Professional Documents
Culture Documents
Final How Fast Shall It Be XXX
Final How Fast Shall It Be XXX
net/publication/351729889
CITATIONS READS
3 687
3 authors, including:
Some of the authors of this publication are also working on these related projects:
Minimization of Power Interruption Time in Modern MV Networks Based on Optimal Placement of Fault Passage Indicators (FPI) View project
All content following this page was uploaded by Zoran Gajic on 23 May 2021.
ABSTRACT An ultra-high-speed protective relay has been an important topic within the scientific com-
munity, and specifically within the power industry, for decades. The main drivers are the anticipated
improvements in power system stability and power transfer capability which have become even more
important with the increased penetration of renewable generation sources. The relay operate time is a
relatively small part of the required improvement, since the circuit breaker interrupting time contributes
the major part of the total fault clearing time. The first promising results in reducing the fault clearing time,
from two or three cycles, down to one power system cycle, date back to 1976 when the relay operate time
of 1.5 ms was achieved. Availability of sub-cycle breakers was anticipated in the early 1980-s. Nevertheless,
almost forty years later, commercially viable 3/4 cycle breakers are still not available and their impact on
the total fault clearing time has been omitted from most of the literature. The numerical relays operate time
improvement has become the only goal and results are wrongly equalized with improvements in the total
fault clearing time and directly correlated with improvements in power system stability. In this paper the real
benefits of ultra-high-speed relay operate time are analyzed, considering the characteristics of the state-of-
the-art circuit breakers and their interrupting time of 1.5-2 power system cycles (older circuit breakers are
slower). A more holistic view, including interactions between protective relays and circuit breakers, as well
as final benefits to utilities, is given in the paper.
INDEX TERMS Power system protection, line protection, circuit breaker, power system faults, power system
stability, transmission lines.
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/
VOLUME 9, 2021 1
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
FIGURE 2. Definition of Fault Clearing Time (FCT), relay operate time and
circuit breaker interrupting time.
FIGURE 1. Illustration of a fault clearance system that consists of
instrumental transformers, protection equipment and circuit breaker.
adjacent CBs). The relay operate time is the time between the
the performance of relays and circuit breakers are considered fault inception and the moment when the relay operate signal
in combination, along with their combined impact on system triggers the CB to interrupt the current.
stability, is not present in available literature. The circuit breaker interrupting time is the interval of time
In this paper, a new methodology for estimating the total between the beginning of the opening time and the end of
fault clearing time is proposed. The impact of relay operate the arcing time. The opening time is the time between the
time together with circuit breaker interrupting time (i.e total moment when relay signal appears to the CB trip coil until
fault clearing time) on power system stability, is presented. the moment when the arcing CB contacts physically start to
Relevant mechanical and electrical characteristics of widely separate. Vendors usually provide some average value and
used circuit breakers were taken into consideration during variation interval for the opening time. After the arcing con-
the analysis, together with different relay generations (phasor tacts start to separate, the current continues to flow and final
domain, time domain and travelling wave approach). Circuit fault clearing happens when the arc is extinguished, which
breakers are also analyzed from the perspective of require- can occur only at one of the current’s natural zero-crossing
ments from standards and their lifetime. points. The time interval during which current continues to
flow is called the arcing time and thermal and dielectric
II. FAULT CLEARING TIME DEFINITION stresses require a minimum arcing time prior to successful
Fig.1 shows a part of a substation where protection of a power interruption at a fault current zero-crossing [16].
line is illustrated. In order to protect the line (or any other Due to the all mentioned factors there is an embedded
power system element) it is necessary to have: uncertainty in the circuit breaker interrupting time. An even
• instrument transformers – to provide measurements of more important fact is that the nature of that time is discrete
the most important variables related to the protected since current can be interrupted only in the fault current
element (currents and voltages), zero-crossing moments.
• circuit breaker (CB) – to interrupt the fault current (to
allow physical separation of the protected element), III. FAULT CLEARING TIME REQUIREMENTS FROM A
• protection equipment (protective relay) – to recognize POWER SYSTEM PERSPECTIVE
abnormal operating conditions of the protected element There are two main requirements, at the power system level,
and to trigger the circuit breaker operation when needed. that could be related to the protective relay performances:
The trip coil and DC control voltage are also parts of the 1) to minimize damage on power system equipment in
protection system, while all of them together make the fault case of abnormal operating conditions,
clearance system [17]. The protection system complies with 2) to help maintain power system stability.
N-1 requirement since each element is typically duplicated Both requirements imply that the fault clearing time shall be
for HV lines [25], while this is only partially true for the as short as possible. Additionally, in the first case, the relay
circuit breaker. On the power system level, the performance needs to be selective since the unnecessary disconnection of
of the fault clearance system is relevant, not performance of healthy elements affects more customers and system stability.
the protection equipment or circuit breaker itself. From the perspective of the transient stability of power sys-
The total Fault Clearing Time (FCT in Fig.2) is the time tems, besides the speed requirement, a relay must be secure.
between the fault inception and the moment when fault This means that the relay must not trip in the case of a
current is interrupted. It consists of the relay operate time and fault outside of its zone of protection or in the case of a
the circuit breaker interrupting time (if CB operates correctly, disturbance that is not a genuine faulty state. In the case of
otherwise it prolongs until a breaker failure scheme opens a temporary disturbance, incorrect relay operation might lead
2 VOLUME 9, 2021
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
VOLUME 9, 2021 3
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
of the power system. From the perspective of power system the type tests of a widely used CB model and addition-
stability, the FCT with BFP scheme is relevant, as shown in ally, using statistics from CB operations in China Southern
Fig.4. Grid [6]. Finally, >1 million fault cases were simulated and
It is important to notice that in the given example a single- average fault clearing times were calculated for each one of
phase to ground fault is considered as the most optimistic the three generations of protective relays.
scenario. In case of two-phase or three-phase faults the fault
clearing times will be somewhat longer since fault current A. IMPACT OF POWER SYSTEMS ON FAULT
interruption in each phase will occur at different time instants, CLEARING TIME
due to the phase displacement of individual phase currents. In Fig.5, a situation is illustrated where the case of fault cur-
Sometimes series capacitors are used on transmission lines rent zero-crossings occurring at 17 ms, 22.5 ms and 36.6 ms
to increase the line transfer capability; however, there are after fault inception, and relay operate time from 1,5 ms
several negative impacts of series compensation on the perfor- to 11 ms, did not change the total fault clearing time. It is
mance of the line relay protection and the line circuit breaker. obvious that for different zero-crossing moments and/or cir-
A well-known impact on line protection is that the change cuit breaker characteristics the impact of the relay operate
of line series impedance can pose a problem to distance pro- time will differ. In order to have a fair evaluation, a wide
tection. To overcome this, there are several modern solutions range of fault current asymmetry levels were used, resulting
based on communication schemes, which from the perspec- in a different time spread of fault current zero-crossings –
tive of this study do not greatly impact the relay operate different peaks and duration of last major and minor loops,
time [11], [12], [14], [27]. Also, it should be observed that the as shown in Fig. 6.
accumulated energy in the series capacitance will expose the The set of 48 asymmetrical fault current waveforms and
circuit breaker to higher transient recovery voltages [28]. The corresponding zero-crossings were obtained from simula-
resultant prolonged total fault clearing time, will exacerbate tions of power line faults where:
the results presented in this study. • fault inception angle was selected from 0◦ to 330◦ (with
Additionally, according to the international standards 30◦ steps),
[8], [9] the asymmetrical breaker rating is based on the refer- • fault location is varied to achieve different levels of d.c.
ence that the relay operate time is not faster than a half-cycle component (faults close to busbar, at 40 km, 80 km and
of power-frequency (10 ms for 50 Hz and 8.3 ms for 60Hz). 120 km).
If relay operate time is made shorter, it will lead to a higher As an illustration, in Fig.6, 12 waveforms are shown for
percentage of d.c. component at contact separation and in sets of faults close to the busbar and relay location. The first
the worst-case scenario a circuit breaker might not be able to six zero-crossings are recorded for each of the 48 waveforms
interrupt the fault current. In other words, if faster protection and are used for further calculation of fault clearing time
is used, it might be required to derate the CBs and/or perform distribution.
additional system studies to verify if the CBs are still able to
operate properly [10], [24]. This is another factor that needs B. IMPACT OF PROTECTIVE RELAYS ON FAULT
to be considered when the speed of protection is discussed. CLEARING TIME
It would be incorrect (based only on Fig.5) to conclude that The relay operate time depends on a number of factors: the
faster operate times are not beneficial. There are other factors, protection algorithm type, hardware and software limitations
such as fault inception angle and current magnitude, where a (algorithm execution interval, bandwidth of internal filters,
faster relay operate time will lead to a faster FCT. For this speed of output contacts), accuracy of measurement chain
reason, it is important to use a methodology that considers (CT saturation, CVT transients, noise) and a number of exter-
all of the important factors, and shows the real difference nal factors (fault inception angle, fault location, power flow,
in FCT for varying relay performances and considers all of fault resistance etc.). To get exact values it would be required
the pros and cons relevant to power system stability. A new to use products from different vendors with correct settings
methodology for such assessment is proposed and presented and test them in a hardware-in-loop setup with a large number
in Section IV. of test scenarios, which is not practical.
The proposed approach is to divide all numerical relays
IV. FAULT CLEARING TIME EVALUATION METHODOLOGY into three generations, which should cover the main algorithm
The starting point in the proposed methodology is the model- types and hardware limitations.
ing of all relevant system elements. In order to consider all I generation line protective relays are based on low
the uncertainties in power systems (such as fault location, sampling frequency (from <1kHz till a few kHz) and
source impedance, fault inception angle), different fault cur- phasor-domain (PD) algorithms [11], [12] (or some hybrid
rent waveforms were simulated on a network model. All the with incremental quantities). Operate times in the range
variations in relay operate times were statistically modeled of 8 ms – 20 ms are assumed, which should cover the majority
and sorted into three generations of protection devices. The of cases.
circuit breaker’s complex physics is statistically modeled II generation line protective relays use higher sampling
based on ranges of opening and arcing times obtained from frequency (4 kHz – 10 kHz) and time-domain (TD) algo-
4 VOLUME 9, 2021
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
VOLUME 9, 2021 5
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
6 VOLUME 9, 2021
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
TABLE 3. Fault clearing time limits – scenario with circuit breaker model Slightly better improvement in FCT was achieved with TD
based on records from china southern grid. based protection when compared to the slowest, PD protec-
tion; but even in that case, both the average and the maximum
FCT improvements were below 20%. This reinforces the
point that relay operate time cannot be analyzed separately
from circuit breaker interrupting time, which is an equally
Using TW protection, instead of TD, reduces the average important part of the fault clearance system (Fig. 1).
FCT by 3.29 ms or 7%. The maximum FCT is improved by Are those FCT improvements relevant for the transient
5.2 ms or 5.71%. The minimum FCT was improved by 2.5 ms. stability of a power system? The power system stability must
In 66% of fault cases both algorithms cleared the fault in the be secured for the worst-case scenarios and cannot rely on
same time (as illustrated in Fig 4). a few cases where ultra-fast FCT is achieved. The presented
In Fig.13 the distribution of FCT records from CSG [6] reduction in the maximum FCT cannot be taken as an impor-
(CB plus relay operate time) are shown. The range of the tant factor since the ultra-fast protection is not 100% depend-
results fits well into simulated results from Fig.11a, while able, and also, there are faults which would not be detected
FCT distribution is between simulated PD and TD protection with such algorithms, whereas slower and more dependable
since more FCT were in the range of 40 ms – 50 ms than in algorithms will pick them up. Therefore, the power system
the range of 50 ms – 60 ms. stability must be preserved in such situations; even if circuit
breaker fails to operate.
VI. FAULT CLEARING TIME IMPROVEMENTS AND THEIR To secure power system stability, a more reasonable
IMPACT ON THE POWER SYSTEM approach is to secure the fault clearance time below the
The results show that ultra-high speed protection based on critical clearing time in a power system through optimization
TW is capable of clearing faults in about 25 ms, albeit only in of the breaker failure scheme, as presented in a study from
a very limited number of cases. Overall speed improvements China Southern Grid [6]. If in a particular location in the
are very modest, since both the average and the maximum network the critical clearing time is shorter than the possible
FCT improvements were below 10%, when compared to the fault clearing time (with the breaker failure scheme), then
time-domain based algorithms. The main reason for this is it is necessary to use two breakers in series, preferably of
the physics of the short-circuit current interruption process the same make/type [18]. In such a case, at least one of the
and associated circuit breaker technology, which allows for breakers will interrupt the fault and the total clearing time will
fault current interruption to take place only at a few discrete be close to the shortest possible with existing circuit breaker
moments which are separated by approximately half the time technology. There is also an alternative proposal for using a
period increments of the power-frequency cycle: 10 ms at breaking resistor for large thermal generators to increase the
50Hz and 8.33 ms at 60Hz. For this reason, two out of three critical fault clearance time [26].
VOLUME 9, 2021 7
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
8 VOLUME 9, 2021
S. Zubic et al.: Line Protection Operate Time: How Fast Shall It Be?
[2] K. L. Hicks and W. H. Butt, ‘‘Feasibility and economics of ultra-high- [23] A. di Tomasso, G. Invernizzi, and G. Vielmini, ‘‘Line ultra high speed
speed fault clearing,’’ IEEE Trans. Power App. Syst., vol. PAS-99, no. 6, Protection. Principles and field experience,’’ in Proc. AEIT Int. Annu. Conf.
pp. 2138–2145, Nov. 1980. (AEIT), Sep. 2019, pp. 1–6.
[3] M. Chamia and S. Liberman, ‘‘Ultra high speed relay for EHV/UHV [24] N. Metzger, B. Carstens, and F. Heleniak, ‘‘Practical experience with ultra-
transmission lines—Development, design and application,’’ IEEE Trans. high-speed line protective relays,’’ in Proc. 45th Annu. Western Protective
Power App. Syst., vols. PAS–97, no. 6, pp. 2104–2116, Nov. 1978. Relay Conf. Spokane, Oct. 2018, pp. 1–5.
[4] K. Ohse and S. Mitsuhashi, ‘‘Synchronous ABB for one cycle interruption [25] NERC. (Nov. 2008). Protection System Reliability Redun-
delivered to keeler substation, Bonneville Power Administration, U.S.A,’’ dancy of Protection System Elements. [Online]. Available:
Fuji Electr. Rev., vol. 19, no. 3, 1973. Accessed: Mar. 20, 2021. [Online]. https://www.nerc.com/docs/pc/spctf/Redundancy_Tech_Ref_1-14-09.pdf
Available: https://www.fujielectric.com/company/tech_archives/pdf/19- [26] M. Wamundson, S. Lindahl, J. Hagman, D. Johansson, and F. Heyman,
03/FER-19-03-095-1973.pdf ‘‘Dimensioning of EHV series braking resistor for large thermal genera-
[5] ENTSOE, Version 17, SPD-Inertia TF. Inertia and Rate of Change tors,’’ in Proc. IREP Symp. Bulk Power Syst. Dyn. Control, Aug. 2013,
of Frequency (RoCoF). Accessed: Mar. 20, 2021. [Online]. pp. 1–5.
Available: https://eepublicdownloads.azureedge.net/clean-documents/ [27] M. Kockott, S. Zubic, Z. Liu, H. Jernberg, T. Roseburg, and W. Rees,
SOC%20documents/Inertia%20and%20RoCoF_v17_clean.pdf ‘‘A POTT scheme, using transient directional elements, for a complex
[6] Y. Jiang, Z. Hongyang, C. Zhaohui, L. Jie, L. YiQuan, and Z. Shaofan, 525 kV transmission corridor comprising long, heavily loaded and heavily
‘‘The optimization of 500 kV breaker failure protection,’’ in Proc. series compensated parallel lines,’’ in Proc. Western Protective Relay
China Int. Conf. Electr. Distrib. (CICED), Shenzhen, China, Sep. 2014, Conf., 2019, pp. 1–6.
pp. 1755–1758. [28] IEEE Guide for the Application of Transient Recovery Voltage for AC
[7] M. Mohammadhosein, K. Niayesh, A. A. Shayegani-Akmal, and High-Voltage Circuit Breakers with Rated Maximum Voltage above 1000
H. Mohseni, ‘‘Online assessment of contact erosion in high voltage gas V, Standard C37.011-2019 IEEE Std C37.011-2011, Nov. 2019, pp. 1–127.
circuit breakers based on different physical quantities,’’ IEEE Trans. Power
Del., vol. 34, no. 2, pp. 580–587, Apr. 2019.
SINISA ZUBIC was born in Bugojno, Bosnia and
[8] IEEE Standard Rating Structure for AC High-Voltage Circuit Breakers,
Standard C37.04-1999, 2006. Herzegovina, in 1982. He received the M.S.E.E.
[9] International Standard on High-Voltage Switchgear and Controlgear. Part degree in power engineering from the Faculty of
100: Alternating-current circuitbreakers, document IEC 62271-100, 2020. Electrical Engineering, Banja Luka, Bosnia and
[10] B. Kasztenny and J. Rostron, ‘‘Circuit breaker ratings—A primer for pro- Herzegovina, in 2006, and the Ph.D. degree from
tection engineers,’’ in Proc. 71st Annu. Conf. Protective Relay Engineers the University of Belgrade, Serbia, in 2013. He has
(CPRE), College Station, TX, USA, Mar. 2018, pp. 1–13. worked as a Teaching and Research Assistant with
[11] Hitachi ABB Power Grids—Grid Automation Products. (2020). the Faculty of Electrical Engineering, Banja Luka,
Line Distance Protection REL670 Version 2.2 ANSI—Technical till 2014. He joined ABB, in 2014, where he
Manual ABB. [Online]. Available: https://search.abb.com/library/ was the Senior Scientist of the ABB Corporate
Download.aspx?DocumentID=1MRK506369- Research Center, Cracow, Poland. Since 2018, he has been the Research
UUS&LanguageCode=en&DocumentPartId=&Action=Launch and Development Manager (application software) of Hitachi ABB Power
[12] Siemens, Manual. SIPROTEC 5 Distance and Line Differential Grids, Vasteras, Sweden. His main research interest includes power system
Protection, Breaker Management for 1-Pole and 3-Pole Tripping. protection.
Accessed: Mar. 20, 2021. [Online]. Available: https://cache.industry.
siemens.com/dl/files/440/109742440/att_1040496/v1/SIP5_7SA-SD-SL-
VK-87_V08.40_Manual_C011-E_en.pdf ZORAN GAJIC received the M.S.E.E. degree
[13] C. Dzienis, M. Kereit, J. Blumschein, and M. Claus, ‘‘An experimental (Hons.) in power engineering from the University
analysis of high-speed-distance protection,’’ in Proc. Mod. Electr. Power of Belgrade, Serbia, in 1990, and the Ph.D. degree
Syst., Wroclaw, Poland, 2010, pp. 1–8. in electrical engineering from Lund University,
[14] E. O. Schweitzer, B. Kasztenny, A. Guzman, V. Skendzic, and Sweden, in 2008.
M. V. Mynam, ‘‘Speed of line protection–can we break free of phasor lim- He is currently a Relay Protection Expert with
itations?’’ in Proc. 68th Annu. Conf. Protective Relay Engineers, College Grid Automation Products, Hitachi ABB Power
Station, TX, USA, Mar. 2015, pp. 448–461. Grids, Vasteras, Sweden. Since 1993, he has been
[15] B. Kasztenny, M. V. Mynam, T. Yoshi, and D. Holmbo, working in the area of power system protection and
‘‘Preventing line faults with continuous monitoring based on current control within ABB Group of companies, where
traveling waves,’’ in Proc. 15th Int. Conf. Develop. Power Syst. he had various engineering positions. From 2008 to 2015, he was the ABB
Protection 2020, pp. 1–5. [Online]. Available: https://static.selinc.
Global Product Manager for generator and transformer protection. He has
com/assets/Literature/Publications/Technical%20Papers/6957
published many technical articles in the relay protection area and holds
_PreventingLine_TJ_20191107_Web.pdf?v=20210310-184122
more than 20 patents. He has participated in different CIGRE, IEC, and
[16] R. Thomas, ‘‘Controlled switching of high voltage SF6 circuit
breakers for fault interruption,’’ Dept. Elect. Power Eng., Chalmers PSRC/IEEE working groups and was the Convenor of CIGRE Working
Univ. Techn., Göteborg, Sweden, Tech. Rep. 514L, 2004. Accessed: Group ‘‘Modern techniques for Protecting Busbars in HV Networks.’’ In
Mar. 20, 2021. [Online]. Available: http://webfiles.portal.chalmers. 2014, he received the Technical Committee Award from Cigré Study Com-
se/et/Lic/ThomasRichardLic.pdf mittee B5 (Protection and Automation).
[17] S. Lindahl, ‘‘Reliable fault clearance and back-up protection,’’ CIGRE
Working Group, Paris, France, Tech. Rep. 140, Apr. 1999. DAVOR KRALJ was born in Sarajevo, Yugoslavia,
[18] IEEE Guide for Breaker Failure Protection of Power Circuit Breakers, in 1979. He received the M.S.E.E. degree in elec-
Standard C37.119-2016 Std C37.119-2005, Jul. 2016, pp. 1–73. trical engineering from the Electronic Faculty,
[19] H. T. Nguyen, G. Yang, A. H. Nielsen, and P. H. Jensen, ‘‘Combina- Nis, Serbia, in 2010. From 2012 to 2020, he has
tion of synchronous condenser and synthetic inertia for frequency stabil-
worked as a Research and Development Engineer
ity enhancement in low-inertia systems,’’ IEEE Trans. Sustain. Energy,
with ABB Global Technical Lead Center, Ludvika,
vol. 10, no. 3, pp. 997–1005, Jul. 2019.
[20] N. TSOs. (2016) Challenges and Opportunities for the Nordic Power
Sweden, where he worked on developing new and
System. [Online]. Available: https://www.fingrid.fi/en/pages/news/news/ existing SF6 live-tank high voltage circuit break-
2016/report-challenges-and-opportunities-for-the-nordic-power-system/ ers, as well as on implementation of controlled
[21] M. Al Talaq, ‘‘Frequency stability enhancement for a system with inte- switching technology. He is currently working as
grated renewable energy sources and HVDC link,’’ in Proc. Int. Seminar a Technical Expert for substation primary equipment and switchgear with
Appl. Technol. Inf. Commun., 2020, pp. 391–395. Swedish National Grid, Svenska Kraftnet. He is an Active Member of IEC
[22] P. Tielens and D. Van Hertem, ‘‘The relevance of inertia in power systems,’’ TC/SC 17A Switching Devices.
Renew. Sustain. Energy Rev., vol. 55, pp. 999–1009, Mar. 2016.
VOLUME 9, 2021 9