K GOWDA & CO

KSPH NAGARBHAVI
UNITS INNER CONCRETE WORK SCHEDULE

SHUTTERING WORK BLOCK UNITS D & C BLOCK NO OF DELAYED REASONS IF


SL NO DESCRIPTION DESCRIPTION NAME NAME DAYS ANY STATUS
STARTING DATE COMPLETION DATE
SHUTTERING &
1 LINTELS, FINS,KITCHEN 26/04/2019 28/04/2019 3DAYS
REINFORCEMENT WORK
SLAB ( OF ALL 8 UNITS) 101, 102,
2 CONCRETING WORK BLOCK D 29/04/2019 30/04/2019 2DAYS
GROUND 103, 104,
105, 106,
LOFT SHUTTRING & FLOOR
3 107, 108 1/5/2019 1/5/2019 1DAYS
REINFORCEMENT WORK LOFTS ( OF ALL 8 UNITS)
4 CONCRETING WORK 2/5/2019 2/5/2019 1DAYS
SHUTTERING &
5 LINTELS, FINS,KITCHEN 29/04/2019 1/5/2019 3DAYS
REINFORCEMENT WORK
SLAB ( OF ALL 8 UNITS) 201, 202,
6 CONCRETING WORK BLOCK C 203, 204, 2/5/2019 3/5/2019 2DAYS
GROUND
LOFT SHUTTRING & 205, 206,
7 FLOOR 207, 208 4/5/2019 4/5/2019 1DAYS
REINFORCEMENT WORK LOFTS ( OF ALL 8 UNITS)
8 CONCRETING WORK 5/5/2019 5/5/2019 1DAYS

9 SHUTTERING & 2/5/2019 5/5/2019 3DAYS


REINFORCEMENT WORK LINTELS, FINS,KITCHEN
SLAB ( OF ALL 8 UNITS) 201, 202,
10 CONCRETING WORK BLOCK D 6/5/2019 7/5/2019 2DAYS
203, 204,
FIRST
LOFT SHUTTRING & 205, 206,
11 FLOOR 207, 208 8/5/2019 8/5/2019 1DAYS
REINFORCEMENT WORK LOFTS ( OF ALL 8 UNITS)
12 CONCRETING WORK 9/5/2019 9/5/2019 1DAYS
SHUTTERING &
13 LINTELS, FINS,KITCHEN 6/5/2019 8/5/2019 3DAYS
REINFORCEMENT WORK
SLAB ( OF ALL 8 UNITS) 201, 202,
14 CONCRETING WORK BLOCK C 203, 204, 9/5/2019 10/5/2019 2DAYS
FIRST 205, 206,
15 LOFT SHUTTRING & FLOOR 11/5/2019 11/5/2019 1DAYS
REINFORCEMENT WORK 207, 209
LOFTS ( OF ALL 8 UNITS)
16 CONCRETING WORK 12/5/2019 12/5/2019 1DAYS

ACCEPTED BY RECEIVED FROM


K GOWDA & CO
KSPH NAGARBHAVI
PLINTH BEAM SCHEDULE

DATE OF REVISED SCHEDULE : 28/07/2018

D BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE

1 PLINTH BEAM OF 4 UNITS 16/07/2018 25/07/2018 10DAYS

2 PLINTH BEAM OF 4 UNITS 26/07/2018 31/07/2018 6DAYS

C BLOCK
SL NO DESCRIPTION NO OF DAYS
STARTING DATE COMPLETION DATE
1 PLINTH BEAM OF 4 UNITS 1/8/2018 4/8/2018 4DAYS

2 PLINTH BEAM OF 4 UNITS 4/8/2018 7/8/2018 4DAYS

THANKING YOU

SCHEDULED BY

K GOWDA & CO. SRI SAI CONSTRUCTIONS