Week 1 Villa 4 GF Struckture Helmi
Week 1 Villa 4 GF Struckture Helmi
Mandor : Helmi
Periode : Week 1
Date : 18/11/22 - 24/11/22
PROGRESS OF WORK
NO SCOPE OF WORK VOLUME UNIT WEIGHT LAST WEEK (%) THIS WEEK (%) UNTIL THIS WEEK (%)
VOLUME PROGRESS PERCENTAGE VOLUME PROGRESS PERCENTAGE VOLUME PROGRESS PERCENTAGE
A VILLA 1
GROUND STRUKTUR
A PREPARATION -
1 Bowplank 61.200 m1 1.08 0% - 52.020 85% 0.92 52.02 85% 0.917
-
B SOIL -
1 Soil Exavation 214.578 m3 2.80 0% - 107.289 50% 1.40 50% 1.398
2 Digging Footplate 41.100 m3 1.61 0% - 0% - 0% -
3 Dinging River stone 22.000 m3 0.57
4 Sandfill under Footplate t= 2.5cm 0.877 m3 0.06 0% - 0% - - 0% -
5 Sandfill under Riverstone t= 10cm 3.514 m3 0.24 0% - 0% - 0% -
6 Sandfill under Slab t=2.5cm 2.072 m3 0.14 0% - 0% - - 0% -
7 Lean Concrete Under Footplate t= 2.5 cm 35.080 m2 0.45 0% - 0% - - 0% -
8 Lean Concrete under Slab t=2.5 cm 82.896 m2 1.06 0% - 0% - 0% -
9 Plastick Sheet Under LC Footplate 35.080 m2 0.06 0% - 0% - 0% -
10 Plastick Sheet Under LC Slab 82.896 m2 0.15 0% - 0% - 0% -
11 Anti Termit 139.000 m2 2.36 0% - 0% - - 0% -
12 Backfill 71.526 m3 0.65 0% - 0% - - 0% -
13 Compaction 329.936 m2 1.72 0% - 0% - 0% -
-
C FOUNDATION -
1 River Stone Crush Foundation 1 PC : 4 Sand Type 1 19.578 m3 3.86 0% - 0% - - 0% -
D REINFORCED CONCRETE -
1 Foot Plate 120x120x30 RC - K300 -
- Concrete K300 2.160 m3 0.73 0% - 0% - - 0% -
- Reinforcement 321.180 kg 1.28 0% - 0% - 0% -
- Formwork ( Using Batako, Spesi 1 PC : 3 Sand ) 7.200 m2 0.18 0% - 0% - - 0% -
2 Foot Plate 150x150x30 RC - K300
- Concrete K300 3.375 m3 1.14 0% - 0% - - 0% -
- Reinforcement 479.123 kg 1.91 0% - 0% - 0% -
- Formwork ( Using Batako, Spesi 1 PC : 3 Sand ) 9.000 m2 0.23 0% - 0% - - 0% -
3 Foot Plate 170x170x30
- Concrete K300 2.601 m3 0.88 0% - 0% - - 0% -
- Reinforcement 351.384 kg 1.40 0% - 0% - 0% -
- Formwork ( Using Batako, Spesi 1 PC : 3 Sand ) 6.120 m2 0.16 0% - 0% - - 0% -
4 Column 30/40 RC - K300 (-2000)
- Concrete K300 2.736 m3 0.94 0% - 0% - - 0% -
- Reinforcement 1,059.547 kg 4.23 0% - 0% - 0% -
- Formwork 31.920 m2 1.72 0% - 0% - - 0% -
PROGRESS OF WORK
NO SCOPE OF WORK VOLUME UNIT WEIGHT LAST WEEK (%) THIS WEEK (%) UNTIL THIS WEEK (%)
VOLUME PROGRESS PERCENTAGE VOLUME PROGRESS PERCENTAGE VOLUME PROGRESS PERCENTAGE
5 Tie Beam 25/40 RC - K300
- Concrete K300 6.561 m3 2.22 0% - 0% - - 0% -
- Reinforcement 1,367.861 kg 5.46 0% - 0% - 0% -
- Formwork 12.160 m2 0.58 0% - 0% - - 0% -
- Formwork ( Using Batako, Spesi 1 PC : 3 Sand ) 40.590 m2 1.04 0% - 0% - - 0% -
6 RC Slab 100 mm
- Concrete K300 10.998 m3 3.72 0% - 0% - 0% -
- Reinforcement 711.717 kg 2.84 0% - 0% - - 0% -
-
E REINFORCED CONCRETE GROUND FLOOR STRUCTURE -
1 Column 30/40 RC - K300 (-2000) -
- Concrete K300 5.418 m3 1.87 0% - 0% - - 0% -
- Reinforcement 1,839.103 kg 7.35 0% - 0% - - 0% -
- Formwork 63.210 m2 3.41 0% - 0% - - 0% -
E WATERPROFFING -
1 Waterproffing Footplate 47.880 m2 0.50 0% - 0% - - 0% -
2 Waterproffing Coloumn Pedestal 31.920 m2 0.33 0% - 0% - 0% -
3 Waterproffing Tie beam 12.160 m2 0.13 0% - 0% - 0% -