8.2SSP HSE Compliance Inspection Done in 26.04.2023
8.2SSP HSE Compliance Inspection Done in 26.04.2023
2023
No Location Picture Remark
1 CH 00 Silt trap is covered up by
excavated material
Action required:
-to remove/ dispose this
material to dumping
ground
-to reactivate the silt trap
2 CH 00
Action required:
To send to PBAPP store
and be documented
Action required:
-to activate
4 CH 00
Unsatisfactory
housekeeping
Action required:
-to clear
5 CH00
6 CH 00
Excavated material
dumped outside site
(beyond hoarding)
Action required:
-to remove/ dispose this
material to dumping
ground
7 CH 00
Missing Hoarding
Action required:
-to reinstate
8 CH00
Cover to rebar
Action required:
-to expedite
9 Near
Petronas
reserve
REMARK:
-this is typical. There
are many cut off piles
along pipe route
especially at river
crossing sites
11 Near Unsatisfactory
Petronas housekeeping
reserve
Action required:
-to clear
12 Near Unsatisfactory
Petronas housekeeping
reserve
Action required:
-to clear
13 PJ 4 Site clearing
-To expedite
14 Mak Sulong To turf
Pump
House
15 Near To turf
Mosque