventive Action: