Professional Documents
Culture Documents
Monthly Site Meeting Minutes-17-June 2023
Monthly Site Meeting Minutes-17-June 2023
Monthly Site Meeting Minutes-17-June 2023
Senior Manager
RDA Headquarters
1|Page
SITE MEETING MINUTES
ACTION
BY
DISCUSSION ITEMS WHOM BY WHEN
1 WELCOME REMARKS
1.1 The Regional Manager (RM) welcomed everyone in To Note
attendance of site meeting no. 17 on the project.
The Site Progress Meeting No. 17 was preceded by an
inspection by the Parties to appreciate progress recorded as To Note
well as the outstanding scope. The RM emphasized the
importance of continued progress on this priority project
and stated that the Stakeholders remained committed to
ensuring the successful completion of the Project.
The RM requested attendees to sign the attendance To Note
register. The RM encouraged members to participate
freely in the interest of progress on the project.
1.2 APOLOGIES
Apologies were received on behalf of the RDA-HQ
Agency Project Engineer, Eng. Namalala Chilala and the To Note
Contractor’s Contract Manager, Mr. Zhan Yuting.
1.3 READING AND APPROVAL OF AGENDA
The agenda was tabled, read and approved with the
following changes: To Note
- Inclusion of Sub-Item 3.2: Construction of Bailey
Bridges;
To Note
- Sub-items under Item 3 are to be renumbered
accordingly subsequent to inclusion of the sub-item
above;
- a change under item 3.8 to read “Work plan for March” To Note
in lieu of “Work plan for December” Further, item 3.10
was renumbered to item 3.9.
Subsequent to proposal by SM-C&R and secondment by
the Contractor’s Chief Engineer, the Agenda was
adopted. An Attendance Register, Minutes of the previous
site meeting, Action Matrix, Contractor’s Progress Report
and Programme of Works were circulated.
2|Page
SITE MEETING MINUTES
ACTION
BY
DISCUSSION ITEMS WHOM BY WHEN
3|Page
SITE MEETING MINUTES
ACTION
BY
DISCUSSION ITEMS WHOM BY WHEN
2 MOBILIZATION
2.1 Contractor’s Site Establishment
The Meeting recalled that the laboratory equipment for the June 15,
Engineer’s laboratory had been calibrated and the AVIC 2023
certificates submitted to the RM. The meeting further
recalled that the Contractor was instructed to replace the
compression machine. The meeting noted that this was
outstanding. The Contractor undertook to look into the
matter and provide feedback within a week of the meeting.
4|Page
SITE MEETING MINUTES
ACTION
BY
DISCUSSION ITEMS WHOM BY WHEN
The meeting recalled that the Survey equipment had been To Note
supplied and had been calibrated.
2.4.5 Vehicles
The Contractor informed the meeting that they were in the To Note
process of remobilizing at Mangango Quarry. Nevertheless,
the Contractor assured the meeting that they had sufficient
crushed stone to cover the period until crushing resumed.
The meeting noted that the Contractor had reported on the AVIC Next
available fuel on site. However, the report did not include a Meeting
section on the status of the bailey bridges sub-structure
components. The Contractor was guided to attend to this
without fail.
To Note
However, the Contractor stated that all Luanginga Bridge July 2023
sub-structure components were on site and those for the
Silanda Bridge were enroute from China and would be on
site in the month of July, 2023
5|Page
SITE MEETING MINUTES
3 PHYSICAL PROGRESS
CHAINAGE DISTANCE
WORK
S/No.
ACTIVITY
FROM TO DONE To Note
(Km) (Km) (Km)
Breaking up 15+50
01 0+000 15.5
old road 0
Road bed 15+50 15.5
02 0+000
0
Subgrade 15+50 15.5
03 0+000
0
Subbase 15+50 15.5
04 0+000
0
Base 15+50 15.5
05 0+000
0
Asphalt 15+50 15.5
06 0+000
0
NOTES:
1. This is only for Mongu – Limulunga road and the
Palace road because works on other roads have not yet To Note
commenced.
6|Page
SITE MEETING MINUTES
3.3 Drainage Related Works
The meeting recalled that side drain Works on the section
from Km0+000 to Km0+500 had been carried out.
7|Page
SITE MEETING MINUTES
3.7 Program of Works
The meeting noted that the property owners on the RDA/ June 2023
extension of the Limulunga road to the Jeutine stream may AVIC
need to be engaged.
To Note
The Contractor reported the progress of Work as 95% on
the Mongu Limulunga road and 48% on the entire
approved scope. The meeting noted that progress had been
revised downward from 63% as a result of the additional
scope approved under Addendum No. 5. AVIC June 16,
2023
The Contractor was guided to submit a revised programme
of works indicating the workplan for the additional roads
based on the meetings discussion.
3.8 Projected Cash Flow
The Contractor submitted a cash flow on page 28-29 of
their progress report (refer to Contractor’s report). To Note
8|Page
SITE MEETING MINUTES
4 DESIGN
4.1 Status on Design Drawings
The meeting recalled that RDA had issued its “No
Objection” to the Detailed Drawings for the Luanginga and
Silanda Bridges on October 19, 2022.
4.2 Design
The Meeting noted that there would be need for the AVIC June 2023
Contractor to review the design for the drainage channels
and strucutures.
AVIC June 2023
The Meeting noted that the Contractor would carry out
design of the additional roads approved under Addendum
No. 5 within the month of June 2023.
4.3 Status on Design Report
The Meeting noted that the Contractor would carry out AVIC June 2023
design of the additional roads approved under Addendum
No. 5 within the month of June 2023.
5 FINANCIAL REPORT
9|Page
SITE MEETING MINUTES
5.1 Measurement and Works Certification
10 | P a g e
SITE MEETING MINUTES
The meeting recalled that this had been approved and was
being implemented. The subbase was being stabilized with To Note
5% cement content. The cement being utilized was 32.5
from Sinoma.
The Contractor was guided to enhance the Quality Conrol AVIC Next
section of the report by providing clarity on the sections Meeting
that were tested as well as the description of the headings
on the table of results.
6.4 Status on Asphalt Concrete Mix Design
The meeting recalled that this had been approved and was
being implemented. The Asphalt Concrete had a To Note
binder/aggregate ratio of 4.9 formulated using the Marshal
Mix Method. The bitumen content was 4.7. Further, the
meeting recalled that the Contractor had submitted a copy
of the Ashpalt Mix Design being utilized on Site for
record purposes.
11 | P a g e
SITE MEETING MINUTES
6.5 Calibration of Laboratory and Survey Equipment
12 | P a g e
SITE MEETING MINUTES
8.2 Health Report and HIV/AIDS Awareness
The meeting noted with concern that HIV/AIDS awareness AVIC Next
and prevention campaigns had not bee carried out in Meeting
Kalabo, and were intermittent in Mongu. The Contractor
was instructed to rectify this. The Contractor indicated that
they were addressing the matter and would present a report
during the next site progress meeting.
8.3 Environmental and Social Issues
9 SUBCONTRACTING
13 | P a g e
SITE MEETING MINUTES
10.2 The Employer was happy with the progress on the AVIC ASAP
Mongu Limulunga and Palace roads and encouraged the
Contractor to finalize the ancillary works such as
installation of road signs, road marking, installation of
road studs and construction of speed humps at required
locations.
AVIC Ongoing
10.3The meeting recalled that Vendor Rating had been
carried out on the Project during the month of
November, 2022. The Contractor scored 68.12% and
was encouraged to enhance their strengths and address
the weaknesses so as to improve their performance.
AVIC June 2023
10.4The Meeting recalled that the Contractor was required to
purchase a Site Instruction Book and noted that this
remained outstanding. The Contractor stated that they
were unclear on where it could be purchased from. The
RM guided the Contractor accordingly and the AVIC Next
Contractor undertook to purchase the Site Instruction Meeting
Book within the month of June, 2023.
14 | P a g e
SITE MEETING MINUTES
15 | P a g e
SITE MEETING MINUTES
16 | P a g e