Professional Documents
Culture Documents
N100 Transport PL
N100 Transport PL
N100 Transport PL
Requirements
Table of Contents
1 General ........................................................................................................................... 2
2 Weights, dimensions and handling instructions .............................................................. 3
2.1 Nacelle ............................................................................................................................ 3
2.2 Drive train........................................................................................................................ 4
2.3 Rotor hub ........................................................................................................................ 4
2.4 Weights of components on crane hook...........................................................................5
2.5 Transport frames.............................................................................................................6
2.6 Towers N80/2500, N90/2500 ..........................................................................................8
2.7 Towers N100/2500..........................................................................................................9
2.8 Anchor cage ..................................................................................................................10
3 Requirements on the access roads...............................................................................11
3.1 Loads ............................................................................................................................ 11
3.2 Slopes ........................................................................................................................... 11
3.3 Clearance profile on a straight route ............................................................................. 11
3.4 Bends ............................................................................................................................ 12
3.5 Road foundation............................................................................................................12
4 Crane requirements ......................................................................................................13
5 Crane hard standing area ............................................................................................. 13
1 General
All details regarding the transport project must be agreed with all persons involved
beforehand.
Local conditions always define the transport project i.e. the process is always project-specific.
All drawing dimensions in chapter 2 are given in millimeter (mm).
2.1 Nacelle
As a standard procedure, drive train, rotor hub and further exterior assemblies (obstacle
lights, wind measuring instruments, lightning arrester, etc.) are not assembled for nacelle
transport.
The transport frame for the nacelle consists of 4 single feet. They can be used for twist lock
fastening, see chapter 2.5. Otherwise anti-slip mats must be used for transportation.
The nacelle must only be placed on the compacted ground or on the crane mats.
3800
1050
1670
90
400
1370 6980 2400
11070 3500
The coordinates of the center of gravity of the nacelle must be determined not considering
the drive train and the transport frame.
Transport foot
front rear
Center of gravity
max. 2990
1470
2260
25
1990 ±30
2990
3500
max. 5190
The rear part of the gearbox with the assembled components is protected by wood lagging.
This protection has been considered for the length measure.
The rotor hub is delivered on a transport frame. The transport frame does not protrude on the
sides.
Transformer
With transformers installed in tower the transformer substation is omitted.
Individual components per wind turbine:
Transformer approx. 8.6 t, L x W x H: 2.6 x 1.3 x 2.54 m
Medium voltage switchgear approx. 1.0 t, L x W x H: 2.0 x 1.0 x 2.0 m
Transformer substation
In terms of time schedule, building of the transformer substation and wind turbine erection
are carried out independently.
For precise dimensions and weights please refer to the manufacturer. Values may vary
even within a wind farm depending on design/variants and scope of supply.
The following values can be found:
Length 3.3 to 7.0 m
Width 2.5 to 3.0 m
Height 2.7 to 3.9 m
Weight (incl. transformer etc.) 15 to 31 t
Transport foot
front rear
Support piece
for gearbox
1357
3500 2260
For return transport, up to 3 drive train transport frames can be stacked, including the base
up to 4. The bearing shells remain assembled.
290
2227
Base required
760
5780
720
500
755
30
00
2066 3680
N80/2500
N80/2500 N80/2500
DIBt 3
IEC 1a NVN 1a/IEC 1a
N80/2500 N90/2500 LS
Classification
IEC 1a N90/2500 LS DIBt 2/IEC 3a
N90/2500 HS N90/2500 HS
DIBt 3/NVN 2a
IEC 1b IEC 1b
IEC 2a
• Due to the applied transport means, the transport height is 7 cm greater than the tower
diameter.
• The lifting tackles have a height of 15 cm each. Thus the tower sections become longer.
• Please allow changes in the weight of ±2 %.
• The centers of gravity deviate from the center of tower sections by approx. 5 %.
N100/2500
Classification
DIBt 2/IEC 3a
• Due to the applied transport means, the transport height is 7 cm greater than the tower
diameter.
• The lifting tackles have a height of 15 cm each. Thus the tower sections become longer.
• Please allow changes in the weight of ±2 %.
• The centers of gravity deviate from the center of tower sections by approx. 5 %.
The anchor cage of N100 R100MTR consists of 200 anchor bolts and has larger dimensions.
Number Dimensions Weight
Name
of parts maximum maximum
Load spreading 2
outside ∅ 4675 mm approx. 4.8 t
plate
Anchor plate 2 outside ∅ 4550 mm approx. 3.1 t
Anchor bolts 200 L = 3450 mm approx. 7.5 t
Washers, nuts and other small parts approx. 0.4 t
The complete anchor cage, including transport supports weighs approx. 14.5 t.
3.1 Loads
For each wind turbine the access road must be capable of supporting the following loads:
Vehicles:
- Approx. 50 concrete and construction vehicles, up to 70 vehicles for hybrid towers
- 12 to 20 heavy trucks for crane erection, depending on hub height
- approx. 10 to 13 heavy trucks with turbine components
(3 to 5 tower sections, 3 rotor blades, 3 for nacelle, rotor hub and drive train,
2 for switch cabinet (Bottombox), small parts and erection container)
- max. length: 57 m
- required free height: 4.40 to 5.90 m depending on the method of transportation
- div. construction vehicles
Weight of vehicles:
- max. load per axle: approx. 12 t
- max. overall weight: approx. 165 t
3.2 Slopes
In the case of surfaces as described in section 3.5, slopes must not exceed approx. 6 %. If it
does, please contact Nordex. Steeper slopes may require an extra traction engine, the
additional length must be considered.
Side inclination: maximal 2 %
3.4 Bends
For all hub heights
R1 Inside radius bend 35 m
R2 Inside radius of obstacle-free area 50 m
R3 Outside radius of obstacle-free area Determined by the protruding length of the rotor
blade
The marked area (- - -) must be free of all obstacles, that is, trees, buildings, masts, etc.
min. 8 m
R1
R3 R2
min. 4.5 m
30-100 cm 30-55 cm
Subsoil
min. 4.5 m
• Access roads built as compact gravel road, if required with hydraulic or asphalt bond
• Structure from bottom to top:
1. Base compacted, 30 to 100 cm depending on site position and subsoil
geomembrane as separation layer against erosion
2. Bed compacted, gravel, 15 to 30 cm, depending on material used
3. Top layer compacted, ballast, 15 – 25 cm, depending on material
• Instead of gravel, bed and top layer may be made of breakage material (free of all
demolition waste)
• All layers and the subsoil must be compacted using proper machinery allow for heavy
loads
4 Crane requirements
A main crane and an auxiliary crane are required. The auxiliary crane must change its
position several times before, during and after the wind turbine erection.
• The required hook height is: Hub height + 10 m
• Main crane radius min. 15 to 30 m, depending on crane type
• Auxiliary crane radius min. 6 to 12 m, depending on crane type
• The nacelle must only be placed on the crane hard standing area or on the crane mats.
• A clear area for assembly of the crane jib is required for lattice cranes. The length of this
area is hub height + 10 m. The auxiliary crane must be free to move parallel to entire
length of the crane jib. Crane hard standing areas of 10 x 10 m each must be provided at
the third points of the assembly length (see following drawings).
• Example 1 shows the crane hard standing area - including storage areas - when the
delivery of the parts of the wind turbine is not time-critical. The final layout for the specific
site must be planned after the site has been inspected.
• Example 2 shows the crane hard standing area with the minimum requirements. The
area that is required for the temporary storage of the tower sections and the rotor blades
is not included in example 2. This example with incur higher transport costs. The final
layout for the specific site must be planned after the site has been inspected.
• In addition to the examples shown above, a clear area for assembling the rotor (star
arrangement) is also required. This area depends on the local conditions and therefore
Nordex has to be consulted before any action is taken.
• Space for at least 2 Nordex erection containers must be provided (power generator,
tools). Further space must be provided for one Nordex material container to be able to
store material, rubbish skip, cabins, construction vehicles, etc.
• The access roads to the wind turbine must always be kept free for ambulance and rescue
vehicles.
We expressly point out that all values are to be regarded as standard values only.
The lay out of access roads and hard standing area depends on the specific
transportation and erection method.
- The lay out must be individually for each site.
- Depending on the site different variants are possible.
- Transport weights may also vary with the erection site.
The exact design of access roads, crane hard standing areas and assembly areas
must be agreed with Nordex prior to start of construction.
Improper design or lay out of access roads and crane hard standing areas can cause
considerably higher logistic and erection costs at a later stage.
K0801_011803_EN
single site
individually.
15,5 m
5 Optimized geometry of the
crane hard standing area
4
3 17 m
Even surface for
the assembly of
2 Auxiliary crane the crane jig
Transport, Access Roads and Crane Requirements
17 m
22,5 m
max. 150 m
Working space 4m
m
15-30
68 m
4,5 m
24 m
15 / 16
Example 2: Minimum requirements to the crane hard standing area without storage areas
for an S77 wind turbine with a hub height of 80 m
This sketch is only exemplary and
must be modified for each single
site individually.
K0801_011803_EN
Optimized geometry of
2 Nordex erection containers the crane hard standing
1 rubbish skip area
25 m Rotor hub
25 m
max. 150 m
Working space 4m
m
15-30
45 m
4,5 m
16 / 16