Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18

Project

Location
Date

Subject
Bill of Quantities

Item Particulars Amount (PHP)

1 DIVISION 03 – CONCRETE 1,468,979.98

2 DIVISION 04 – MASONRY 281,710.80

3 DIVISION 05 – METALS 2,394,128.23

4 DIVISION 31 – EARTHWORK 488,733.00

5 DIVISION 06 – FINISHES AND ARCHITECTURAL WORKS 700,655.50

6 DIVISION 07 – FIRE PROTECTION WORKS 12,600.00

7 DIVISION 08 – MECHANICAL WORKS 120,225.00

8 DIVISION 09 – PLUMBING WORKS 719,995.17

9 DIVISION 10 - ELECTRICAL WORKS 289,700.00

GENERAL REQUIREMENTS / PRELIMINARIES

TOTAL COST WITH OUT REBAR COST = 6,476,727.68


REBAR COST (OSM) =

GRAND TOTAL 6,476,727.68


Project 0
Location 0
Date

Subject
Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

1 Mobilization/Demobilization lot 1.00


2 Project Management and Supervision lot 1.00
3 Bonds and Insurances
Surety Bond lot 1.00
Performance Bond lot 1.00
Guarantee Bond lot 1.00
4 Handling, Hauling and Lifting of Materials lot 1.00
5 Temporary Facilities, Shed and Barracks lot 1.00
6 Temporary Power and Water Consumption lot 1.00
7 Cleaning, clearing, haul-out, disposal of debris lot 1.00
8 Safety, PPE, and Covid Provisions lot 1.00
9 Permits lot 1.00
10 As-built and Shop Drawings lot 1.00
- -

SUB TOTAL Sub Total (Php) -

TO COLLECTION -

DIVISION 01 – GENERAL REQUIREMENTS To Summary (PHP) -


Project 0
Location 0
Date 12/30/1899

Subject : CONCRETE - LOCKER ROOM AND SOUTH GUARD HOUSE


Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

DIVISION 03 – CONCRETE

03 10 00 CONCRETE FORMING AND ACCESSORIES

03 11 00 Concrete Forming
Supply, fabrication , installation, stripping and/or leaving formwork
with the actual surface in contact with the concrete, including
provision of block-outs, chamfered edges, notching and overlaps,
necessary greasing or coating with form oil, all necessary hardware,
scaffolding, shoring and staging, all fixing accessories, use of plant,
tools and equipment, and all necessary items to complete the works.

Formworks to produce fair surface to:


1 Isolated Footing m2 34.92 650.00 200.00 850.00 29,682.00
2 Footing Tie Beam m2 67.54 650.00 200.00 850.00 57,409.00
3 Column m2 100.30 650.00 200.00 850.00 85,255.00
4 Beams/Girder m2 112.11 650.00 200.00 850.00 95,293.50
5 Slab on Grade m2 43.79 650.00 200.00 850.00 37,221.50
6 Wall Footing m2 20.90 650.00 200.00 850.00 17,765.00
7 Curbs and Gutter m2 - -

03 20 00 CONCRETE REINFORCING
03 21 00 Reinforcing Steel

Supply, fabricate and fix of steel bars 20mm Ø rebar to:


1 Footing Tie Beam kg 1,795.70 45.00 45.00 80,806.50
2 Column kg 1,724.35 45.00 45.00 77,595.75

Supply, fabricate and fix of steel bars 16mm Ø rebar to:


3 Isolated Footing kg 698.67 28.00 28.00 19,562.76
4 Footing Tie Beam kg - -
5 Column kg 113.76 28.00 28.00 3,185.28
6 Beams/Girders kg 1,349.58 28.00 28.00 37,788.24

Supply, fabricate and fix of steel bars 12mm Ø rebar to:


7 Isolated Footing kg 392.67 15.00 15.00 5,890.05
8 Column kg 132.42 15.00 15.00 1,986.35
9 Slab on Grade kg 2,215.65 15.00 15.00 33,234.75

Supply, fabricate and fix of steel bars 10mm Ø rebar to:


10 Footing Tie Beam kg 110.51 10.00 10.00 1,105.10
11 Column kg 11.52 10.00 10.00 115.20
12 Beams/Girders kg 119.31 10.00 10.00 1,193.10
13 Slab on Grade kg 155.57 10.00 10.00 1,555.70
14 Wall Footing kg 321.92 10.00 10.00 3,219.20

03 30 00 CAST-IN-PLACE CONCRETE

03 31 00 Structural Concrete
Supply and delivery and placing of concrete including necessary
grouting, vibrating, hammering, tamping, consolidating, curing,
hardening, wetting, sealing, brooming and scratching, protecting,
sampling, all fixing accessories, use of plant, tools and equipment,
and all necessary items to complete the works.

3000 PSI Concrete to:


1 Isolated Footing m3 14.69 6,000.00 2,400.00 8,400.00 123,396.00
2 Footing Tie Beam m3 10.39 6,000.00 2,400.00 8,400.00 87,276.00
3 Column m3 10.76 6,000.00 2,400.00 8,400.00 90,384.00
4 Beams/Giirders m3 11.77 6,000.00 2,400.00 8,400.00 98,868.00
5 Slab-on-grade m3 43.82 6,000.00 2,400.00 8,400.00 368,088.00
6 Wall Footing m3 8.36 6,000.00 2,400.00 8,400.00 70,224.00
7 Curbs & Gutter m3 - -

1500 PSI Concrete to:


8 Lean Concrete m3 - -
03 60 00 GROUTING
Supply and installation of non-shrink grout including all fixing
accessories, use of tools and equipment, and all necessary items
to complete the works.

1 Leveling Grout m3 14.60 2,000.00 800.00 2,800.00 40,880.00

OTHER ITEMS

Allow other items for which the contractor requires payment to


comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL Sub Total (Php) 1,468,979.98

TO COLLECTION 1,468,979.98

DIVISION 03 – CONCRETE To Summary (PHP) 1,468,979.98


Project 0
Location 0
Date 12/30/1899

Subject
Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

DIVISION 04 – MASONRY

04 20 00 UNIT MASONRY

04 22 00 Concrete Unit Masonry


Hollow concrete masonry units including all required reinforcement,
doweling, mortar, sealing, lintel beams, stiffener columns, all
fixing accessories, use of plant, tools and equipment, and all
necessary items to complete the works.

1 150mm Thick CHB wall load bearing m2 360.78 500.00 200.00 700.00 252,546.00
2 100mm Thick CHB wall load bearing m2 52.08 400.00 160.00 560.00 29,164.80

OTHER ITEMS
Allow other items for which the contractor requires payment to
comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL 281,710.80

TO COLLECTION 281,710.80

DIVISION 04 – MASONRY To Summary (PHP) 281,710.80


Project 0
Location 0
Date 12/30/1899

Subject : METALS - LOCKER ROOM AND SOUTH GUARD HOUSE


Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

DIVISION 05 – METALS

05 10 00 STRUCTURAL METAL FRAMING

05 12 00 Structural Steel Framing


Supply and installation of structural steel framing system, cost to
include cutting, pointing to position, welding, bolts, plate
connectors, stiffeners, base plates, anchor bolts, primary paint,
use of tools and equipment and all other fixing accessories to
complete the works.

Truss / Rafter
1 HSS5X4X5/16 (RF-1&2) kg 1,361.76 334.00 116.90 450.90 614,017.58
2 2-L125x125x12 kg 1,089.41 334.00 116.90 450.90 491,214.97
3 2-L100x100x6 kg 777.38 250.00 87.50 337.50 262,365.75
4 2-L50x50x5 kg 267.67 132.00 46.20 178.20 47,698.79
5 2-L75x75x5 kg 1,565.82 197.00 68.95 265.95 416,429.83
6 LC 150x65x20x2.0 kg 2,329.40 120.00 42.00 162.00 377,362.80

Connection
7 Base Plate, Gusset Plate, Connecting Plate kg 532.00 - - -
8 Ø25mm Anchor Bolt pcs 48.00 38.00 13.30 51.30 2,462.40
9 Ø20mm Anchor Bolt pcs 28.00 30.00 10.50 40.50 1,134.00
10 Ø12mm A325 Bolt pcs - -
Connection/Bracing/Purlins
11 Ø12 Tension Rod kg 106.56 38.00 13.30 51.30 5,466.53
12 Ø10 Sag Rod kg 56.06 28.00 9.80 37.80 2,119.07
13 Turnbuckle sets 16.00 150.00 52.50 202.50 3,240.00
Pedestal
14 Ø200mm GI Pipe to PC-1 lm 17.70 670.00 234.50 904.50 16,009.65
14 Ø100mm GI Pipe to Guard House lm - -
Steel Tubular (2" x 4" & 1"x 1")
15 Turnstile Area kg 1,252.94 40.00 14.00 54.00 67,658.76
16 Sidewalk kg - -
17 Waiting Area kg 1,453.49 40.00 14.00 54.00 78,488.46
18 Typical Fence kg - -
19 Pedestrian Gate (1.2m x 2.4m - 4sets) kg 156.66 40.00 14.00 54.00 8,459.64
Automatic Collapsible Gate
20 13.84mL x 2mH Stainless Steel Retractable Gate sets 1.00 - - -
Guard Post
21 Prefab Guard Booth (1.5mLx1.5mWx2.5mH) sets 1.00 - - -
22 Boom Barrier sets 1.00 - - -

OTHER ITEMS
Allow other items for which the contractor requires payment to
comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL 2,394,128.23

TO COLLECTION 2,394,128.23

DIVISION 05 – METALS To Summary (PHP) 2,394,128.23


Project 0
Location 0
Date 12/30/1899

Subject : EARTHWORKS - LOCKER ROOM AND SOUTH GUARD HOUSE


Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

31 05 16 Aggregates for Earthwork


Supply and installation of 50 mm thick gravel bedding, cost to
include spreading, compacting, levelling, use of plant, tools and
equipment, and all necessary items to complete the works.

1 Footing Tie Beam m3 10.39 1,000.00 1,000.00 10,390.00


2 Slab m3 43.82 2,100.00 1,000.00 3,100.00 135,842.00

31 10 00 SITE CLEARING

31 11 00 Clearing and Grubbing


Removal of vegetation at the site, including stripping of sod and
soil, and tree pruning for the site clearing.

4 Clearing m2 293.00 100.00 100.00 29,300.00

31 20 00 EARTH MOVING

31 23 00 Excavation and Fill


Excavation shall perform as describe regardless of the character
of material encountered, within the limits of work, to the lines and
grades indicated on the drawings & depths indicated, as specified.

5 Structural Excavation m3 150.00 1,000.00 1,000.00 150,000.00

Backfill materials shall consist of approved site excavated


materials and shall be free from brush, roots and other unsuitable
materials which would be detrimental to compaction requirements.

6 Backfill and compaction to substructure m3 175.80 600.00 240.00 840.00 147,672.00


7 Backfill and compaction to site development item

31 30 00 EARTHWORK METHODS

31 31 00 Soil Treatment
Soil treatment for termite control for all areas and surfaces in
contact with the ground.

8 Soil Poisoning m2 2.93 5,000.00 300.00 5,300.00 15,529.00

OTHER ITEMS

Allow other items for which the contractor requires payment to


comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL 488,733.00

TO COLLECTION 488,733.00

DIVISION 31 – EARTHWORK To Summary (PHP) 488,733.00


Project 0
Location 0
Date 12/30/1899

Subject
Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

DIVISION 06 – FINISHES AND ARCHITECTURAL WORKS

FINISHES
Supply of materials, labor and consumable to finish/complete the
works, with regards to standard and as specified by the designer
and shall comply to any necessary requirement for the testing of
materials or as specified.

1 Interior Partition m2 - -
2 Plastering m2 70.80 300.00 200.00 500.00 35,400.00
3 Ceiling Works -

1/2" thk. Moisture Resistant Gypsum Board in Metal Furring Frame m2 117.80 600.00 200.00 800.00 94,240.00

1/2" thk. Gypsum Board in Metal Furring Frame m2 25.80 600.00 200.00 800.00 20,640.00
PVC Ceiling Eaves (Silver Gray Finish from Gemkonstruct) m2 196.40 600.00 200.00 800.00 157,120.00
4 Interior Painting Works m2 70.80 300.00 120.00 420.00 29,736.00
5 Exterior Painting Works m2 155.70 300.00 120.00 420.00 65,394.00
4 Baseboard Finish m2 16.00 300.00 120.00 420.00 6,720.00
Tiling Works 0.6x0.6 Polished Homogenous Tiles to Floor (CCTV,
6 m2 30.20 350.00 350.00 10,570.00
Storage, Guard Area, Lactation Room)
Tiling Works 0.3x0.3mm Homogenous Tiles Ceramica De Milano to
7 m2 28.80 350.00 350.00 10,080.00
Floor (Male Toilet Floor Finish, Toilet)
Tiling Works 0.3x0.6mm Homogenous to Wall Tiles Ceramica De
8 m2 350.00 350.00 -
Milano (Male Toilet, Female Staff Lockers, Toilet)
9 Tiling Works 0.6x0.6 Non-Skid Tiles (Turnstile Area) m2 55.00 350.00 350.00 19,250.00
10 Broom Concrete Finish - Pathways, Sidewalk, Waiting Area m2 173.80 300.00 300.00 52,140.00
11 Smooth Concrete Finish - Male & Female Lockers m2 86.76 300.00 300.00 26,028.00

ROOFING WORKS
Ga.22 Pre-Painted Long Span Roofing, Color Steel Supreme (CS
1 m2 340.00 300.00 300.00 102,000.00
Blue)
2 Ga.22 Pre-painted G.I Flashing (CS Blue) LM 24.30 350.00 350.00 8,505.00
3 Ga.22 Stainless Steel Gutter (0.20m W x 0.30m D) LM 61.30 350.00 350.00 21,455.00
4 Ga.22 Pre-painted Ridge Roll, Color Steel Supreme (CS Blue) LM 30.65 300.00 300.00 9,195.00
5 1/2" thk Fiber Cement Fascia Board LM 91.95 350.00 350.00 32,182.50

DOOR AND WINDOWS


Gate
G1 3000mm x 2400mm x 50mm Grilles Door with Frame in 2"x4" &
1 1"1"Ø 0.10 O.C. in epoxy paint finish with complete accessories as SETS 1.00 - -
per indicated in the specification and plan.
Doors
D1 800mm x 2100mm x 45mm Metal Door Swing Type in powder
coated finish - with Lever Type Yale Stainless Door Handle with
2 SETS 1.00 - -
Dead Bolt with complete accessories as per indicated in the
specification and plan.
D2 700mm x 2100mm x 45mm Swing Type Wood Flush Door in
Painted Finish in 002 Elusive White with Yale Stainless Door
3 SETS 4.00 - -
Handle with dead bolt with complete accessories as per indicated in
the specification and plan.
D3 700mm x 2100mm x 45mm Swing Type Heavy-Duty PVC in
4 Painted Finish in 002 Elusive White with complete accessories as SETS 1.00 - -
per indicated in the specification and plan.
D4 900mm x 2100mm x 45mm Metal Door Swing Type in Boysen
5 Epoxy Paint Finish with complete accessories as per indicated in SETS 2.00 - -
the specification and plan.
Windows
W1 2400mm x 1200mm x 45mm Sliding Type - Powder Coated
Aluminum Frame in Ral 7016, 6mm thk. Ordinary Glass, provide
6 SETS 2.00 - -
with insect screen with complete accessories as per indicated in the
specification and plan.
W1 1200mm x 1200mm x 45mm Sliding Type - Powder Coated
Aluminum Frame in Ral 7016, 6mm thk. Ordinary Glass, provide
7 SETS - -
with insect screen with complete accessories as per indicated in the
specification and plan.
W2 600mm x 1200mm x 45mm Awning Type - Powder Coated
Aluminum Frame in Ral 7016, 6mm thk. Ordinary Glass, provide
8 SETS 5.00 - -
with insect screen with complete accessories as per indicated in the
specification and plan.
W3 600mm x 400mm x 45mm Awning Type - Powder Coated
Aluminum Frame in Ral 7016, 6mm thk. Ordinary Glass, provide
9 SETS 1.00 - -
with insect screen with complete accessories as per indicated in the
specification and plan.
W4 3200mm x 600mm x 45mm Awning Type - Powder Coated
Aluminum Frame in Ral 7016, 6mm thk. Ordinary Glass, provide
10 SETS 2.00 - -
with insect screen and frosted sticker with complete accessories as
per indicated in the specification and plan.
W5 800mm x 600mm x 45mm Awning Type - Powder Coated
Aluminum Frame in Ral 7016, 6mm thk. Ordinary Glass, provide
11 SETS 5.00 - -
with insect screen with complete accessories as per indicated in the
specification and plan.

TOILET PARTITIONS AND FIXTURES


1 Water Closet (HCG-CS995PB) SETS 5.00 - -
2 Urinal (HCG-Urinal Bennet-U24) SETS 3.00 - -
3 Lavatory (HCG-L4011) SETS 10.00 - -
Toilet Partition 12mm thk. HPL x 1800mmH to Male Toilet and
4 SETS 9.00 - -
Female Staff Lockers Partitions
5 Urinal Partitions SETS 4.00 - -
6 Countertop and Splash Board SETS 3.00 - -
7 Mop Sink (600x600mm) SETS 1.00 - -
8 Basin Mixer / Faucet (COTTO-C30207BI) SETS 10.00 - -
9 Floor Drain (COTTO-C30207BI) SETS 10.00 - -
10 Shower (HCG-BF3716PX) SETS 5.00 - -
11 Perenial Spray / Bidet SETS - -
12 Mirror 1x1.5m (Female Locker) SETS 1.00 - -
13 Mirror 1x3.3m (Male Locker) SETS 1.00 - -

OTHER ITEMS
Allow other items for which the contractor requires payment to
comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL 700,655.50

TO COLLECTION 700,655.50

DIVISION 06 – FINISHES AND ARCHITECTURAL WORKS To Summary (PHP) 700,655.50


Project
Location
Date

Subject
Bill of Quantities

Unit Rate
Item Description Unit Amount
Materials Labor Total

DIVISION 07 - FIRE PROTECTION WORKS


Supply and Installation of Fire Protection Equipments and Piping
works, complete accessories & control, use of tools and equipment,
and all necessary items to complete the works.

1.0 OTHER ACCESSORIES


(UL / FM Approved; Supply & Install)
Portable Fire Extinguishers
FE-1 10 lbs ABC Dry Chemical PFE pcs. 6 2,000.00 100.00 2,100.00 12,600.00

3.0 OTHER ITEMS

Allow other items for which the contractor requires payment to


comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL 12,600.00

TO COLLECTION

GRAND TOTAL To Summary (PHP) 12,600.00


Project : STEELASIA COMPOSTELA STEEL 800,000 MTPA BAR ROLLING MILL PROJECT
Location : Brgy. Poblacion, Municipality of Compostela, Cebu
Date 0

Subject : MECHANICAL WORKS - LOCKER ROOM AND SOUTH GUARD HOUSE


Bill of Quantities

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

1.0 DIVISION 08 - VENTILATION EQUIPMENT & DUCTING


Supply and Installation of Mechanical Equipment and accessories,
secondary wiring, control and other works, use of tools and
equipment, and all necessary items to complete the works.

1.1 VENTILATION EQUIPMENT (FANS & BLOWERS)


(Supply & Install; See Equipment Schedule)

EF-LSGH-01 to 02 units 2.00 5,000.00 5,000.00 10,000.00


250 L/s, 0.05 kW, 230V, 1Ø, 60Hz
Wall Mounted ( Exhaust) (Male Locker)

EF-LSGH-03 units 1.00 5,000.00 5,000.00 5,000.00


80 L/s, 0.04 kW, 230V, 1Ø, 60Hz
Wall Mounted ( Exhaust) (Male Locker - Toilet)

EF-LSGH-04 to 07 units 4.00 5,000.00 5,000.00 20,000.00


25 L/s, 0.03 kW, 230V, 1Ø, 60Hz
Ceiling Mounted ( Exhaust) (Male Locker - Toilet)

EF-LSGH-08 units 1.00 5,000.00 5,000.00 5,000.00


25 L/s, 0.03 kW, 230V, 1Ø, 60Hz
Ceiling Mounted ( Exhaust) (Lactation)

EF-LSGH-09 units 1.00 5,000.00 5,000.00 5,000.00


25 L/s, 0.03 kW, 230V, 1Ø, 60Hz
Ceiling Mounted ( Exhaust) (Female Locker - Toilet)

EF-LSGH-10 units 1.00 5,000.00 5,000.00 5,000.00


50 L/s, 0.04 kW, 230V, 1Ø, 60Hz
Ceiling Mounted ( Exhaust) (Female Locker)

EF-LSGH-11 units 1.00 5,000.00 5,000.00 5,000.00


35 L/s, 0.03 kW, 230V, 1Ø, 60Hz
Ceiling Mounted ( Exhaust) (Guard Storage)

TEF-LSGH-01 units 1.00 5,000.00 5,000.00 5,000.00


25 L/s, 0.01 kW, 230V, 1Ø, 60Hz
Wall Mounted ( Exhaust) (Guard Toilet)

WF-LSGH-01 units 1.00 5,000.00 5,000.00 5,000.00


0.04 kW, 230V, 1Ø, 60Hz
Wall Fan ( Exhaust) (Guard Counter)

OF-LSGH-01 TO 02 units 2.00 5,000.00 5,000.00 10,000.00


0.07 kW, 230V, 1Ø, 60Hz
Oscillaitng Fan ( Exhaust) (Male Locker)

OF-LSGH-03 units 1.00 5,000.00 5,000.00 5,000.00


0.07 kW, 230V, 1Ø, 60Hz
Oscillaitng Fan ( Exhaust) (Female Locker)

OF-LSGH-04 units 1.00 5,000.00 5,000.00 5,000.00


0.07 kW, 230V, 1Ø, 60Hz
Oscillaitng Fan ( Exhaust) (CCTV Monitor)

Secondary Wiring and Controls lot 1.00 12,750.00 12,750.00


Miscellaneous Materials lot 1.00 5,950.00 5,950.00
Testing and Commissioning lot 1.00 2,550.00 2,550.00

1.2 VENTILATION DUCTWORKS


Toilet Exhaust Duct
Round Duct - G.I. Sheet Ga. 24
100 mm Ø lm 35.00 250.00 250.00 8,750.00
Vent Cap
100 mm dia. pcs. 8.00 250.00 250.00 2,000.00

Hangers and Supports lot 1.00 1,612.50 1,612.50


Miscellaneous Materials lot 1.00 752.50 752.50
Sleeve and Insert Work lot 1.00 537.50 537.50
Testing and Commissioning lot 1.00 322.50 322.50

SUB-TOTAL (Php) - Item 2

2.0 OTHER ITEMS


Allow other items for which the contractor requires payment to
comply with all respect with the provisions of the relevant conditions
of the contract particular specifications and drawings which are
not in the Bills of Quantities.

SUB-TOTAL (Php) - Item 3 -

TO COLLECTION 120,225.00

MECHANICAL WORKS 120,225.00


Project : STEELASIA COMPOSTELA STEEL 800,000 MTPA BAR ROLLING MILL PROJECT
Location : Brgy. Poblacion, Municipality of Compostela, Cebu
Date 0

Subject
Bill of Quantities

Unit Rate
Item Description Unit Amount
Materials Labor Total

DIVISION 09 - PLUMBING SYSTEM


1.0 PUMPS AND PUMP ACCESSORIES
(Supply & Install; See Equipment Schedule)

2.0 POTABLE WATER PIPING WORKS


PPR PN-20 Pipes
50 mm Ø m 25.00 555.00 194.25 749.25 18,731.25
40 mm Ø m 40.00 350.00 122.50 472.50 18,900.00
32 mm Ø m 15.00 225.00 78.75 303.75 4,556.25
25 mm Ø m - -
20 mm Ø m - -
15 mm Ø m - -

Hot Dipped Galvanized Iron Pipes (Seamless) - Sched. 40


(conforming to ASTM A53 or equivalent)
50 mm Ø m - -

Pipe Fittings (PP-R & G.I.)


Tee Equal
50 mm Ø pcs. 5.00 250.00 87.50 337.50 1,687.50
40 mm Ø pcs. 20.00 140.00 49.00 189.00 3,780.00
20 mm Ø pcs. 20.00 30.00 10.50 40.50 810.00

Tee Reducer
50 mm x 40 mm pcs. 5.00 250.00 87.50 337.50 1,687.50
50 mm x 32 mm pcs. 3.00 250.00 87.50 337.50 1,012.50
20 mm x 15 mm pcs. 3.00 30.00 10.50 40.50 121.50

Elbow 90deg
50 mm Ø pcs. 10.00 215.00 75.25 290.25 2,902.50
20 mm Ø pcs. 40.00 25.00 8.75 33.75 1,350.00

Reducer
50 mm x 40 mm pcs. 5.00 250.00 87.50 337.50 1,687.50

End cap
50 mm Ø pcs. 2.00 120.00 42.00 162.00 324.00
40 mm Ø pcs. 2.00 80.00 28.00 108.00 216.00
25 mm Ø pcs. 2.00 30.00 10.50 40.50 81.00
20 mm Ø pcs. 2.00 22.00 7.70 29.70 59.40

Female Coupling
20 mm Ø pcs. 10.00 45.00 15.75 60.75 607.50

Hangers and Supports lot 1.00 - 941.63 941.63

Gate Valve, Class 150


40 mm Ø pcs. 7.00 600.00 210.00 810.00 5,670.00
32 mm Ø pcs. 3.00 400.00 140.00 540.00 1,620.00

Water Hammer Arrester (WHA)


40 mm Ø pcs. 1.00 600.00 210.00 810.00 810.00
32 mm Ø pcs. 1.00 400.00 140.00 540.00 540.00

Plumbing Fixtures
Lavatory set/s 7.00 3,500.00 3,500.00 24,500.00
Shower Drain w/ water heater set/s 5.00 3,500.00 3,500.00 17,500.00
Urinal set/s 3.00 3,500.00 3,500.00 10,500.00
Water Closet set/s 5.00 3,500.00 3,500.00 17,500.00

Miscellaneous Materials lot 1.00 9,666.72 9,666.72


Sleeve and Insert Work lot 1.00 6,904.80 6,904.80
Testing and Adjustment lot 1.00 4,142.88 4,142.88

3.0 SANITARY AND SEWER PIPING SYSTEM


uPVC Pipe (Orange) S-1000
100 mm Ø m 40.00 1,200.00 420.00 1,620.00 64,800.00
50 mm Ø m 12.00 450.00 157.50 607.50 7,290.00

Fittings
Wye Equal
100 mm Ø pcs. 5.00 160.00 56.00 216.00 1,080.00
Elbow 90deg
75 mm Ø pcs. 5.00 80.00 28.00 108.00 540.00
50 mm Ø pcs. 20.00 55.00 19.25 74.25 1,485.00

Tee Equal
100 mm Ø pcs. 5.00 160.00 56.00 216.00 1,080.00
50 mm Ø pcs. 8.00 55.00 19.25 74.25 594.00

Hangers and Supports lot 1.00 10,813.50 10,813.50

Floor Drain
50 mm Ø pcs. 8.00 200.00 70.00 270.00 2,160.00

Floor Clean Out


100 mm Ø pcs. 5.00 200.00 70.00 270.00 1,350.00

P-trap pcs. 5.00 200.00 70.00 270.00 1,350.00

Miscellaneous Materials lot 1.00 6,477.98 6,477.98


Sleeve and Insert Work lot 1.00 4,627.13 4,627.13
Excavation lm 70.00 150.00 150.00 10,500.00
Sand Bedding lm 70.00 150.00 150.00 10,500.00
Backfill & Compaction lm 70.00 150.00 150.00 10,500.00
Testing and Adjustment lot 1.00 - -

4.0 STORM DRAINAGE PIPING SYSTEM


STORM DRAINAGE PIPING WORKS
uPVC Pipe (Orange) S-1000
150 mm Ø m 12.00 1,800.00 630.00 2,430.00 29,160.00
100 mm Ø m 12.00 1,200.00 420.00 1,620.00 19,440.00
75 mm Ø m 54.00 900.00 315.00 1,215.00 65,610.00

Fittings
Elbow 90deg
75 mm Ø pcs. 36.00 80.00 28.00 108.00 3,888.00

Hangers and Supports lot 1.00 17,131.50 17,131.50

Gutter Drain
75 mm Ø pc. 12.00 900.00 315.00 1,215.00 14,580.00

Catch Basin pc. 12.00 1,000.00 350.00 1,350.00 16,200.00

Ceiling Clean Out


75 mm Ø pcs. 2.00 900.00 315.00 1,215.00 2,430.00

Miscellaneous Materials lot 1.00 11,790.77 11,790.77


Sleeve and Insert Work lot 1.00 84,219.75 84,219.75
Excavation lm 60.00 150.00 150.00 9,000.00
Sand Bedding lm 60.00 150.00 150.00 9,000.00
Backfill & Compaction lm 60.00 150.00 150.00 9,000.00
Testing and Adjustment lot 1.00 7,328.70 7,328.70

5.0 VENT PIPING SYSTEM


VENT PIPING WORKS
uPVC Pipe (Orange) S-1000
100 mm Ø m 6.00 1,200.00 420.00 1,620.00 9,720.00
75 mm Ø m 40.00 900.00 315.00 1,215.00 48,600.00
50 mm Ø m 50.00 450.00 157.50 607.50 30,375.00

Fittings
Elbow 90deg
75 mm Ø pcs. 6.00 80.00 28.00 108.00 648.00
50 mm Ø pcs. 25.00 55.00 19.25 74.25 1,856.25

Tee Equal
100 mm Ø pcs. 2.00 160.00 56.00 216.00 432.00
50 mm Ø pcs. 25.00 80.00 28.00 108.00 2,700.00

Tee reducer
75 mm x 50 mm pcs. 8.00 80.00 28.00 108.00 864.00

P-trap
50 mm Ø pcs. 20.00 80.00 28.00 108.00 2,160.00

Hangers and Supports lot 1.00 13,304.25 13,304.25


Miscellaneous Materials lot 1.00 7,746.17 7,746.17
Sleeve and Insert Work lot 1.00 5,532.98 5,532.98
Testing and Adjustment lot 1.00 3,319.79 3,319.79

8.0 OTHER ITEMS


Allow other items for which the contractor requires payment to
comply with all respect with the provisions of the relevant
conditions of the contract particular specifications and drawings
which are not in the Bills of Quantities.

SUB TOTAL 719,995.17

TO COLLECTION 719,995.17

GRAND TOTAL 719,995.17


Project : STEELASIA COMPOSTELA STEEL 800,000 MTPA BAR ROLLING MILL PROJECT
Location : Brgy. Poblacion, Municipality of Compostela, Cebu
Date : 14 June 2023

Bill of Materials

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total

ELECTRICAL WORKS
1 PANELBOARDS
Supply and installation of Distribution Panels including nameplates,
supports, terminal lugs, connectors, busbar, breakers, consumable
and all necessary materials as specified.

Section 26 24 16 Panelboards

Panel Board
Supply and installation Panelboards including nameplates, supports,
terminal lugs, connectors, busbar, breakers, consumables and all
necessary materials as specified.
DP-LSGH-01 assy 1.0 17,000.00 17,000.00 17,000.00
Main: 100AT,100AF,3P,230V MCCB with MTS
Branches: 1- 100AT, 100AF, 3P, 230V MCB
1- 40AT, 50AF, 3P, 230V MCB
14 - 20AT, 60AF, 2P, 230V MCB

SUB-TOTAL (Php) - Item 1 17,000.00

3 WIRES AND CABLES

Supply and installation of wires and cables including all necessary


consumables, wire identification and other materials as required
to complete the system

Section 26 05 19 Conductors and Cables


Low Voltage Wires/Cables
125mm2 THWN lm 300.0 30.00 30.00 9,000.00
14mm2 THWN lm 300.0 30.00 30.00 9,000.00
3.5mm2 THWN lm 900.0 30.00 30.00 27,000.00
8.0mm2 TW lm 300.0 30.00 30.00 9,000.00
5.5mm2 TW lm 1,500.0 30.00 30.00 45,000.00
3.5mm2 TW lm 900.0 30.00 30.00 27,000.00

Terminal Lugs
125mm2 pcs 1.0 250.00 250.00 250.00
14mm2 pcs 1.0 250.00 250.00 250.00
8.0mm2 pcs 1.0 250.00 250.00 250.00
5.5mm2 pcs 1.0 250.00 250.00 250.00
3.5mm2 pcs 1.0 250.00 250.00 250.00

SUB-TOTAL (Php) - Item 3 127,250.00

4 Section 26 05 33 Raceways and Boxes


CONDUITS AND CABLE TRAYS
Supply and installation of Intermediate Metallic Conduit (IMC),
and other conduits complete with
fittings, hangers, supports, consumables and other necessary
materials required to complete the system

4" Ø PVC pc 20.0 250.00 250.00 5,000.00


1 1/2" Ø IMC pipe pc 30.0 250.00 250.00 7,500.00
3/4" Ø IMC pipe pc 30.0 250.00 250.00 7,500.00
1/2" Ø IMC pipe pc 30.0 250.00 250.00 7,500.00
3/4" Ø IMC coupling pc 10.0 250.00 250.00 2,500.00
1/2" Ø IMC coupling pc 10.0 250.00 250.00 2,500.00
3/4" Ø IMC lucknut and bushing pc 10.0 250.00 250.00 2,500.00
1/2" Ø IMC lucknut and bushing pc 10.0 250.00 250.00 2,500.00
1/2" Flexible metalic conduit m 30.0 250.00 250.00 7,500.00

SUB-TOTAL (Php) - Item 4 45,000.00

5 Section 26 41 13 - LPS (Faraday Cage System)


LIGHTNING PROTECTION & GROUNDING SYSTEM

Lightning Protection System


Supply and installation of lightning protection system including
Air Terminal, conduits, conductors, connections, ground wells, ground
Project : STEELASIA COMPOSTELA STEEL 800,000 MTPA BAR ROLLING MILL PROJECT
Location : Brgy. Poblacion, Municipality of Compostela, Cebu
Date : 14 June 2023

Bill of Materials

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total
rods, stroke counter,air terminal and all necessary works required
to complete the system.

9.5mm ɸ, 600mm Copper Air Terminal, Solid Surface Mounted pcs 12.0 250.00 250.00 3,000.00
25mm x 1.2mm Copper Tape Conductor m 110.0 100.00 100.00 11,000.00

Section 26 05 26 Grounding and Bonding


Grounding and Bonding
Supply and installation of grounding and bonding materials
complete with supports, consumables and all necessary
accessories.
100mm2 Bare Copper Wire lm 50.0 100.00 100.00 5,000.00
25 mm Ø PVC pcs 25.0 200.00 200.00 5,000.00
Ground Rod, 20 mm Ø x 3000mm pcs 1.0 - -
Ground Bar, 300mm (L) x 50mm (w) x 6mm (T) Copper Ground Bar w complete wall
pc 1.0 300.00 300.00 300.00
mounted insulator spacer.
Exorthermic Connections assy/lot 1.0 - -
Bonding for Electrical Equipment lot 1.0 - -

SUB-TOTAL (Php) - Item 5 24,300.00

6 WIRING DEVICES
Supply and installation of wiring devices including supports,
consumables and other necessary materials

Single pole switch, flush tumbler, 15A, 230V pcs 4.0 700.00 700.00 2,800.00
Two gang switch, flush, 15A, 230V pcs 5.0 500.00 500.00 2,500.00
Duplex receptacle outlet, 15A, 250V, parallel blade grounding type, parallel slot wall
pcs 15.0 500.00 500.00 7,500.00
mounted
Single receptacle outlet, 15A, 250V, parallel blade grounding type, parallel slot ceiling
pcs 15.0 500.00 500.00 7,500.00
mounted
Floor Mounted power outlet, 15A, 230V pcs 4.0 500.00 500.00 2,000.00
Special Purpose Outlet (IDF) pcs 1.0 500.00 500.00 500.00
4" x 2" Utility Boxes pcs 40.0 250.00 250.00 10,000.00
4" x 4" Junction Boxes pcs 7.0 250.00 250.00 1,750.00

SUB-TOTAL (Php) - Item 6 34,550.00

7 Section 265100 - Luminaires and Accessories


Project : STEELASIA COMPOSTELA STEEL 800,000 MTPA BAR ROLLING MILL PROJECT
Location : Brgy. Poblacion, Municipality of Compostela, Cebu
Date : 14 June 2023

Bill of Materials

Unit Rate
Item Description Unit Quantity Amount
Materials Labor Total
LIGHTING FIXTURES
Interior Lighting
Supply and installation of lighting fixtures including supports,
connectors, consumables and all necessary materials

IP20 Ceiling Recessed Mounting Luminaire Complete w/ 1200mmX600mm complete


with 2x14 Watts Power , 4200 Lumen output and 6500 Kelvin Color Temperature LED pcs 16.0 300.00 300.00 4,800.00
lamp.
IP65 Suspended Mounting Luminaire Complete w/ 1200mmX300mm complete with 16
pcs 8.0 300.00 300.00 2,400.00
Watts Power , 4200 Lumen output and 6500 Kelvin Color Temperature LED lamp.
IP20 Ceiling Recessed Downlight Luminaire Complete w/18W Power , 2300 Lumen
pcs 15.0 300.00 300.00 4,500.00
Output and 4000 Kelvin Color Temperature LED Lamp
IP65 Suspended mounting Downlight Luminaire Complete w/18W Power , 2300 Lumen
pcs 6.0 300.00 300.00 1,800.00
Output and 4000 Kelvin Color Temperature LED Lamp
Emergency Lighting Fixture In 2X8W Led Lamp. Emergency Lighting Duration: 2 Hours pcs 6.0 300.00 300.00 1,800.00

5 watts self-contained, maintained exit light and 2 hours battery pack. pcs 3.0 300.00 300.00 900.00

SUB-TOTAL (Php) - Item 7 16,200.00

8 OTHER ITEMS
Unistrut Channel, gauge 12, 41mm x 41mm x 3m H.D lm 30.0 300.00 300.00 9,000.00
Unistrut Clamp 1/2" pc 15.0 150.00 150.00 2,250.00
Unistrut Clamp 3/4" pc 15.0 150.00 150.00 2,250.00
C and Z purlin Clip pc 20.0 150.00 150.00 3,000.00
Full threaded rod 3/8 G.I. lm 45.0 150.00 150.00 6,750.00
Electrical Tape 16mm x 20m pc 10.0 65.00 65.00 650.00
G.I. Tie Wire kg 20.0 75.00 75.00 1,500.00
Other Miscellaneous and Consumable lot 1.0 - -
(including wire tapes, labels, etc.)

OTHER ITEMS

Allow other items for which the contractor require payment to comply with all respect
with the provision of the relevanr conditions of the contract particular specifications
and drawings which are not in bill of Quantities

SUB-TOTAL (Php) - Item 8 25,400.00

TO COLLECTION 289,700.00

ELECTRICAL WORKS 289,700.00

You might also like