Professional Documents
Culture Documents
221105A-01AF-TED SOM-2022 Final Report
221105A-01AF-TED SOM-2022 Final Report
SEPTEMBER OPPORTUNITY
OF MAINTENANCE
(SOM-2022)
October 2022
1
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CONTENTS
1. Executive Summary
2. Scope of Work
3. Cost
4. Schedule
5. Quality
6. Contractors
8. Summary of Recommendations
9. Lessons Learnt
10. Annexes
2
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
1. Executive Summary
3
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
2. Scope of Work
5
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Duration
Activity Start Date End Date
s (Days)
Plant Ramp Down/ Making Safe 18th September
15th September 2022 04
Condition 2022
Engineering Days
19th September 2022 02nd October 2022 14
Two contractors were selected to support BMC TED Staff during STA-
2021R:
9
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
12
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
13
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
14
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
15
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
17
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
21
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
22
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
23
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Recommendations Rectification works were executed for the choke ring section only,
whereby the debris at the back of the dislodged brick was removed,
and the internal sides prepared with Thermbond Formula 18W. The
brick was gently eased back into position and propped for support
over a period of 12 hours to allow it to set. The prop was removed,
and the cracked surface was coated with Thermbond Formula 18W
as a protective coating. Other area remains as it is, as it pose no
concern for Incinerator operation. It is also recommended to have the
choke ring block replace of the brick due to currently observed of
loose condition. Area above the choke ring to be rectified in next
opportunity where possible.
DPT PT inspection for any anchor weld repair work inside of Incinerator
Finding DPT No removal of existing refractory lining be made; hence no
inspection being performed.
Recommendations No plan unless it was pre-defined on the necessity beforehand or
anticipate refractory lining repair work above the choke ring section
be carrying out.
W-1714 Clarifier
Inspection on the clarifier basin condition after cleaning are done
VISUAL
Inspection on the existing feed piping after cleaning are done
Basin is adequately cleaned up and acceptance. Along the basin
wall observed of spot deterioration of concrete condition at multiple
location along with rusty stained patch.
Structural support for both Agitator shaft and housing unit observed
of severe corrosion and deterioration, posing a risk of broken off and
Finding VT
falling off for the housing. Multiple through holes of sizeable condition
resulting from corrosion effect were noted along the housing casing
itself, and on the agitator shaft structure. The Agitator blade unit also
found to have deteriorated, with the blade rubber being worn out and
entirely defeating the sweeping purpose.
Existing feed piping also noted of multiple corrosion effect perforated
through holes at multiple location. This has deemed the pipe being
unusable and serve no purpose in channeling the waste contents
over its designate path. New pipe spool are available for the
replacement.
26
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Finding Strainer elements are clogged with black deposit and contaminants.
The housing itself also observed of surface contaminant.
Recommendations Proceed for cleaning on both strainer housing and element, followed
by reinstatement works
PS-B1620A-1 Pump Strainer PS-B1620A-1
VISUAL Inspection and Cleaning
Finding Strainer elements are free from deposit clogging. No damaged
observed. Housing itself are observed minor dirt at bottom side.
Recommendations Proceed for cleaning on both strainer housing and element, followed
by reinstatement works
PS-B1620B-1 Pump Strainer PS-B1620B-1
VISUAL Inspection and Cleaning
Finding Strainer elements are free from deposit clogging. No damaged
observed. Housing itself are observed minor dirt at bottom side.
Recommendations Proceed for cleaning on both strainer housing and element, followed
by reinstatement works
FX-18001 Pump Strainer FX-18001
VISUAL Inspection and Cleaning
Finding Strainer elements are free from debris, and with minor dirt on the
meshing. The housing itself are adequate with general cleaning be
require.
Recommendations Proceed for cleaning on both strainer housing and element, followed
by reinstatement works
Corrective Maintenance.
30
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CM
D/S manual valve of HV-1111 jammed open
COLD WORK
Inspect flange surface and cleaning
VISUAL
CM
Incinerator air damper issue
COLD WORK
CM
PTR - Wrong gasket specification installation at Process Area
COLD WORK
CM
PTR - Wrong gasket installation at Compressor area
COLD WORK
Recommendations Carried out flange gasket replacement - 3/4", 1/2"& 1" & 3”1500#
CM
V-1211 valve passing
COLD WORK
31
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CM
Main 8'' FNG burner header flange leak
COLD WORK
CM
K-1201T-E1A Lube Oil Leaked
COLD WORK
CM
FTW line to vapor seal pot (SP1820B) clogging
HOT WORK
VISUAL Cut and remove affected spool / Install and weld with new piping (1
DPT length) / Touch-up painting
Recommendations Replaced.
CM
12"-PTW-11242 line leakage
HOT WORK
VISUAL
Cut and removal/ replacement of 2 length of piping/ Touch up painting
DPT
Findings PT: No indication of significant weld defects for the new line observed
CM
K1101 air ejector gland leak
HOT WORK
VISUAL To carry out hot cut out and replacement of manual valve (1”& 1 ½”
DPT both #800)
32
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CM
Drain valve passing SM inlet to K-1301-P1AT drains
HOT WORK
VISUAL Carry out removal of insulation/ cut out of existing and replacement
DPT with new drain valves (3/4” of 2nos)
PT: No indication of weld defects for the replaced valves. Existing
Findings
valve found worn out of valve part for the packing area.
CM
Drain valve passing RG line to K-1301LP
HOT WORK
VISUAL
To perform cut out and replace valve - 3/4"(1no.)
DPT
PT: No indication of weld defect for the replaced valve. Removed
Findings
found stuck of stem condition
CM
Drain valve passing u/s of PV-1408-2
HOT WORK
VISUAL
To cut out and replace valve - 3/4"(2nos.)
DPT
PT: No indication of weld defect for the replaced valve. The removed
Findings
valve observed of worn-out internal component
CM
Drain valve passing u/s of XV-1412 to V-1406
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 2" #600(2nos)
PT: No indication of weld defect for the replaced valve. The removed
Findings valve observed to be stuck open position possibly due to internal part
corroded.
CM
Drain valve passing u/s of XV-1413 to V-1406
HOT WORK
33
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 2" #600(2nos)
PT: No indication of weld defect for the replaced valve. The removed
Findings valve observed to be stuck open position possibly due to internal part
corroded.
CM
Drain valve passing u/s of HV-1402B to SPC
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(2nos)
PT: No indication of weld defect for the replaced valve. The removed
Findings valve observed to be stuck open position possibly due to jammed
stem
CM
Steam trap faulty (chattering sound) near to E1404
HOT WORK
VISUAL Insulation removal, cut out existing trap and replacement with new -
DPT 3/4"(1no)
No replacement made in this opportunity due to no spare valve
Findings
available
CM
Drain passing downstream of S39 (PG-1407) V-1406 to SL Header
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(1no)
PT: No indication of weld defect for the replaced valve. The removed
Findings valve unable to full close possibly due to foreign material affecting
proper seating of valve
CM
HV-1402A/B drain valve passing
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(4nos)
PT: No indication of weld defect for the replaced valve. Suspected
Findings
improper seating of existing valves.
34
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CM
V-1401 blow down valve jammed
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(1no)
PT: No indication of weld defect for the replaced valve. Existing valve
Findings
suspected of stem sticking over time
CM
TV1214 drain valve passing
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 1.5" 1500#(2nos.)
PT: No indication of weld defect for the replaced valve. Existing valve
Findings
condition yet to be verify.
CM
Steam trap on SM inlet to F-1740 passing
HOT WORK
VISUAL Insulation removal, cut out existing trap and replacement with new -
DPT 3/4"(1no.)
PT: No indication of weld defect for the replaced steam trap valve.
Findings
Possibly of deteriorated internal part for the removed trap valve.
CM
6''-PZ-15121-MC3-HB piping leakage
HOT WORK
VISUAL
DPT To cut out, remove and install new length
RT
PT and RT indicate of good weld quality with no significant defects be
detected. Existing pipe length subjected to process damaged
Findings
mechanism and deteriorated pipe integrity condition resulting from
damaged mechanism in place.
CM
TK-1610 outlet pinhole leak (18''-FTW-11001-LC1)
HOT WORK
35
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
VISUAL
To cut out, remove and install new length (short spool)
DPT
PT: No indication of weld defect for the replaced pipe spool length.
Findings Existing pipe observed of biologically induced corrosion effect from
service fluid.
CM
V-1509 Inlet 26'' RG line leakage
HOT WORK
VISUAL
To carry out cut out and replacement of tee section
DPT
Scope cancelled due to late delivery of require component for pipe
Findings
modification works(purging use).
CM
W-1714 feed 8'' line pinhole leaked
HOT WORK
VISUAL
To cut out, remove and install new length
DPT
PT: No indication of weld defect to be made. Existing pipe length
Findings observed of perforated holes of adequate sizing along the length
resulting from water induced corrosion (waste water).
Recommendations Proceed for re-use of existing pipe flange onto the new pipe length
CM
12"-PTW-11200-LS1 line leakage
HOT WORK
VISUAL
To cut out, remove and install new length (1 length)
DPT
PT: No indication of weld defect for the replaced length. Existing pipe
Findings length observed of biological induced corrosion effect from service
fluid condition
CM
3/4"FTW handwheel found broken
HOT WORK
VISUAL
To cut out and replace valve - 3/4"(1no.)
DPT
PT: No indication of weld defect for the replaced valve. Handwheel
Findings
broken from human factor.
36
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CM
Steam trap passing at Boiler A
HOT WORK
VISUAL
To cut out, remove and install new steam trap
DPT
PT: No indication of weld defect to be noted. Most probably
Findings
deterioration of internal part of removed steam trap made.
CM
Boiler A SH exchanger outlet steam trap passing
HOT WORK
VISUAL
To cut out, remove and install new steam trap
DPT
PT: No indication of weld defect to be noted. Most probably
Findings
deterioration of internal part of removed steam trap made.
CM
Drain spool broke at Boiler A
HOT WORK
VISUAL
To cut out, remove and install new length
DPT
CM
Sampling line valve passing at Boiler B
HOT WORK
VISUAL
To cut out and replace defective valves - 1/2(2nos.) & 3/4"(1no.)
DPT
CM
STG SM block valve jammed
HOT WORK
37
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
VISUAL
To cut out and replace valve - 1 1/2"(1no.)
DPT
PT: No indication of weld defect to be noted. Valve jammed resulting
Findings
from stem in sticking position
CM
Vent Valve passing: SM Inlet to P-1620A
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(1no)
PT: No indication of weld defect to be noted. Deteriorated valve
Findings
seating to be anticipated for the removed valve.
CM
Drain valve passing: SM Header drain near to EDG Station
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(1no)
PT: No indication of weld defect to be noted. Deteriorated valve
Findings
seating to be anticipated for the removed valve.
CM
Drain valve passing: P-1516 discharge drain
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 3/4"(1no)
PT: No indication of weld defect to be noted. Existing valve unable to
Findings be fully closed possibly from presence of deposit restricting such
closure be made
CM
P-1503A vent valve handle broken
HOT WORK
VISUAL
Cut, removal and replace valve - 3/4"(1no)
DPT
PT: No indication of weld defect to be noted. Existing valve handle
Findings
result from human factor
38
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CM
Valve jammed for FX-1510A
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 1"(2nos) & 1.5"(2nos)
PT: No indication of weld defect to be noted. Valve jammed unknown,
Findings
yet to be verify.
CM
E-1205 blow down valve passing (R77, R78 & R79)
HOT WORK
VISUAL Insulation removal, cut out existing valve and replacement with new -
DPT 2" 1500#(3nos.)
PT: No indication of weld defect to be noted. Valve passing may be a
Findings result of stem unable to fully closed due to foreign particle presence
on the stem seating area (similar to previous replacement)
CM
WHB 2"vent valve passing west side of WHB
HOT WORK
VISUAL Unbolt and disconnect piping, cut out existing valve and replacement
DPT with new - 2" 1500#(1no)
PT: No indication of weld defect to be noted. Existing valve potentially
Findings
deteriorated of valve stem condition during in service
Corrosion Maintenance.
For pressure relief valves the following inspection activities were carried out.
VISUAL & Inspection of relief valves at 'as-received' condition prior work bench
TEST testing (workshop)
VISUAL & Inspection of relief valves at 'as-acceptance" condition prior to
TEST dispatch back to site
Supervising, coordinating, managing, and providing quality control
QA/QC roles on relief valve transportation, testing, installation, and
overhauling works at appointed workshop
Findings Replaced.
Findings Replaced.
Findings Replaced.
Findings Replaced.
Findings Replaced.
42
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
43
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
44
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
45
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found satisfactory
according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found
satisfactory according to ASME BPVC VIII.1-2017
46
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found
satisfactory according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found
satisfactory according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found
satisfactory according to ASME BPVC VIII.1-2017
Overhauled.
Recommendations Post pop test, back seat test and bubble test were found
satisfactory according to ASME BPVC VIII.1-2017
47
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Visual Major and minor maintenance of AFC. AFC units as per below.
49
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
52
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Visual Minor maintenance and inspection at tank, strainer and oil filter
including oil sample collection for analysis.
No major findings during external and internal inspection on tank,
Findings
strainer, and oil filter conditions.
Collected lube oil sample to be send for analysis to ensure oil free
Recommendations
from contamination.
54
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
2.2.5 Instrumentation.
Unable to completed for all function during plant start-up due to plant
Recommendations shut down.
Will be carried out remaining function during STA2023 start-up.
FUNCTIONAL Conduct function test after actuator replaced and confirmed good
TEST function.
Recommendations The removed actuators will be repaired and kept as spare parts.
ON-OFF VALVE
HV-1205
RG TO E-1222 BY-PASS_HV-1205 - Overhauling Works
55
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
FUNCTIONAL
Installation and Functional Test at plant site
TEST
ON-OFF VALVE
HV-1204
RG TO E-1222 SHELL_HV-1204 - Overhauling Works
FUNCTIONAL
Installation and Functional Test at plant site
TEST
Confirmed no leakage for body and actuator.
Findings
Replaced booster relay due to air leakage.
ON-OFF VALVE
HV-1209
RG TO E-1223 - Overhauling Works
FUNCTIONAL
Installation and Functional Test at plant site
TEST
Confirmed no leakage for body and actuator.
Findings
Replaced speed controller due to air leakage.
ON-OFF VALVE
XV-1207
E-1223 BTM TO E-1701_XV-1207
Actuator overhaul
Scope
Actuator top cover replacement due to deformation
FUNCTIONAL
Installation and Functional Test at plant site
TEST
56
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
CONTROL VALVE
HV-17001
SM TO FLARE STACK_HV-17001 - Direct Replacement Works
FUNCTIONAL
Installation and Functional Test at plant site
TEST
CONTROL VALVE
LV-1510
LP COLUMN - Overhauling Works
FUNCTIONAL
Installation and Functional Test at plant site
TEST
57
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
58
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
59
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
2.2.6 Electrical.
60
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Finding No findings
Recommendations No recommendation
61
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
At time of plant initial startup, issue on set pressure setting for both PSV-
C1621-1 and PSC-C1621-2 encountered whereby the post-SOM set
pressure were set at lower value compared to design, result in low pH feed
onto BFW service fluid for 2 days. Temporary corrective action taken on the
spot in resetting such set pressure back to design manually.
At current plant shut down resulting from K-1301T issue, no major concern
to be highlighted at.
2.5 Recommendations.
3. Cost
3.1 Original Cost.
62
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
A few additional scope of inspections made during this SOM were notably made
chargeable under the existing Annual Inspection Contract Rates (ad hoc
requisition). The detail on each of such additional scope of inspections are detail as
following.
Tag Description of
NO Change Request
Numbe Additional Origin
. Number
r Inspection
Provision of Services
in supplying manpower BFW Piping
and resources for both Fabrication Class
1 SI-IRS-001 E-1206 PWHT and Genset for requirement as per
E-1206 BFW Piping Specification
Fabrication Works on document
site
63
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Tag Description of
NO Change Request
Numbe Additional Origin
. Number
r Inspection
3.3 Recommendations.
4. Schedule
4.1 Original Schedule.
Primary gas seal vent High-High alarm was detected for K-1301 HP side
during compression startup operation (65% Reformer load), leading to
further high alarm on primary gas seal vent of DE side and eventual K-
1301T tripped operation. It was decided to perform total Reformer shut
down for rectifying on the issue arose.
Plant Startup Operation was thus interrupted resulting from such failure
finding and progressive shut down occurred in finding on fault cause and
necessary rectification works.
4.3 Recommendations.
5. Quality
5.1 Definition
66
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Non-conformity NCR form was also delivered for those cases where there is
an identified major deviation (see Section 10.3)
For NDT Inspection Contractor and Main Contractor, a QA/QC team was
requested.
67
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
5.3 Recommendations.
6. Contractors
6.1 Organization
68
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
6.3 Recommendations.
69
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
7.1 Organizations
70
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
71
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
72
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
9. Lessons Learnt
74
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Planning Equipment listing not The defined listing are not taking into consideration on
Stage properly defined for previous recommendations, such need to be review
execution thoroughly in order to optimize on opportunity for
execution
Planning Scope for maintenance Change of scope are within MTD, and not properly
Stage change without cascade to SOM members. It is important to provide
awareness such cascading time to time to ensure all updates are
as per latest edition
Planning Cancellation of scope Weekly meeting shall be used to highlight on any issue
Stage not mutually agree at of concern, and way forward/ decision on proceeding,
instead of only between selected personnel
Planning Lack of proper Lack of follow up and communicating between
Stage coordination and department to ensure smooth preparation are in place.
communication MTD need to provide such communication time to time
with all department involve
Pre-SOM Lack in follow up on Discipline focal point shall take lead in coordinating with
Stage Contractor preparation Contractor in ensuring all preparation are adequate,
instead on relying on MTP for the overall scope.
Pre-SOM Lack understanding on Both BMC and Contractor lack the content and
Stage work pack scope understanding on work pack scope, require re-
educating BMC internal, and get the right person for the
right job for contractor side
Pre-SOM Internal inadequacy for Spare part list unable to be define due to lack of
Stage spare part preparation responsibility by focal person. Instruction need to be
made to all for mutual understanding and commitment
SOM Stage Poor resource planning Lack of resources by Contractor will require to be re-
by Contractor assess in ensuring all resources are well ahead plan
and in place prior to SOM execution
SOM Stage Poor understanding of Contractor supervisor do not have experience and
Contractor in knowledge on equipment scope. Assessment on
undertaking on supervisory level require to be made in advance, prior
maintenance works to undertake on the scope.
Cost Cost variance: a. PWHT services was overlooked, and
a. Cost variance by fabrication requirement shall be thoroughly
IRS review to incoporate on any other services be
b. Cost variance by require in future exection
PTAS b. IRIS inspection that are conducted at
opportunity will require to be kept as firmed
scope of % application in future engagement
Schedule a. Insulation a. Lack of resources and understanding can be
removal works minimized with a better coordination
b. Scaffolding b. Lack of resources and understanding can be
erection minimized with a better coordination
c. Delays in c. Lack of permit awareness on requirement, poor
maintenance setup of site preparation and lack for
commencement management in coordination need to be re-
of works look.
NDT Lack of detailed Request during contracting process a minimum
Inspection information and clarity of standard of prepsentation reqired by BMC during SOM
75
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
Management Late submission and To enable advanced/ early engagement and to provide
, approval of require firm allocation of assigned personnel at least 1 mnth in
Staffing and documentations owing to advance without any inerruption of planning
Organization constant change of
resources
10. Annexes
10.1 Final Inspection Reports.
SOM-2022 final inspection reports are available in the BMC Share Point
TED & MTD Search Engine.
76
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
77
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
78
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
79
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
80
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
81
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
82
DATE:
BMC BRUNEI METHANOL COMPANY
SEPTEMBER OPPORTUNITY OF MAINTENANCE SOM 2022 OCTOBER 2022
83