COMMISSIONING CHECK RECORD SHEET

System n° : ITR reference : INSTRUMENT PANEL

Sub-system n° : ITR code : A-IN-1008


Item Description Yes No N/A
1 Tag plate fitted with correct Tag number.

2 Nameplate securely attached, legible not obscured and data conforms to the
information given on the data sheet.
3 Equipment suitable for Area classification.

4 Terminals undamaged.

5 No dust inside Panel/ JB and insulation surfaces are clean.

6 Panel externally clean.

7 I.P. rating as specified.

8 Panel as specified, all internal items installed.

9 Equipment undamaged and doors operational. Shipping stops / packing removed.

10 All holding down bolts used and tight, equipment vibration free.

11 Equipment erected as shown on the Plot Plan / General Arrangement’s and access
is acceptable.
12 All dust seals undamaged and unused gland entries plugged correctly.

13 All electrical connections correct and tight.

14 All connections to earth bosses correctly installed and internal earthing correct.

15 Fuse ratings correct. Correct fuses and links inserted.

16 Segregation between Power, I.S. and Non I.S. is correct.

17 Heater and / or Air Conditioning Unit installed correctly.

18 Alarm legends and Instrument Tag plates correct.

19 Tubing and piping “Hook-up” complete and flushed.

20 Cable core connections correct and identified correctly.

Remarks
Completed by Witnessed by Accepted by Others
Company
Signature
Name
Date