Question # 01

Construction Works should begin ?


A. One week before the official permission from the local authority.
B. After the official permission from local authority.
C. One day before the official permission from local authority.

Question # 02
What is the type of bond guarantees that if contractor goes
broke on a project, the surety will pay the necessary amount to
complete the job ?
A. Bed Bond.
B. Performance Bond.
C. Acceptance Bond
D. Payment Bond

1
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 03
When a T-Beam span over several supports continuously then
the beam at mid span should be designed as ?
A. Simply Supported.
B. Flanged Section.
C. Rectangular Section
D. Pre stressed Beam

Question # 04
Sand drains are used to ?
A. Help in Compacting of Sand Layers.
B. Increase Bearing Capacity of Dry Backfills.
C. Enhance the Permeability of Rock Masses
D. Accelerate the Consolidation Process Decreasing in Soil Volume

2
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 05
A formal CPM analysis for a project shows the planned costs to
date are $ 85,000 and accounting reports charges are $ 85,000
for work value of $ 70,000, the cost and schedule status for the
project are most nearly as?
A. ahead of schedule and over budget.
B. ahead of schedule and under budget.
C. behind schedule and over budget.
D. behind schedule and under budget
Question # 06

3
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 07
Consider the following statements
Entrainment of air in concrete is done so as to ?
1. Increase the workability.
2. Increase the strength.
3. Increase the resistance to freezing and thawing.
Which of the above statements is / are correct – select one :-
A. 1, 2 and 3
B. 1 only
C. 1 and 3 only
D. 3 only

4
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 08
The advantage of a Design and Build contractual arrangement is
(are) ?
A. Reduce project time.
B. Non adversary relationship among participants.
C. Known project cost before construction.
D. All of the above

Question # 09

The main activity in project scope definition is to :


A. Set up the meeting on the project.
B.Analyze the current budget plan.
C.Meet with team members.
D.Select team members.
E. Define the work breakdown structure

5
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 10

Question # 11
If D is the duration, ES and EF are the earliest start and finish, LS
and LF are latest start and latest finish time, then the following
relation holds good
A. EF = ES + D
B. LS = LF – D
C. LF = LS + D
D. D = EF – ES
E. All Above 6
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 12
The goals of a quality management system ?
A. The ability of the product and services to meet customer expectations
can be
understood and evaluated on a continual basis
B. The effectiveness of systematic action can be measured on a regular
basis.
C. The quality of the products or services related to customer needs can
be continuously improved.
D. All the above
Question # 13
Contractor’s claims either extra cost or extra time should be
notice within :-
A. 45 days
B. 21 days
C. 14 days
D. 28 days
7
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 14

What are the main reasons for conducting pull-out tests for
soil nails?
A. To check if there is any slippage or creep occurrence.
B. To check compaction of the soil
C. To measure bearing capacity of the soil
D. All in the above

Question # 15
Increased water – cement ratio {W/C} in concrete mix :-
A. Results in decrease strength
B. Reduce workability
C. Decrease hydration
D. Reduce the slump value

8
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 16
Load path is one of the key considerations in structural design, and it is
about how to bring the load acting on the building
A. to the building façade.
B. to the ground / foundation.
C. to the columns.
D. to the beams
Question # 17

9
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 18

10
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 19

11
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 20
A tower crane with a 7000 Ib Counterweigh {A} is used to pick up {Load} with 15 ft.
boom extension as shown. The boom have weight of 1000 Ib {CG} shown in the figure.
The tower weigh is 3000Ib and the footing {6ft x 6 ft}weighs is 20,000 Ib. The
maximum load that the crane can lift without overturning is most near :

A. 7.50 kips
B. 10.75 kips
C. 13.25 kips
D. 11.00 kips

12
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 21
A precast wall panel 20 ft. long (perpendicular to drawing plane) x 14 ft. high x 4 Inches
thick is being tilted into position using single horizontal cable connected to the top of
the panel as shown in the figure below. The unit weight of the wall is 80 ib/ft³. At the
position showing the tension in the cable (Kips) is most nearly :-

A. 2.2
B. 3.6
C. 5.5
D. 4.8

13
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 22
The maximum moment in the beam is
A. 4200 N m
B. 5600 N m
C. 6400 N m
D. 6800 N m

Question # 23
A. 5 KN
B. 3 KN
C. 7 KN
D. 4 KN

14
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 24

15
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 25

Question # 26

D
16
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # 27

17
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Hands Up !!!!

18
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved
Question # Correct Answer
1 B
2 D
3 B
4 D
5 C
6 A
7 C
Answers 8
9
D
E
10 B
11 E
12 D
13 D
14 A
15 B
16 B
17 C
18 D
19 D
20 D
21 A
22 B
23 A
24 A
25 D
26 D
27 D
19
Green International - India | Kuwait | Qatar www.greenintl.net ©2010-2018 All Rights Reserved

You might also like