Professional Documents
Culture Documents
Schedule For Unit Concrete
Schedule For Unit Concrete
KSPH NAGARBHAVI
UNITS INNER CONCRETE WORK SCHEDULE
D BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE
C BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE
1 PLINTH BEAM OF 4 UNITS 1/8/2018 4/8/2018 4DAYS
THANKING YOU
SCHEDULED BY