Plan Service Periodic MARET 2020

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

PT.

Primajaya Persada Nusantara


Job Site PAMA-KIDECO
Monthly Plan Periodical Service Unit & Backlog
Periode : MARET 2020

PLAN PENARIKAN UNIT PLAN EKSEKUSI BACKLOG


LAMA PARETO LAST
PENGERJA LOKASI PRIORITAS DOWNTIME
NO EGI C/N PIC STATUS MONTH (Trend BUS BS PA REMARKS
KETERSEDIAA AN BS KERJA PEKERJAAN BD) BUS (HRS)
TANGGAL HM UNIT PS TYPE ITEM BACKLOG (HRS)
N SPARE PART

1 KIPJEX051 13-Mar-20 14500 2 Pengelasan bucket On site 4 Afrianto Coal Urgent Close B/D Attachment
PC 300 M0-8 system 24 72.7% 27.3% 95.6%
2 KIPJEX051 29-Mar-20 14750 3 Service saja On site 5 Musa Coal Urgent Open
1 KIPJEX058 07-Mar-20 9750 3 Service saja On site 4 Afrianto PSV Urgent Close
PC 300 M0-8 B/D Engine system 12 54.5% 45.5% 97.0%
2 KIPJEX058 27-Mar-20 10000 4 Pengelasan link H On site 6 Slamet PSV Urgent Close
19 36 63.6% 36.4% 96.3%

1 KIPJEX053 03-Mar-20 11750 3 Ganti resistors On site 6 Mislan Coal Urgent Close B/D Attachment
PC 200 M0-8 24 66.7% 33.3% 95.2%
2 KIPJEX053 19-Mar-20 12000 4 Ganti seal cylinder boom On site 6 Mislan Coal Urgent Close system

1 KIPJEX061 02-Mar-20 6500 2


ganti lock tooth, safety On site 12 Mislan Coal Urgent Close B/D Engine
swing, termostat AC system, opt
PC 200 M0-8 accessoriess, 24 100.0% 0.0% 100.0%
2 KIPJEX061 20-Mar-20 6750 3 Ganti bucket On site 6 Agung Coal Urgent Close undercarrieage
system
24 24 100.0% 0.0% 100.0%

1 KIPJDZ032 14-Mar-20 3250 1 Pengelasan canopy On site 4 Afrianto Drilling Urgent Close B/D Electrict
D85ESS-2 12 75.0% 25.0% 97.8%
2 KIPJDZ032 30-Mar-20 3500 2 Service saja On site 5 Musa Drilling Urgent Close system
9 12 75.0% 25.0% 97.8%

1 KIPJCP004 04-Mar-20 11750 3 Service saja On site 4 Musa PSV Urgent Close B/D OPT.
BW211D-40 24 85.7% 14.3% 96.2%
2 KIPJCP004 26-Mar-20 12000 4 Ganti hose pompa On site 6 Agung PSV Urgent Close Accesoriess
B/D engine
1 BW211D-40 KIPJCP005 17-Mar-20 11750 3 Service saja On site 4 Afrianto PSV Urgent Close system, electrict 72 94.7% 5.3% 89.8%
system
13 14 12 96 90.2% 9.8% 93.0%

Achiv BL 92.31%
Target PA 95.14% Target BS 17.78%
Target Ach BL 80.00% Target BUS 82.22%

Dibuat, Disetujui, Mengetahui,

Afifah Yunivia S. ................................. Saiful Misbach


Planner Mekanik Site Manager
PT. Primajaya Persada Nusantara MONTHLY PLAN PERIODICAL SERVICE UNIT
Job Site PAMA-KIDECO
Periode: Maret 2020
Plan Eksekusi Plan Eksekusi Backlog
Kesediaan Lama Lokasi Prioritas
No EGI C/N Mek Remark
Tanggal HM Unit PS Type Item Backlog P/N Sparepart Desc Sparepart Jumlah Sparepart Pengerjaan Kerja Pekerjaan
BL/PS
ST-TH-006 termostat 1 pcs
1 PC 200 KIPJEX061 2-Mar-20 6500 2 ganti lock tooth, safety swing, termostat AC On site 12 jam Mislan Coal Urgent Open
LB52U 4.00mm kawat las 1 pack
2 PC 200 KIPJEX053 3-Mar-20 11750 3 ganti resistors AC ST-WR-006 resistors 1 pcs On site 6 jam Mislan Coal Urgent Open
3 BW211D KIPJCP004 4-Mar-20 11750 3 On site 4 jam Musa PSV Urgent Open
4 PC 300 KIPJEX058 7-Mar-20 9750 3 On site 4 jam Afrianto PSV Urgent Open
5 PC 300 KIPJEX051 13-Mar-20 14500 2 On site 5 jam Afrianto Coal Urgent Open
6 D85ESS KIPJDZ032 14-Mar-20 3250 1 On site 4 jam Afrianto Drilling Urgent Open
7 BW211D KIPJCP005 17-Mar-20 11750 3 On site 4 jam Afrianto PSV Urgent Open
8 PC 200 KIPJEX053 19-Mar-20 12000 4 Ganti seal cylinder boom 707-98-46280 service kit 1 set On site 6 jam Mislan Coal Urgent Open
9 PC 200 KIPJEX061 20-Mar-20 6750 3 Ganti bucket bucket repair On site 6 jam Agung Coal Urgent Open
10 BW211D KIPJCP004 26-Mar-20 12000 4 Ganti hose pompa hose 1 pcs On site 6 jam Agung PSV Urgent Open
11 PC 300 KIPJEX058 27-Mar-20 10000 4 pengelasan link H LB52U 4.00mm kawat las 1 pack On site 6 jam Slamet PSV Urgent Open
12 PC 300 KIPJEX051 29-Mar-20 14750 3 On site 4 jam Musa Coal Urgent Open
13 D85ESS KIPJDZ032 30-Mar-20 3500 2 On site 5 jam Musa Drilling Urgent Open
Note: Service sewaktu - waktu dapat berubah melihat keadaan Breakdown unit, Cuaca , Delay , Idle, Man power, dll.

Dibuat Oleh, Mengetahui, Mengetahui, Disetujui,

Afifah Yunivia S. Ahmad Ibnu ______________________ Saiful Misbach


Planner Logistik Mekanik Site Manager
SCHEDULE PERIODIC SERVICE
PERIODE: 01 sd 31 Maret 2020

PS I (250) PS II (500) PS III (750) PS IV (1.000)


NO C/N Unit Equipment PLAN PLAN PLAN PLAN REMARK
HM Date HM Date HM Date HM Date
1 KIPJDZ-32 D85ESS-2 3,250 14.03.2020 3,500 30.03.2020
2 KIPJEX 43 PC 300-8
3 KIPJEX 51 PC 300-8 14,500 13.03.2020 14,750 29.03.2020
4 KIPJEX 53 PC 200-8 11,750 03.03.2020 12,000 19.03.2020
5 KIPJEX 58 PC 300-8 9,750 07.03.2020 10,000 27.03.2020
6 KIPJEX 61 PC 200-8 6,500 02.03.2020 6,750 20.03.2020
7 KIPJCP 04 BW211D-40 11750 04.03.2020 12,000 26.03.2020
8 KIPJCP 05 BW211D-40 11,750 17.03.2020

Dibuat oleh, Diketahui Oleh, Diketahui Oleh, Mengetahui

Afifah Y. S. A. Ibnu ………………………… Saiful Misbach


Planner Logistik Mekanik Site Manager
SCHEDULE PERIODIC SERVICE
PT PRIMA JAYA PERSADA NUSANTARA
PERIODE: 1 s/d 7 Maret 2020

PLAN SERVICE ACTIVITY


DATE ENGINE UNIT Estimasi PIC REMARK
PS HM (INCLUDE BACKLOG)
1-Mar-20
2-Mar-20 PC 200 KIPJEX061 2 6500 ganti lock tooth, safety swing, termostat AC 12 Jam Mislan
3-Mar-20 PC 200 KIPJEX053 3 11750 ganti resistors AC 6 Jam Mislan
4-Mar-20 BW211D KIPJCP004 3 11750 4 Jam Musa
5-Mar-20
6-Mar-20
7-Mar-20 PC 300 KIPJEX058 3 9750 4 Jam Afrianto
Note: Service sewaktu - waktu dapat berubah melihat keadaan Breakdown unit, Cuaca , Delay , Idle dll.

Plan cuci unit Week 1


Periode: Maret 2020
UNIT PLAN DAY KET
EX043 1-Mar-20 Minggu
EX051 1-Mar-20 Minggu
EX053 1-Mar-20 Minggu
EX058 1-Mar-20 Minggu
EX061 1-Mar-20 Minggu
DZ032 1-Mar-20 Minggu
CP004 1-Mar-20 Minggu
CP005 1-Mar-20 Minggu

Dibuat, Disetujui, Disetujui, Disetujui, Mengetahui,

Afifah Y.S. A. Ibnu ……………………….. ……………………….. Saiful Misbach


Planner Logistic Mekanic Foreman Site Manager
SCHEDULE PERIODIC SERVICE
PT PRIMA JAYA PERSADA NUSANTARA
PERIODE: 8 s.d 14 Maret 2020

PLAN SERVICE
DATE EGI UNIT ACTIVITY (INCLUDE BACKLOG) Estimasi PIC REMARK
PS HM

8-Mar PC-300 KIPJEX58 3 9750 4 Jam Arfrianto

9-Mar

10-Mar

11-Mar

12-Mar

13-Mar PC-300 KIPJEX51 2 14500 5 Arfrianto

14-Mar D85ESS-2 KIPJDZ32 1 3250 4 Arfrianto


Note: Service sewaktu - waktu dapat berubah melihat keadaan Breakdown unit, Cuaca , Delay , Idle, Man power, dll.

Plan cuci unit Week 2


Periode: Maret 2020
UNIT PLAN DAY KET
EX043 8-Mar-20 Minggu
EX051 8-Mar-20 Minggu
EX053 8-Mar-20 Minggu
EX058 8-Mar-20 Minggu
EX061 8-Mar-20 Minggu
DZ032 8-Mar-20 Minggu
CP004 8-Mar-20 Minggu
CP005 8-Mar-20 Minggu

Dibuat, Disetujui, Disetujui, Disetujui, Mengetahui,

Afifah Y.S. A. Ibnu …………………… …………………… Saiful Misbach


Planner Logistic Mekanic Foreman Site Manager
SCHEDULE PERIODIC SERVICE
PT PRIMA JAYA PERSADA NUSANTARA
PERIODE: 15 s.d 21 Maret 2020

PLAN SERVICE ACTIVITY


DATE EGI UNIT Estimasi PIC REMARK
PS HM (INCLUDE BACKLOG)

15-Mar D85ESS-2 KIPJDZ32 1 3250 4 Jam Arfrianto

16-Mar

17-Mar BW211D-40 KIPJCP05 3 11750 4 Jam Arfrianto

18-Mar

19-Mar PC-200 M0 KIPJEX53 4 12000 6 Jam Arfrianto

20-Mar PC-200 M0 KIPJEX61 3 6750 Ganti bucket 6 Jam Agung, Arfrianto 2 Jam Pengerjaan backlog

21-Mar

Note: Service sewaktu - waktu dapat berubah melihat keadaan Breakdown unit, Cuaca , Delay , Idle, Man power, dll.

Plan cuci unit Week 3


Periode: Maret 2020
UNIT PLAN DAY KET
EX043 15-Mar-20 Minggu
EX051 15-Mar-20 Minggu
EX053 15-Mar-20 Minggu
EX058 15-Mar-20 Minggu
EX061 15-Mar-20 Minggu
DZ032 15-Mar-20 Minggu
CP004 15-Mar-20 Minggu
CP005 15-Mar-20 Minggu

Dibuat, Disetujui, Disetujui, Disetujui, Mengetahui,

Afifah Y.S. A. Ibnu …………………… …………………… Saiful Misbach


Planner Logistic Mekanic Foreman Site Manager
SCHEDULE PERIODIC SERVICE
PT PRIMA JAYA PERSADA NUSANTARA
PERIODE: 22 s.d 31 Maret 2020

PLAN SERVICE
DATE EGI UNIT ACTIVITY (INCLUDE BACKLOG) Estimasi PIC REMARK
PS HM
22-Mar
23-Mar PC 200 KIPJEX061 3 6750 Ganti bucket 4 Jam Mislan
24-Mar
25-Mar
26-Mar BW211D KIPJCP004 4 12000 Ganti hose pompa 6 Jam Agung
27-Mar PC 300 KIPJEX058 4 10000 Pengelasan link H 12 Jam Slamet
28-Mar
29-Mar PC 300 KIPJEX051 3 14750 4 Jam Musa
30-Mar D85ESS KIPJDZ032 2 3500 5 Jam Musa
31-Mar
Note: Service sewaktu - waktu dapat berubah melihat keadaan Breakdown unit, Cuaca , Delay , Idle, Man power, dll.

Plan cuci unit Week 4


Periode: Maret 2020
UNIT PLAN DAY REMARK
EX043 22-Feb-20 Minggu
EX051 22-Feb-20 Minggu
EX053 22-Feb-20 Minggu
EX058 22-Feb-20 Minggu
EX061 22-Feb-20 Minggu
DZ032 22-Feb-20 Minggu
CP004 22-Feb-20 Minggu
CP005 22-Feb-20 Minggu

Dibuat, Disetujui, Disetujui, Disetujui, Mengetahui,

Afifah Y.S. A. Ibnu …………………… …………………… Saiful Misbach


Planner Logistic Mekanic Foreman Site Manager