Professional Documents
Culture Documents
00 Report FloodStudy Elec Eltek Pathum Thani Dec 09 2021
00 Report FloodStudy Elec Eltek Pathum Thani Dec 09 2021
00 Report FloodStudy Elec Eltek Pathum Thani Dec 09 2021
To be submitted to
Prepared by
Author st 8/12/2021
Prasop S. (Bsc.1 Honor)
This report has been prepared for the exclusive use of the commissioning party
and may not be reproduced without prior written permission from Infratech Energy
Co.,Ltd. All work has been carried out within the terms of the
brief using all reasonable skill, care and diligence. No liability is accepted by
brief using all reasonable skill, care and diligence. No liability is accepted by
preparation of this report, or for any use of this report other than for the purpose
TABLE OF CONTENTS
Table of Contents…………………………………………………………………………….... 1
List of Plate……………………………………………………………………………………... 2
List of Figures……..…………………………………………………………………………… 3
List of Annex………………….………………………………………………………………... 3
Annex
Figures
Appendix
Page 1 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
List of Plate
List of Figures
Page 2 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
List of Appendix
Page 3 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Page 4 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
2.1 Collection of relevant information for the subject property and surrounding area. This
included site area maps and identification of land use.
2.2 Collect flood map of Thailand as being described and collected from Geo-Informatics
and Space Technology Development Agency Gistda 2005-2020 to be used as to
preliminary information for the analysis. Precise elevation and distance of nearest
flood area to construction site have been conducted by high precision GPS
2.3 Collection of historical rainfall data (Daily rainfall data, from the Meteorological
Department) and available information on the existing natural drainage system in the
area;
2.4 A visit of the site, including a visual survey of the entire drainage area as identified from
the maps and data collected. Discussions with the farmers and local population to
understand the historical flood levels in the area.
2.5 Investigate around the vicinity to find evidence of the highest flood marks or signs ever
existed.
2.6 Level checks those marks or signs (if any) compared with the referenced road levels
which contractor will use to decide the final fill level.
2.7 A review of readily available records and documents on the hydrology of the area, to
assist in determining surface water drainage patterns for the subject property and
adjacent areas:
2.8 Estimation of design parameters, including storm intensity based on the rainfall data
collected for this area. In absence of site-specific information, standard engineering
assumptions and factors of safety are applied to available information on this issue;
2.9 Estimation of the peak discharges for various return period floods using modeling |
approach with the help of Hydrology Studio software;
2.10 Analysis and estimation of the High Flood Levels (HFLs) for the site location using
the modeling approach with the help of Geo-HecRas software;
2.11 Flood Risk Analysis of The Site, including the flood levels likely to be reached for
various scenarios and the impact of these flood levels at the site; and
2.13 Protect neighboring plots from flooding caused by the plant / the plant’s mitigation
techniques
Page 5 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
3.1 Studied the available data of the site to obtain a general knowledge of the site
including collecting flood maps between the years 2005-2020 from Gistda.
3.2 Site survey over construction starts from the nearest BM from the Ministry of Agriculture and
Cooperative to the nearest flood area by high precision GPS model Trimble R8s GPS system has been
used for collection co-ordinate and elevation of ground spot covering flood map area and a project site in
Kinematics mode by installation on a moving vehicle and combination of ground pacing.
One unit of Trimble R8s GPS has been used a base station installed on the nearest BM
from the Ministry of Agriculture and Cooperative all the time during the period of
measurement while other 2 GPS have been used as a rower for collecting ground
data(X, Y, Z) in UTM WGS 1984-47N system.
3.3 Confirm work done in 3.2 by visiting the site, interviewing the residents in the vicinity and
looked for any marks or signs that could represent the highest flood level ever experienced in the area.
Those marks could be on the piers of the bridges or on the walls or fences of permanent structures such
as buildings, temples, etc.
3.5 Perform the analysis for prediction of 100 years ARI of highest water level from Chao Phaya
River by Gumbel distribution and correlate to flood elevation on the project site.
3.6 Suggestion on flood mitigation and protection of the ground solar plant.
Page 6 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Page 7 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Page 8 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Page 9 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Computation and Data Analysis for Overtopping from the Chao Phraya River for the peak
Water Level Calculation has been conducted by Gumbel Distribution Analysis
Distance from the project site to hydrological gauge station (Nonthaburi Bridge) is 2.104
km, the maximum water level is considered as the computed 25 or 50 or 100 years flood level of
that particular station and then adjusted with the project site area.
The maxim annual water level of the hydrological gauge station (Nonthaburi Bridge) is
shown in Plate 5-1
The computation for peak water level has been done by using Gumbel’s Method
The following analysis has been done by using Gumbel’s Extreme value distribution
equation:
Where,
XT - Peak Water Level for a specific return period (m)
X̄ - Mean Peak Water Level (m)
‐ Standard Deviation
T - Return Period
n - Number of Year Records, available
KT - V.T. Chow's frequency factor for T-years return period
10
Page 10 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Plate 5-3: Result of Peak Water Level Calculation using Gumbel Distribution
Analysis at Nonthaburi Bridge Station
The result of peak water level in Plate 5-3, demonstrated the design HWL for 25, 50, and
100 years return periods at Nonthaburi Bridge Gauge Station are 3.245m, 3.613m, and 3.978 m
respectively.
From field survey by high precision GPS, the distance from the project site to Nonthaburi
Bridge Gauge Station is 2.104 km and the gradient is 0.00011 m/m. |
Hence, the design HWL at each ARI at the project site is calculated below.
• For 25 years return period at the project site has been computed as 3.245-
(0.00011x2104) = 3.014 m.
• For 50 years return period, design HWL has been computed as 3.613-
(0.00011x2104) =3.382 m.
• For 100 years return period, design HWL has been computed as 3.978-
(0.00011x2104) =3.747 m.
11
Page 11 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
6.1 The predicted flood level at the project site for 100 years ARI is EL.3.747 m.
6.3 Average elevation for the proposed area for the ground solar plant is EL. 1.324 m. and
considered to be the lowest ground elevation among the surrounded areas.
The surveyed area will collect water from all directions with no discharge point.
6.4 Average flood depth on construction site is 3.747 -1.324 = 2.432 m. with the flood
depth between 0.6 m. to 3.8 m.
12
Page 12 of 59
Infratech Energy Co., Ltd. Flood Study: Elec & Eltek Project
Plate 6-2: Sample of the typically elevated PV module in the flooded area
Walkway for communication within solar plant is to be provided as shown in the picture below;
It is suggested to perform soil investigation for the design of piling work for PV module
structure and walkway.
13
Page 13 of 59
Figure 1
Topographic Map
Page 14 of 59
Page 15 of 59
Page 16 of 59
Page 17 of 59
Page 18 of 59
Page 19 of 59
Page 20 of 59
Page 21 of 59
Page 22 of 59
Page 23 of 59
Page 24 of 59
Page 25 of 59
Page 26 of 59
Page 27 of 59
Figure 2
Page 28 of 59
Page 29 of 59
Created with GeoHECRAS 2D v3.1.0.970
ภาพถ่ ายแนวสารวจปริมาณนา้ สถานี C.55 แม่ นา้ เจ้ าพระยา อ.เมือง จ.ปทุมธานี
-6.00
-13.00
Ref:http://hydro-5.rid.go.th/
Elevation was adjusted to corelate to Ministry of Agriculture and Cooperatives Ground Control Point
Page 30 of 59
ภาพถ่ ายแนวสารวจปริมาณนา้ สถานี C.38 แม่ นา้ เจ้ าพระยา รร.คณะราษฎร์ บารุ ง อ.เมือง จ.ปทุมธานี
-1.00
ระดับ - เมตร ( รทก.)
-6.00
-11.00
-16.00
River Bed -16.980 M.(MSL.)
-21.00
-60 -20 20 60 100 140 180 220 260
ระยะ - เมตร
Ref:http://hydro-5.rid.go.th/
Elevation was adjusted to corelate to Ministry of Agriculture and Cooperatives Ground Control Point
Page 31 of 59
ภาพถ่ ายแนวสารวจปริมาณนา้ สถานี C.22A แม่ นา้ เจ้ าพระยา อ.ปากเกร็ด จ.นนทบุรี
-6.00
-13.00
Ref:http://hydro-5.rid.go.th/
Elevation was adjusted to corelate to Ministry of Agriculture and Cooperatives Ground Control Point
Page 32 of 59
Appendix A
Page 33 of 59
Page 34 of 59
Page 35 of 59
Appendix B
Page 36 of 59
Page 37 of 59
Page 38 of 59
Page 39 of 59
Page 40 of 59
Page 41 of 59
Page 42 of 59
Page 43 of 59
Page 44 of 59
Page 45 of 59
Page 46 of 59
Page 47 of 59
Page 48 of 59
Page 49 of 59
Page 50 of 59
Page 51 of 59
Page 52 of 59
Appendix C
Equipment Details
Page 53 of 59
DATASHEET
Trimble R8s
GNSS SYSTEM
One Receiver Configured for Today Communication Options and Remote
Scalable for Tomorrow Access Via Web UI Key Features
Rather than a pre‑configured system, the The Trimble R8s GNSS receiver provides data
Trimble® R8s GNSS system gives you just the communication options including an integrated
features and benefits you need, in one flexible, wide-band UHF radio or 3G cellular modem. ► One configurable receiver that is scalable
scalable system. It’s never been easier to build a for future needs
system tailored to your job. Trimble’s exclusive Web UI eliminates the need ► Available in post-processing, base only,
to travel for routine monitoring of base station rover only, or base & rover configurations
The Trimble R8s easily integrates with Trimble receivers.
S-Series total stations and the innovative
► Advanced satellite tracking with Trimble
Trimble V10 imaging rover. Create a complete The Complete Solution 360 receiver technology
solution by combining the Trimble R8s receiver Create an industry-leading field solution by ► Includes Trimble Maxwell 6 chips with
with a Trimble controller running Trimble pairing the Trimble R8s GNSS receiver with 440 channels
Access™ field software, and Trimble Business a powerful Trimble controller loaded with our ► Simple integration with Trimble S-Series
Center office software. easy‑to-use Trimble Access field software. Total Stations and the V10 Imaging Rover
Configure and Scale With Ease Trimble Access field software offers the features ► Intuitive Trimble Access Field Software and
With the Trimble R8s, it’s easy and simple to and capabilities to simplify everyday work. Our Trimble Business Center Office Software
build a receiver that is right for the job. Choose streamlined workflow modules such as Roads,
the configuration level that suits your needs Monitoring, Mines, and Tunnels guide crews
best, whether it’s post-processing, base, rover, through common project types, enabling them
or a combination of base and rover functionality. to get the job done faster. Survey companies
After you’ve selected a configuration level, can also implement their unique workflows
additional individual options can be added to by taking advantage of the customization
further extend the receiver functionality. capabilities available in the Trimble Access
Software Development Kit (SDK).
The Trimble R8s offers the ultimate in scalability.
As your requirements change, the Trimble R8s Once you’re back in the office, Trimble Business
can adapt. Simply add functionality whenever Center enables you to check, process and
you need it. adjust your data with confidence. No matter
what Trimble solution you use in the field, you
Trimble 360 Technology can trust that Trimble Business Center office
software will help you generate industry leading
Each Trimble R8s comes integrated with
deliverables.
powerful Trimble 360 tracking technology that
supports signals from all existing and planned
Trimble Mobile App—A New Way to
constellations, and augmentation systems.
Quickly Collect GNSS Raw Data
Trimble 360 technology can expand the reach
of your GNSS rover to sites that were previously The Trimble DL Android app provides a simple
inaccessible due to moderate vegetation or and easy to use mobile interface for collecting
other obstructions by taking advantage of the static GNSS raw data for post-processing
availability of additional satellite signals. purposes without the need of using a Trimble
controller or Trimble Access field software.
The Trimble R8s includes two integrated This free of charge app is available through the
Maxwell™ 6 chips and 440 GNSS channels. Google Play Store and operates on Android
Capable of tracking a full range of satellite smart phones and tablets.
systems, including GPS, GLONASS, Galileo,
BeiDou and QZSS.
© 2015-2020, Trimble Inc. All rights reserved. Trimble and the Globe & Triangle logo are trademarks of Trimble Inc., registered in the United States and in other countries. Access and Maxwell
are trademarks of Trimble Inc. The Bluetooth word mark and logos are owned by the Bluetooth SIG, Inc. and any use of such marks by Trimble Inc. is under license. Android and Google Play are
trademarks of Google Inc. All other trademarks are the property of their respective owners. PN 022516-130C (10/20)
3LFWXUHRI$FWLYLWLHV
Page 56 of 59
Page 57 of 59
Page 58 of 59
Page 59 of 59